Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2018, February - 2021, March - 2018, March - 2021, April - 2018, April - 2021, May - 2018, May - 2021, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 7

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
- - - 16-10-17 - 36.386 15 9 9 9 0 15 12.386 66% 41%
December - 2017
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work order will be issued in week.
No Image
1) Havelian
2) PG at Mandian … AA cost Rs.4.852 m
3) Tehsil level PG at Dhamtour … AA cost Rs.16.534 m dated 20/10/2017
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
- - - 19-11-14 - 24.801 15 4 4 4 0 15 5.801 77% 60%
September - 2017
Completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site) and Dhamtour. Sites not yet H/O.
No Image
1) Havelian
2) PG at Mandian … AA cost Rs.4.852 m
3) PG at Dhamtour … AA cost Rs.4.949 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
- - - 19-11-14 - 24.801 15 4 4 4 0 15 5.801 77% 60%
August - 2017
Completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site) and Dhamtour. Sites not yet H/O.
No Image
1) Havelian
2) PG at Mandian … AA cost Rs.4.852 m
3) PG at Dhamtour … AA cost Rs.4.949 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
- - - 19-11-14 - 24.801 15 0 0 0 0 15 9.801 - 60%
July - 2017
Completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site) and Dhamtour. Sites not yet H/O.
No Image
1) Havelian
2) PG at Mandian … AA cost Rs.4.852 m
3) PG at Dhamtour … AA cost Rs.4.949 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 4 4 4 0 15 17.386 52% 41%
November - 2017
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - sites not yet H/O.
No Image
1) Havelian
2) PG at Mandian ? AA cost Rs.4.852 m
3) Tehsil level PG at Dhamtour ? AA cost Rs.16.534 m dated 20/10/2017
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 4 4 4 0 15 17.386 52% 41%
October - 2017
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - sites not yet H/O.
No Image
1) Havelian
2) PG at Mandian ? AA cost Rs.4.852 m
3) Tehsil level PG at Dhamtour ? AA cost Rs.16.534 m dated 20/10/2017
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 9 24 12.386 66% 66%
June - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started.
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 6.648 21.648 12.386 66% 59%
May - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started.
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 6.648 21.648 12.386 66% 59%
April - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started.
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 4.316 19.316 12.386 66% 53%
March - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 0 15 12.386 66% 41%
February - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 36.386 15 9 9 9 0 15 12.386 66% 41%
January - 2018
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - revised on new site work started
No Image
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level)
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
15-01-17 - - 28-01-16 - 45 16 14 14 14 14 30 15 67% 67%
December - 2017
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai … AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
- - - 28-01-16 - 45 16 14 14 14 5.8 21.8 15 67% 48%
September - 2017
Completed & H/O (Domel). Pavilian upto lintel level, BW in preogress, site dispute resolved. (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai … AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
- - - 28-01-16 - 45 16 14 14 14 5.8 21.8 15 67% 48%
August - 2017
Completed & H/O (Domel). Foundation plinth in progress, site dispute resolved. Work started (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai … AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
- - - 28-01-16 - 45 16 0 0 0 0 16 29 - 36%
July - 2017
Completed & H/O (Domel). Foundation plinth in progress, site dispute resolved. Work started (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai … AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 45 16 14 14 14 9.423 25.423 15 67% 56%
November - 2017
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 45 16 14 14 14 9.423 25.423 15 67% 56%
October - 2017
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute resolved (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 16 14 14 14 14 30 52.286 36% 36%
June - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 16 14 14 14 14 30 52.286 36% 36%
May - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 16 14 14 14 14 30 52.286 36% 36%
April - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 16 14 14 14 14 30 52.286 36% 36%
March - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 82.286 16 14 14 14 14 30 52.286 36% 36%
February - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 45 16 14 14 14 14 30 15 67% 67%
January - 2018
Completed & H/O (Domel). Pavilian - roof laid, BW in progress, site dispute (Lalozai).
No Image
1) PG at Domel 2) PG at Lalozai ? AA cost Rs.15 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
20-04-15 - - 28-01-16 - 30 15 0 0 0 0 15 15 - 50%
December - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
20-04-15 - - 28-01-16 - 30 15 0 0 0 0 15 15 - 50%
September - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
20-04-15 - - 28-01-16 - 30 15 0 0 0 0 15 15 - 50%
August - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
20-04-15 - - 28-01-16 - 30 15 0 0 0 0 15 15 - 50%
July - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
November - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
October - 2017
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
June - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
May - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
April - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
March - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
February - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram
2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Battagram
30-11--1 30-11--1 - 30-11--1 - 30 15 0 0 0 0 15 15 - 50%
January - 2018
PG Battagram - land not yet handed over. PG Allai - completed & H/O.
No Image
1) Battagram 2) Allai
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
23-01-17 - - 19-11-14 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
December - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra … AA cost Rs.14.632 m
4) PG at GDC Daggar … AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
23-01-17 - - 19-11-14 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
September - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued- site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra … AA cost Rs.14.632 m
4) PG at GDC Daggar … AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
23-01-17 - - 19-11-14 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
August - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued- site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra … AA cost Rs.14.632 m
4) PG at GDC Daggar … AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
- - - 19-11-14 - 59.264 14.054 0 0 0 0 14.054 45.21 - 24%
July - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued- site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra … AA cost Rs.14.632 m
4) PG at GDC Daggar … AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
November - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra ? AA cost Rs.14.632 m
4) PG at GDC Daggar ? AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
October - 2017
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra ? AA cost Rs.14.632 m
4) PG at GDC Daggar ? AA cost Rs.14.146 m
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 0.258 0.258 0.258 0.258 14.312 44.952 24% 24%
June - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0.258 14.312 19.21 68% 24%
May - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
April - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
March - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
February - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Buner
30-11--1 30-11--1 - 30-11--1 - 59.264 14.054 26 26 26 0 14.054 19.21 68% 24%
January - 2018
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progres (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement.
No Image
1) PG Khadukhail 2) PG Mandanr 3) PG at GHS Gagra ? AA cost Rs.14.632 m 4) PG at GDC Daggar ? AA cost Rs.14.146 m 5) Tehsil level PG at Gagra Buner ? AA cost Rs.53.138 m dated 17/01/2018
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Charsadda
19-06-15 - - 19-11-14 - 45 43.05 0 0 0 0 43.05 1.95 - 96%
December - 2017
Completed & H/O (4 units).
No Image
1) Tangi
2) Shabqadar
3) Turangzai
4) Muslim Abad … AA cost Rs.2.703 m dated 02/09/2016
1376
(OG)
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis.
Charsadda
19-06-15 - - 19-11-14 - 45 43.05 0 0 0 0 43.05 1.95 - 96%
September - 2017
Completed & H/O (4 units).
No Image
1) Tangi
2) Shabqadar
3) Turangzai
4) Muslim Abad … AA cost Rs.2.703 m dated 02/09/2016
Pages : 1 2 3 4 5 6 7