Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.42 | 4.42 | 4.42 | 1 | 4.458 | 0 | 100% |
100% December - 2020 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.42 | 4.42 | 4.42 | 1 | 4.458 | 0 | 100% |
100% December - 2020 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 0 | 0 | 0 | 0 | 0 | 0 | 2.471 | - |
- October - 2020 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 0 | 0 | 0 | 0 | 0 | 0 | 2.471 | - |
- September - 2020 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.89 | 4.89 | 4.89 | 4.677 | 8.135 | 0 | 100% |
100% May - 2021 |
02- Units
1. Completed
2. AA. Not issued |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.89 | 4.89 | 4.89 | 1 | 4.458 | 0 | 100% |
100% April - 2021 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.89 | 4.89 | 4.89 | 4.677 | 8.135 | 0 | 100% |
100% March - 2021 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.89 | 4.89 | 4.89 | 4.677 | 8.135 | 0 | 100% |
100% February - 2021 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2.471 | 3.458 | 4.42 | 4.42 | 4.42 | 1 | 4.458 | 0 | 100% |
100% January - 2021 |
02-Units
Completed =1 |
No Image |
1) Land for judicial Complex Langra (Pk37)
2) Additional Itmes in the Allied Buildings at PHC Bench Abbottabad. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 2 | 2 | 2 | 2 | 3.25 | 6.65 | 33% |
33% December - 2020 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 2 | 2 | 2 | 2 | 3.25 | 6.65 | 33% |
33% December - 2020 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 10 | 10 | 10 | 6.46 | 7.71 | 0 | 100% |
78% May - 2021 |
01-Unit
Verandha_I Shuttering for roof completed
Verandha_II upto roof level |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 10 | 10 | 10 | 4.946 | 6.196 | 0 | 100% |
63% April - 2021 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 10 | 10 | 10 | 2.904 | 4.154 | 0 | 100% |
42% March - 2021 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 2 | 2 | 2 | 2 | 3.25 | 6.65 | 33% |
33% February - 2021 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 9.8999 | 1.25 | 2 | 2 | 2 | 2 | 3.25 | 6.65 | 33% |
33% January - 2021 |
Fund of Rs: 3 Million demanded |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- October - 2020 |
Completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- September - 2020 |
Completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- August - 2020 |
50% work completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- July - 2020 |
50% work completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 3.458 | 11.827 | 11.827 | 11.827 | 1.869 | 5.327 | 0 | 100% |
100% May - 2021 |
02- Units
1. Completed.
2. 40% work completed |
No Image |
1 Water supply Tube Well in Session Court
2 Over Head Tank | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 3.458 | 11.827 | 11.827 | 11.827 | 1.869 | 5.327 | 0 | 100% |
100% April - 2021 |
02 units
1 Completed.
2 Roof laid |
No Image |
1 Water supply Tube Well in Session Court
2 Over Head Tank | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 3.458 | 3 | 3 | 3 | 0.076 | 3.534 | 0 | 100% |
99% March - 2021 |
02 units
1 Completed.
2 Roof laid |
No Image |
1 Water supply Tube Well in Session Court
2 Over Head Tank | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 3.458 | 2 | 2 | 2 | 0.076 | 3.534 | 0 | 100% |
99% February - 2021 |
02 units
1 Completed.
2 Roof laid |
No Image |
1 Water supply Tube Well in Session Court
2 Over Head Tank | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 3.458 | 2 | 2 | 2 | 0 | 3.458 | 0 | 100% |
97% January - 2021 |
Completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- October - 2020 |
Completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- September - 2020 |
Completed. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- August - 2020 |
Revised scope of work awaited. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- July - 2020 |
Revised scope of work awaited. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.6 | 1.497 | 8.31 | 8.31 | 8.31 | 5.349 | 6.846 | 0.793 | 93% |
65% May - 2021 |
02- Units
1. Completed & H/O
2. Basement RCC wall in progress |
No Image |
1 Court Rooms and Addl Faciltiies in Buner Rs: 3.40 M
2 Const: of Library in Buner Rs: 7.200
Scope of work:
| |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 1.497 | 9.342 | 9.342 | 9.342 | 4.309 | 5.806 | 0 | 100% |
100% April - 2021 |
02- Units
01 Completed
02 Libraray S/Structure in progress |
No Image |
1 Court Rooms and Addl Faciltiies in Buner Rs: 3.40 M
2 Const: of Library in Buner Rs: 7.200 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 1.497 | 9.153 | 9.153 | 9.153 | 4.309 | 5.806 | 0 | 100% |
100% March - 2021 |
02- Units
01 Completed
02 Libraray S/Structure in progress |
No Image |
1 Court Rooms and Addl Faciltiies in Buner Rs: 3.40 M
2 Const: of Library in Buner Rs: 7.200 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 1.497 | 9.153 | 9.153 | 9.153 | 4.309 | 5.806 | 0 | 100% |
100% February - 2021 |
02- Units
01 Completed
02 Libraray S/Structure in progress |
No Image |
1 Court Rooms and Addl Faciltiies in Buner Rs: 3.40 M
2 Const: of Library in Buner Rs: 7.200 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0.994 | 9.153 | 9.153 | 9.153 | 0 | 0.994 | 0 | 100% |
18% January - 2021 |
02- Units
01 Completed
02 Libraray foundation in progress |
No Image |
1 Court Rooms and Addl Faciltiies in Buner
2 Const: of Library in Buner | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 5.55 | 5.11 | 5.11 | 0.555 | 0.555 | 0 | 100% |
28% October - 2020 |
Completed.Funds demnd Rs.22.461 (M) dt,,,04/09/2020 |
No Image |
1) Construction of Motorcycle Shed.
2) Provision of Additoinal & Missing facilities in PHC D.I Khan
3) Constn: of Record Room at PHC D.I Khan Bench.
4) Extension of Bar Roomat PHC D.I Khan Bench | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 1.1 | 1.1 | 1.1 | 0.5 | 0.5 | 0.9 | 55% |
25% September - 2020 |
Completed.Funds demnd Rs.22.461 (M) dt,,,04/09/2020 |
No Image |
1) Construction of Motorcycle Shed.
2) Provision of Additoinal & Missing facilities in PHC D.I Khan
3) Constn: of Record Room at PHC D.I Khan Bench.
4) Extension of Bar Roomat PHC D.I Khan Bench | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | - |
- July - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.733 | 4.39 | 6.803 | 6.803 | 6.803 | 6.53 | 10.92 | 29.54 | 27% |
27% May - 2021 |
04- Units
1- Completed
2- Completed
3- Work not Started
4- Work not Started |
No Image |
1) Construction of Motorcycle Shed. .?.. Rs: 2.00 (TS 1.701)
2) Provision of Additoinal & Missing facilities in PHC D.I Khan .?.. Rs: 9.003 (TS 3.390)
3) Constn: of Record Room at PHC D.I Khan Bench. .?.. Rs: 9.730
4) Extension of Bar Roomat PHC D.I Khan Bench .?.. Rs: 20.00 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.733 | 4.39 | 6.803 | 6.803 | 6.803 | 6.53 | 10.92 | 29.54 | 27% |
27% April - 2021 |
04 units
02 units - completed
02 units - not started
1- Completed
2- Progress
3-work not Started
4- work not Started |
No Image |
1) Construction of Motorcycle Shed. .?.. Rs: 2.00 (TS 1.701)
2) Provision of Additoinal & Missing facilities in PHC D.I Khan .?.. Rs: 9.003 (TS 3.390)
3) Constn: of Record Room at PHC D.I Khan Bench. .?.. Rs: 9.730
4) Extension of Bar Roomat PHC D.I Khan Bench .?.. Rs: 20.00 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.733 | 4.39 | 29.61 | 29.61 | 29.61 | 1.128 | 5.518 | 6.733 | 83% |
14% March - 2021 |
04 units
02 units - completed
02 units - not started
1- Completed
2- Progress
3-work not Started
4- work not Started |
No Image |
1) Construction of Motorcycle Shed. .?.. Rs: 2.00 (TS 1.701)
2) Provision of Additoinal & Missing facilities in PHC D.I Khan .?.. Rs: 9.003 (TS 3.390)
3) Constn: of Record Room at PHC D.I Khan Bench. .?.. Rs: 9.730
4) Extension of Bar Roomat PHC D.I Khan Bench .?.. Rs: 20.00 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.733 | 4.39 | 29.61 | 29.61 | 29.61 | 1.128 | 5.518 | 6.733 | 83% |
14% February - 2021 |
04 units
02 units - completed
02 units - not started
1- Completed
2- Progress
3-work not Started
4- work not Started |
No Image |
1) Construction of Motorcycle Shed. .?.. Rs: 2.00 (TS 1.701)
2) Provision of Additoinal & Missing facilities in PHC D.I Khan .?.. Rs: 9.003 (TS 3.390)
3) Constn: of Record Room at PHC D.I Khan Bench. .?.. Rs: 9.730
4) Extension of Bar Roomat PHC D.I Khan Bench .?.. Rs: 20.00 | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.733 | 4.39 | 4.611 | 4.611 | 4.611 | 2.55 | 6.94 | 31.732 | 22% |
17% January - 2021 |
1- Completed
2- Progress
3 & 4- work Started |
No Image |
1) Construction of Motorcycle Shed.
2) Provision of Additoinal & Missing facilities in PHC D.I Khan
3) Constn: of Record Room at PHC D.I Khan Bench.
4) Extension of Bar Roomat PHC D.I Khan Bench | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
DI.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | - |
- August - 2020 |
Completed.Funds demnd Rs.22.461 (M) dt,,,04/09/2020 |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 1.25 | 2 | 2 | 2 | 1.975 | 3.225 | 0 | - |
- December - 2020 |
Layout given BW in progress. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 1.25 | 2 | 2 | 2 | 1.975 | 3.225 | 0 | - |
- December - 2020 |
Layout given BW in progress. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 2 | 2 | 2 | 0 | 0 | 0 | - |
- October - 2020 |
Layout given BW in progress. |
No Image |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1169 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.668 | 1.25 | 10.318 | 10.318 | 10.318 | 7.36 | 8.61 | 0 | 100% |
100% May - 2021 |
Layout given BW in progress. |
No Image |
Dir Lower | |||||||||||||||||||