Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 446 59.75 36.148 21.211 21.211 467.211 823.766 38% 35%
December - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1329.516 446 59.75 36.148 21.211 21.211 467.211 823.766 38% 35%
November - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1329.516 446 59.75 59.75 21.211 21.211 467.211 823.766 38% 35%
October - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 446 59.75 59.75 21.211 21.211 467.211 823.766 38% 35%
September - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Dualization / Rehabilitation of road from Gulshan Abad Chowk to Jerma Bridge via Hangu Pattak (11.5 Km) District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 446 59.75 59.75 21.211 21.211 467.211 823.766 38% 35%
August - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Dualization / Rehabilitation of road from Gulshan Abad Chowk to Jerma Bridge via Hangu Pattak (11.5 Km) District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 446 59.75 59.75 21.211 0 446 823.766 38% 34%
July - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 36.148 36.148 36.148 482.148 897.733 36% 34%
June - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 59.75 36.148 36.148 482.148 897.733 36% 34%
May - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 59.75 36.148 36.148 482.148 897.733 36% 34%
April - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 59.75 21.211 21.211 467.211 897.733 36% 33%
March - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 59.75 21.211 21.211 467.211 897.733 36% 33%
February - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1329.516 446 59.75 36.148 21.211 21.211 467.211 823.766 38% 35%
January - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak) 2) Package-2 (Hangu Phatak to Saif CNG) 3) Package-3 (Saif CNG to Jerma Bridge Start Point) 4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
December - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
December - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
October - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
September - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
August - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 0 0 0 0 0 -
July - 2020
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
May - 2021
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
April - 2021
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
March - 2021
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
February - 2021
No Image
1265
(New)
191654-190311 - PCC Link Roads & Drinking Water Supply Schemes in Sub Division Tank [MA]
Tank
30-11--1 30-11--1 - 30-11--1 Line Deptt 25 0 25 25 0 0 0 0 - -
January - 2021
No Image
Pages : 1