Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
10-08-17 | - | - | 03-11-16 | - | 249.995 | 0 | 20 | 17.1 | 12.1 | 12.098 | 12.098 | 229.995 | 8% |
5% December - 2017 |
Length 13 Km - Work in progress (Km-1 to 13). |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
10-08-17 | - | - | 03-11-16 | - | 249.995 | 0 | 20 | 20 | 7.1 | 7.1 | 7.1 | 229.995 | 8% |
3% September - 2017 |
Work in progress (Km-1 to 13) |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
10-08-17 | - | - | 03-11-16 | - | 249.995 | 0 | 20 | 20 | 7.1 | 4.739 | 4.739 | 229.995 | 8% |
2% August - 2017 |
Work in progress (Km-1 to 13) |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
- | - | - | 03-11-16 | - | 249.995 | 0 | 20 | 20 | 7.1 | 0 | 0 | 229.995 | 8% |
- July - 2017 |
Work started. |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 12.1 | 11.581 | 11.581 | 229.995 | 8% |
5% November - 2017 |
Length 13 km - Work in progress (Km-1 to 13). |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 20 | 12.1 | 6.397 | 6.397 | 229.995 | 8% |
3% October - 2017 |
Work in progress (Km-1 to 13). |
No Image |
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 17.1 | 16.598 | 16.598 | 229.995 | 8% |
7% June - 2018 |
Length 13 Km (width 18 ft ) - work in progress (Km-7 to 13). Km 1-6 not started due to CPEC usage. Bridge - 40 m - left abutment work in progress. |
No Image |
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar | |||||||||||||||||||
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 17.1 | 16.598 | 16.598 | 229.995 | 8% |
7% May - 2018 |
Length 13 Km (width 18 ft ) - work in progress (Km-7 to 13). Km 1-6 not started due to CPEC usage. Bridge - 40 m - left abutment work in progress. Rs.60 m demanded to clear liabilities. |
No Image |
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar | |||||||||||||||||||
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 17.1 | 12.098 | 12.098 | 229.995 | 8% |
5% April - 2018 |
Length 13 Km (width 18 ft ) - work in progress (Km-7 to 13). Km 1-6 not started due to CPEC usage. Bridge - 40 m - left abutment work in progress. Rs.60 m demanded to clear liabilities. |
No Image |
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar | |||||||||||||||||||
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 12.1 | 12.098 | 12.098 | 229.995 | 8% |
5% March - 2018 |
Length 13 Km (width 18 ft ) - work in progress (Km-7 to 13).
Km 1-6 not started due to CPEC usage
Bridge - 40 m - left abutment Work in progress. |
No Image |
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar | |||||||||||||||||||
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 12.1 | 12.098 | 12.098 | 229.995 | 8% |
5% February - 2018 |
Length 13 Km (width 18 ft ) - Work in progress (Km-7 to 13).
KM 1-6 not stated due to CPEC usage
Bridge - 40 m - left abutment Work in progress. |
ADP's Images |
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar | |||||||||||||||||||
1174 (OG) |
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.995 | 0 | 20 | 17.1 | 12.1 | 12.098 | 12.098 | 229.995 | 8% |
5% January - 2018 |
Length 13 Km - Work in progress (Km-1 to 13). |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Scheme has benn principally approved |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
Scheme has benn principally approved |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
DCE submitted. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
DCE submitted. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
DCE submitted. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
DCE submitted. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
Pre PDWP held. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
Procurement under process. |
No Image |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1174 (New) |
200265-Construction of 07 District Judicial Complexes (AIP) |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
Pages : 1 2 |