Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 1.5 | 1.5 | 6.811 | 7.916 | 53% |
40% December - 2020 |
04- Units
Work in progress on all. |
No Image |
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 1.5 | 1.5 | 6.811 | 7.916 | 53% |
40% December - 2020 |
04- Units
Work in progress on all. |
No Image |
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 1.5 | 1.5 | 6.811 | 7.916 | 53% |
40% October - 2020 |
04- Units
Work in progress on all. |
No Image |
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 1.5 | 1.5 | 6.811 | 7.916 | 53% |
40% September - 2020 |
04- Units
Work in progress on all. |
No Image |
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 0 | 0 | 5.311 | 7.916 | 53% |
31% August - 2020 |
04- Units
Work in progress on all. |
No Image |
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.996 | 6.223 | 3.773 | 0 | 0 | 0 | 6.223 | 0 |
July - 2020 |
No Image | ||
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 3.773 | 3.762 | 9.073 | 7.916 | 53% |
53% May - 2021 |
04- Units
1 Completed
2 90% Completed
3 Completed
4 Completed |
No Image |
| |||||||||||||||||||
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 3.773 | 3.762 | 9.073 | 7.916 | 53% |
53% April - 2021 |
04- Units
1 Completed
2 90% Completed
3 Completed
4 Completed |
No Image |
| |||||||||||||||||||
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 3.773 | 3.762 | 9.073 | 7.916 | 53% |
53% March - 2021 |
04- Units
1 Completed
2 90% Completed
3 Completed
4 Completed |
No Image |
| |||||||||||||||||||
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 3.773 | 3.762 | 9.073 | 7.916 | 53% |
53% February - 2021 |
04- Units
1 Completed
2 90% Completed
3 Completed
4 Completed |
No Image |
| |||||||||||||||||||
111 (OG) |
191066-180068 - Construction of Building for Existing CVD/CVC in Sub-Division Tank. [MA] |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17 | 5.311 | 3.773 | 3.773 | 1.5 | 1.5 | 6.811 | 7.916 | 53% |
40% January - 2021 |
04- Units
Work in progress on all. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
Site identification awaited. PC-I/DCE for Rs.224.970 m submitted to XEN Manshera (focal person). |
No Image |
Tehsil Complex at Thana Malakand | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Manshera, Abbottabd, Chitral, Haripur, Kohat, Malakand. Land Identification awaited from SMBR in all districts. |
No Image |
Mansehra | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
- | - | - | 25-09-01 | - | 59.84 | 0 | 0 | 0 | 5 | 0 | 0 | 59.84 | - |
- December - 2017 |
Execution by Admin Deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- November - 2017 |
Execution by Admin Deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- October - 2017 |
Execution by Admin Deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
- | - | - | 25-09-01 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- September - 2017 |
Execution by Admin Deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
- | - | - | - | Line Deptt | 60 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Site/scope of work awaited from Admin Deptt. Execution by Admin Deptt. PC-I submitted by flying club to admin deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
- | - | - | - | Line Deptt | 60 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Site/scope of work awaited from Admin Deptt. Execution by Admin Deptt. PC-I submitted by flying club to admin deptt. |
No Image |
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- June - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- May - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- April - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- March - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- February - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
160616-Strengthening & Capacity Building of Peshawar Flying Club. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.84 | 0 | 0 | 0 | 0 | 0 | 0 | 59.84 | - |
- January - 2018 |
Execution by Admin Deptt. |
No Image |
Peshawar | |||||||||||||||||||
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |
111 (New) |
170643-Construction of Tehsil Complexes in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 7.304 | 7.304 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
XEN Mansehra (focal person). 9 units (in 6 districts) DCE for dev work awaited from Abbottabd, Chitral, Haripur, Kohat, Malakand. |
No Image |