Progressive Review for the month(s) of : January - 2018, January - 2021, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2017, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
December - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
December - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
October - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
September - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
August - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 -
July - 2020
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
May - 2021
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
April - 2021
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
March - 2021
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
February - 2021
No Image
1388
(OG)
191698-100207-Project Management Unit for World Food Programme in FATA. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 42.135 21.492 0 0 0 0 21.492 0 - -
January - 2021
No Image
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
- 30-06-18 - 16-10-17 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
December - 2017
1 Work order issued. 2 Under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
- 30-06-18 - 16-10-14 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
September - 2017
Land acquisition under process. Tender approval under process.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
- 30-06-18 - 16-10-14 - 35.1 3.906 12.5 12.5 0 0 3.906 18.694 47% 11%
August - 2017
Land acquisition under process. Tender approval under process.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
- 30-06-18 - 16-10-14 - 35.1 3.906 12.5 12.5 0 0 3.906 18.694 47% 11%
July - 2017
Land acquisition under process. Tender approval under process.
No Image
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
November - 2017
Land acquisition under process. Tender approval under process.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
October - 2017
Land acquisition under process. Tender approval under process.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 0 0 3.906 33.594 33% 8%
June - 2018
1 Work order issued. 2 under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
May - 2018
1 Work order issued. 2 under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
April - 2018
1 Work order issued. 2 under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
March - 2018
1 Work order issued. 2 under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
February - 2018
1 Work order issued. 2 Under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I
2) Picnic Spot at Malam Jabba-II
3) Picnic Spot at Seer
1388
(OG)
140036-Establishment of Picnic Spots at Suitable Places in Malam Jaba, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 50 3.906 12.5 12.5 6.25 0 3.906 33.594 33% 8%
January - 2018
1 Work order issued. 2 Under process, work order in 2 weeks. Land acquisition under process. Tender approval under process. Site not available.
No Image
1) Picnic Spot at Malam Jabba-I 2) Picnic Spot at Malam Jabba-II 3) Picnic Spot at Seer
Pages : 1