Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
- | - | - | 02-03-17 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% December - 2017 |
Work started. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
- | - | - | 02-03-17 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- September - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
- | - | - | 02-03-17 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- August - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
- | - | - | 02-03-17 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- July - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- November - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 0 | 0 | 0 | 0 | 0 | 81.5 | - |
- October - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.48 | 2.48 | 2.48 | 2.48 | 2.48 | 79.02 | 3% |
3% June - 2018 |
Earth work completed. Drain work in progress. |
No Image |
1) Rehabilitation of Civil Station roads (16 Km)
2) Rehabilitation of PCC roads in UC Kakul (5 Km)
3) Abbottabad Thandial road / bridge work (25 Km)
4) Rehabilitation of Dhodial road / bridge (3 Km)
5) Rehabilitation of Malkot link road (0.5 Km)
6) Rehabilitation of Qalandarabad to Tarnawal road (10 Km)
7) Todo Maira road (7 Km)
8) Rehabilitation of Lodhi Abad to Bandi Dhundan road (5 Km)
9) Baghdara road (3 Km)
10) Rehabilitation of Kokal Barseen road (12 Km)
11) Rehabilitation of Samsaiser road (2 Km)
12) Rehabilitation of Manna Karimabad road (3 Km)
13) Rehabilitation of Loon Pattian road (2 Km)
14) Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30 Km)
15) Rehabilitation of Forest Barrier to Shah Di Gali road (8 Km)
16) Rehabilitation of Rajoya road (5 Km)
17) Chanmari Tajwal road (5.50 Km)
18) Maira Roomal road (3 Km)
19) Nelol Sandan road (1 Km)
20) Toheedabad Passala road (4 Km)
21) Lora Swargali road (29 Km)
22) Ratti Gali Lower Barrian road (3 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% May - 2018 |
Earth work completed. Drain work in progress. |
No Image |
1) Rehabilitation of Civil Station roads (16 Km)
2) Rehabilitation of PCC roads in UC Kakul (5 Km)
3) Abbottabad Thandial road / bridge work (25 Km)
4) Rehabilitation of Dhodial road / bridge (3 Km)
5) Rehabilitation of Malkot link road (0.5 Km)
6) Rehabilitation of Qalandarabad to Tarnawal road (10 Km)
7) Todo Maira road (7 Km)
8) Rehabilitation of Lodhi Abad to Bandi Dhundan road (5 Km)
9) Baghdara road (3 Km)
10) Rehabilitation of Kokal Barseen road (12 Km)
11) Rehabilitation of Samsaiser road (2 Km)
12) Rehabilitation of Manna Karimabad road (3 Km)
13) Rehabilitation of Loon Pattian road (2 Km)
14) Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30 Km)
15) Rehabilitation of Forest Barrier to Shah Di Gali road (8 Km)
16) Rehabilitation of Rajoya road (5 Km)
17) Chanmari Tajwal road (5.50 Km)
18) Maira Roomal road (3 Km)
19) Nelol Sandan road (1 Km)
20) Toheedabad Passala road (4 Km)
21) Lora Swargali road (29 Km)
22) Ratti Gali Lower Barrian road (3 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% April - 2018 |
Earth work completed. Drain work in progress. |
No Image |
1) Rehabilitation of Civil Station roads (16 Km)
2) Rehabilitation of PCC roads in UC Kakul (5 Km)
3) Abbottabad Thandial road / bridge work (25 Km)
4) Rehabilitation of Dhodial road / bridge (3 Km)
5) Rehabilitation of Malkot link road (0.5 Km)
6) Rehabilitation of Qalandarabad to Tarnawal road (10 Km)
7) Todo Maira road (7 Km)
8) Rehabilitation of Lodhi Abad to Bandi Dhundan road (5 Km)
9) Baghdara road (3 Km)
10) Rehabilitation of Kokal Barseen road (12 Km)
11) Rehabilitation of Samsaiser road (2 Km)
12) Rehabilitation of Manna Karimabad road (3 Km)
13) Rehabilitation of Loon Pattian road (2 Km)
14) Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30 Km)
15) Rehabilitation of Forest Barrier to Shah Di Gali road (8 Km)
16) Rehabilitation of Rajoya road (5 Km)
17) Chanmari Tajwal road (5.50 Km)
18) Maira Roomal road (3 Km)
19) Nelol Sandan road (1 Km)
20) Toheedabad Passala road (4 Km)
21) Lora Swargali road (29 Km)
22) Ratti Gali Lower Barrian road (3 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% March - 2018 |
Earth work completed. Drain work in progress. |
No Image |
1) Rehabilitation of Civil Station roads (16 Km)
2) Rehabilitation of PCC roads in UC Kakul (5 Km)
3) Abbottabad Thandial road / bridge work (25 Km)
4) Rehabilitation of Dhodial road / bridge (3 Km)
5) Rehabilitation of Malkot link road (0.5 Km)
6) Rehabilitation of Qalandarabad to Tarnawal road (10 Km)
7) Todo Maira road (7 Km)
8) Rehabilitation of Lodhi Abad to Bandi Dhundan road (5 Km)
9) Baghdara road (3 Km)
10) Rehabilitation of Kokal Barseen road (12 Km)
11) Rehabilitation of Samsaiser road (2 Km)
12) Rehabilitation of Manna Karimabad road (3 Km)
13) Rehabilitation of Loon Pattian road (2 Km)
14) Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30 Km)
15) Rehabilitation of Forest Barrier to Shah Di Gali road (8 Km)
16) Rehabilitation of Rajoya road (5 Km)
17) Chanmari Tajwal road (5.50 Km)
18) Maira Roomal road (3 Km)
19) Nelol Sandan road (1 Km)
20) Toheedabad Passala road (4 Km)
21) Lora Swargali road (29 Km)
22) Ratti Gali Lower Barrian road (3 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% February - 2018 |
Work started. |
No Image |
1) Rehabilitation of Civil Station roads (16 Km)
2) Rehabilitation of PCC roads in UC Kakul (5 Km)
3) Abbottabad Thandial road / bridge work (25 Km)
4) Rehabilitation of Dhodial road / bridge (3 Km)
5) Rehabilitation of Malkot link road (0.5 Km)
6) Rehabilitation of Qalandarabad to Tarnawal road (10 Km)
7) Todo Maira road (7 Km)
8) Rehabilitation of Lodhi Abad to Bandi Dhundan road (5 Km)
9) Baghdara road (3 Km)
10) Rehabilitation of Kokal Barseen road (12 Km)
11) Rehabilitation of Samsaiser road (2 Km)
12) Rehabilitation of Manna Karimabad road (3 Km)
13) Rehabilitation of Loon Pattian road (2 Km)
14) Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30 Km)
15) Rehabilitation of Forest Barrier to Shah Di Gali road (8 Km)
16) Rehabilitation of Rajoya road (5 Km)
17) Chanmari Tajwal road (5.50 Km)
18) Maira Roomal road (3 Km)
19) Nelol Sandan road (1 Km)
20) Toheedabad Passala road (4 Km)
21) Lora Swargali road (29 Km)
22) Ratti Gali Lower Barrian road (3 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.5 | 0 | 2.5 | 2.5 | 2.5 | 2.48 | 2.48 | 79 | 3% |
3% January - 2018 |
Work started. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
- | - | - | 02-03-17 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% December - 2017 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
- | - | - | 02-03-17 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- September - 2017 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
- | - | - | 02-03-17 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- August - 2017 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
- | - | - | 02-03-17 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- July - 2017 |
Work started (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% November - 2017 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | - |
- October - 2017 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% June - 2018 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% May - 2018 |
Work in progress (3 units). Rs.40 m demanded to clear liabilities. |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% April - 2018 |
Work in progress (3 units). Rs.40 m demanded to clear liabilities. |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% March - 2018 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% February - 2018 |
Work in progress (3 units). |
ADP's Images |
1) Sujbiar Kandow road (9 Km)
2) Battagram Shamlai Hill road (17 Km)
3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 0 | 3.5 | 3.5 | 3.5 | 3.5 | 3.5 | 46.5 | 7% |
7% January - 2018 |
Work in progress (3 units). |
No Image |
1) Sujbiar Kandow road (9 Km) 2) Battagram Shamlai Hill road (17 Km) 3) Kuza Banda Chattarplain road (25 Km) | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
- | - | - | 02-03-17 | - | 65.51 | 0 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 56.01 | 15% |
15% December - 2017 |
Test pile completed. 2 Nos girders casted. |
No Image |
RCC Bridge at Khost Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
- | - | - | 02-03-17 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- September - 2017 |
Work started. Land acquisition under process. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
- | - | - | 02-03-17 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- August - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
- | - | - | 02-03-17 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- July - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- November - 2017 |
Excavation of abutment in progress. |
No Image |
RCC Bridge at Khost Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 0 | 0 | 0 | 0 | 0 | 65.51 | - |
- October - 2017 |
Excavation of abutment in progress. |
No Image |
RCC Bridge at Khost Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 56.01 | 15% |
15% June - 2018 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier shaft, 8/8 girders completed. |
No Image |
Construction of RCC Bridge at Kosht (55 m), Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 10.5 | 10.5 | 10.5 | 9.5 | 9.5 | 55.01 | 16% |
15% May - 2018 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier shaft, 8/8 girders completed. |
No Image |
Construction of RCC Bridge at Kosht (55 m), Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 10.5 | 10.5 | 10.5 | 9.5 | 9.5 | 55.01 | 16% |
15% April - 2018 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier shaft, 8/8 girders completed. |
No Image |
Construction of RCC Bridge at Kosht (55 m), Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 56.01 | 15% |
15% March - 2018 |
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier shaft, 8/8 girders completed. |
No Image |
Construction of RCC Bridge at Kosht (55 m), Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 56.01 | 15% |
15% February - 2018 |
RCC bride 60 m - 24/24 piles, 2/3 pile cap, 2/3 pier shaft, 8/8 girders completed |
No Image |
RCC Bridge at Khost Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 65.51 | 0 | 9.5 | 9.5 | 9.5 | 9.5 | 9.5 | 56.01 | 15% |
15% January - 2018 |
Test pile completed. 2 Nos girders casted. |
No Image |
RCC Bridge at Khost Upper Chitral | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
- | - | - | 02-03-17 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- December - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
- | - | - | 02-03-17 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- September - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
- | - | - | 02-03-17 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- August - 2017 |
Tender approval under process. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
- | - | - | 02-03-17 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- July - 2017 |
Tender approval under process. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- November - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 0 | 0 | 0 | 0 | 0 | 114.161 | - |
- October - 2017 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 1.007 | 1.007 | 1.007 | 1.007 | 1.007 | 113.154 | 1% |
1% June - 2018 |
Work started. |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjkora Dir Lower | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 3 | 3 | 3 | 1.007 | 1.007 | 111.161 | 3% |
1% May - 2018 |
Work started. |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjkora Dir Lower | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 3 | 3 | 3 | 0.8 | 0.8 | 111.161 | 3% |
1% April - 2018 |
Work started. |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjkora Dir Lower | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 3 | 3 | 3 | 0.8 | 0.8 | 111.161 | 3% |
1% March - 2018 |
Work started. |
No Image |
1) Restoration/reconstruction of Shalfalam Bridge on River Panjkora Dir Lower | |||||||||||||||||||
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 3 | 3 | 3 | 0.8 | 0.8 | 111.161 | 3% |
1% February - 2018 |
Work started. |
ADP's Images |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.161 | 0 | 3 | 3 | 3 | 0.8 | 0.8 | 111.161 | 3% |
1% January - 2018 |
Work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Upper |
- | - | - | 02-03-17 | - | 80.103 | 0 | 0 | 0 | 0 | 0 | 0 | 80.103 | - |
- December - 2017 |
Khall Kozkaly road PK-93, Garawonai road PK-91 - work started. Suspension bridge Sahib Abad - work order issued. |
No Image |
1308 (OG) |
160498-Provision for Rehabilitaiton of flood / torrential Affected Roads & Bridges (SDG). |
Dir Upper |
- | - | - | 02-03-17 | - | 80.103 | 0 | 0 | 0 | 0 | 0 | 0 | 80.103 | - |
- September - 2017 |
Khall Kozkaly road PK-93, Garawonai road PK-91 - work started. Suspension bridge Sahib Abad - work order issued. |
No Image |
Pages : 1 2 3 4 |