Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 12.5 245.5 0 100% 95%
December - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 12.5 245.5 0 100% 95%
December - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 6 239 0 100% 93%
October - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 6 239 0 100% 93%
September - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 6.5 239.5 0 100% 93%
August - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 0 0 0 233 0 100% 90%
July - 2020
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 25 25 258 0 100% 100%
May - 2021
PC-II: Rs. 10.M on dated: 18-02-13 01-Unit Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 25 25 258 0 100% 100%
April - 2021
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 25 25 258 0 100% 100%
March - 2021
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 25 25 258 0 100% 100%
February - 2021
Finishing in progress.
No Image
Bannu
1147
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 233 25 25 12.5 12.5 245.5 0 100% 95%
January - 2021
Finishing in progress.
No Image
Bannu
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 30-06-18 - 15-09-17 - 150 47.905 101.345 101.345 76.008 35.815 83.72 0.75 100% 56%
December - 2017
Length 5 Km - 3.5 Km completed.
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 150 47.905 101.345 101.345 50.672 35.815 83.72 0.75 100% 56%
September - 2017
Length 5 Km - structure work. WBM on both side in progress.
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 100 47.905 101.345 101.345 50.672 32 79.905 0 100% 80%
August - 2017
Length 5 Km - structure work. WBM on both side in progress. Revised PC-I submitted. Pre-PDWP held.
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 100 47.905 101.345 101.345 35.977 0 47.905 0 100% 48%
July - 2017
Length 5 Km - structure work. WBM on both side in progress. Revised PC-I submitted. Pre-PDWP held.
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 76.008 35.815 83.72 0.75 100% 56%
November - 2017
Length 5 Km - 3.5 Km completed
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 50.672 35.815 83.72 0.75 100% 56%
October - 2017
Length 5 Km - 3.5 Km completed
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 55.209 55.209 55.209 103.114 0.75 100% 69%
June - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Cannot be completed because of the work in progress on the revsied scope of work.
No Image
Dir Upper (5 Km)
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 101.344 55.209 103.114 0.75 100% 69%
May - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Canot be complted because of the work in progress on the revsied scope of work.
No Image
Dir Upper (5 Km)
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 101.344 48.115 96.02 0.75 100% 64%
April - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km.
No Image
Dir Upper (5 Km)
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 76.008 48.115 96.02 0.75 100% 64%
March - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km.
No Image
Dir Upper (5 Km)
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 76.008 35.815 83.72 0.75 100% 56%
February - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km.
No Image
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 76.008 35.815 83.72 0.75 100% 56%
January - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km.
No Image
Pages : 1