Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
01-06-15 | - | - | 11-02-15 | - | 380.856 | 78.814 | 50 | 42.75 | 30.25 | 30.216 | 109.03 | 252.042 | 34% |
29% December - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
01-06-15 | - | - | 11-02-15 | - | 380.856 | 78.814 | 50 | 50 | 17.75 | 17.65 | 96.464 | 252.042 | 34% |
25% September - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
01-06-15 | - | - | 11-02-15 | - | 380.856 | 78.814 | 50 | 50 | 17.75 | 17.75 | 96.564 | 252.042 | 34% |
25% August - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
01-06-15 | - | - | 11-02-15 | - | 380.856 | 78.814 | 50 | 50 | 17.75 | 0 | 78.814 | 252.042 | 34% |
21% July - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 42.75 | 30.25 | 30.216 | 109.03 | 252.042 | 34% |
29% November - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 50 | 30.25 | 17.65 | 96.464 | 252.042 | 34% |
25% October - 2017 |
Length 27 Km - earth work, structure work, sub base, WBM in progress. |
No Image |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 100.433 | 100.433 | 100.433 | 179.247 | 252.042 | 34% |
47% June - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 100.433 | 100.433 | 100.433 | 179.247 | 252.042 | 34% |
47% May - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 100.433 | 100.433 | 100.433 | 179.247 | 252.042 | 34% |
47% April - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 100.433 | 100.433 | 50.399 | 129.213 | 252.042 | 34% |
34% March - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 50.433 | 50.433 | 30.216 | 109.03 | 252.042 | 34% |
29% February - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
ADP's Images |
1150 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 78.814 | 50 | 50.433 | 50.433 | 30.216 | 109.03 | 252.042 | 34% |
29% January - 2018 |
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed. |
No Image |
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar MPD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0 | 0 | 0 | 10.002 | 279.997 | 3% |
3% May - 2021 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar MPD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0 | 0 | 0 | 10.002 | 279.997 | 3% |
3% April - 2021 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% December - 2020 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% December - 2020 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% October - 2020 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% September - 2020 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% August - 2020 |
Procurement stopped till possession of site. Schem |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0 | 0 | 0 | 10.002 | 279.997 | 3% |
3% July - 2020 |
Procurement stopped till possession of site. Schem |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0 | 0 | 0 | 10.002 | 279.997 | 3% |
3% March - 2021 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0 | 0 | 0 | 10.002 | 279.997 | 3% |
3% February - 2021 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
1150 (OG) |
120419-F/S for Master Planning & Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 290 | 10.002 | 0.001 | 0.001 | 0 | 0 | 10.002 | 279.997 | 3% |
3% January - 2021 |
Procurement stopped till possession of site. |
No Image |
Peshawar | |||||||||||||||||||
Pages : 1 |