Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.03 | 16.03 | 0 | 0 | 0 | 0 | 16.03 | 0 | - |
100% September - 2018 |
Work order issued (1 unit). |
No Image |
1) GGHS Birot PK-45
2) GGHS Bakot | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 16.03 | 16.03 | 0 | 0 | 0 | 0 | 16.03 | 0 | - |
100% July - 2018 |
Work order issued (1 unit). |
No Image |
1) GGHS Birot PK-45
2) GGHS Bakot | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% December - 2020 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% December - 2020 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 0 | 0 | 0 | 0 | 0 | 0 | 136.452 | - |
- October - 2020 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.818 | 1.508 | 0 | 0 | 0 | 0 | 1.508 | 4.31 | - |
26% September - 2018 |
Completed. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 0 | 0 | 0 | 0 | 0 | 0 | 136.452 | - |
- September - 2020 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 0 | 0 | 0 | 0 | 0 | 0 | 136.452 | - |
- August - 2020 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.818 | 1.508 | 0 | 0 | 0 | 0 | 1.508 | 4.31 | - |
26% July - 2018 |
Completed. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 0 | 0 | 0 | 0 | 0 | 0 | 136.452 | - |
- July - 2020 |
Work order issued on 16/03/2018. Mutation of land/ |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% May - 2021 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Scope of work:
| |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% April - 2021 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% March - 2021 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% February - 2021 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 136.452 | 10.076 | 0 | 0 | 0 | 0 | 10.076 | 126.376 | - |
7% January - 2021 |
Tehsil Bakka Khel _ site Disputed
Sub Tehsil Sardi Khel - In progress. |
No Image |
Bannu | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- December - 2020 |
Work order issued.
Land not yet identified (20-22 Kanal) |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- December - 2020 |
Work order issued.
Land not yet identified (20-22 Kanal) |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- October - 2020 |
Work order issued.
Land not yet identified (20-22 Kanal) |
No Image |
Construction of Tehsil Building Shabqaddar PK | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- September - 2020 |
Work order issued.
Land not yet identified (20-22 Kanal) |
No Image |
Construction of Tehsil Building Shabqaddar PK | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- August - 2020 |
Work order issued. Land not yet identified. |
No Image |
Construction of Tehsil Building Shabqaddar PK | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- July - 2020 |
Work order issued. Land not yet identified. |
No Image |
Construction of Tehsil Building Shabqaddar PK | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- May - 2021 |
Rs: 20 M approved for Land acquisation Section -IV issued |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- April - 2021 |
Rs: 20 M approved for Land acquisation Section -IV issued |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- March - 2021 |
Rs: 20 M approved for Land acquisation Section -IV issued |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- February - 2021 |
Rs: 20 M approved for Land acquisation Section -IV issued |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.45 | 0 | 0 | 0 | 0 | 0 | 0 | 103.45 | - |
- January - 2021 |
Rs: 20 M approved for Land acquisation Section -IV under process |
No Image |
Construction of Tehsil Building Shabqaddar PK-60 | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.19 | 0 | 0 | 0 | 0 | 0 | 0 | 1.19 | - |
- September - 2018 |
Physically completed, contractor liabilities yet to be paid. |
No Image |
Chitral | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.19 | 0 | 0 | 0 | 0 | 0 | 0 | 1.19 | - |
- July - 2018 |
Physically completed, contractor liabilities yet to be paid. |
No Image |
Chitral | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.616 | 10.301 | 0 | 0 | 0 | 0 | 10.301 | 2.315 | - |
82% September - 2018 |
Completed & H/O (2 units). |
No Image |
1) GMPS Wanda Kokar shifted to GMPS Basti Lal Kat PK-65
2) GPS Basti Mahir shifted to GPS Adda Himat PK-64 | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.616 | 10.301 | 0 | 0 | 0 | 0 | 10.301 | 2.315 | - |
82% July - 2018 |
Completed & H/O (2 units). |
No Image |
1) GMPS Wanda Kokar shifted to GMPS Basti Lal Kat PK-65
2) GPS Basti Mahir shifted to GPS Adda Himat PK-64 | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 39.707 | 36.002 | 0 | 0 | 0 | 0 | 36.002 | 3.705 | - |
91% September - 2018 |
Completed & H/O (3 units). |
No Image |
1) Cluster Hostel in Dir Lower--- Rs.18 m
2) GGHS Lajbook PK-96 --- Rs.12.914 m
3) GGHS Moranai PK-96 | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 39.707 | 36.002 | 0 | 0 | 0 | 0 | 36.002 | 3.705 | - |
91% July - 2018 |
Completed & H/O (3 units). |
No Image |
1) Cluster Hostel in Dir Lower--- Rs.18 m
2) GGHS Lajbook PK-96 --- Rs.12.914 m
3) GGHS Moranai PK-96 | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.972 | 11.673 | 0 | 0 | 0 | 0 | 11.673 | 0 | - |
100% September - 2018 |
Out of 3 units, 2 completed, 1 site dispute (GGMS Doaba). |
No Image |
1) GMS Shamal Din Karbogha PK-43
2) GGPS Sial Talab
3) GGMS Doaba | |||||||||||||||||||
183 (OG) |
140204-Continuation of ongoing ADP schemes for completion in 2014-15. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.972 | 11.673 | 0 | 0 | 0 | 0 | 11.673 | 0 | - |
100% July - 2018 |
Out of 3 units, 2 completed, 1 site dispute (GGMS Doaba). |
No Image |
1) GMS Shamal Din Karbogha PK-43
2) GGPS Sial Talab
3) GGMS Doaba | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 0 | 0 | 0 | 0 | 35.5 | 54.946 | - |
39% December - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 0 | 0 | 0 | 0 | 35.5 | 54.946 | - |
39% December - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 0 | 0 | 0 | 0 | 0 | 0 | 90.446 | - |
- October - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 0 | 0 | 0 | 0 | 0 | 0 | 90.446 | - |
- September - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 0 | 0 | 0 | 0 | 0 | 0 | 90.446 | - |
- August - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 0 | 0 | 0 | 0 | 0 | 0 | 90.446 | - |
- July - 2020 |
GF/FF SS in progress.
Demand 20 m for tempo |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 2.5 | 2.5 | 2.5 | 2.5 | 38 | 52.446 | 42% |
42% May - 2021 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 2.5 | 2.5 | 2.5 | 2.5 | 38 | 52.446 | 42% |
42% April - 2021 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 2.5 | 2.5 | 2.5 | 2.5 | 38 | 52.446 | 42% |
42% March - 2021 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 2.5 | 2.5 | 2.5 | 2.5 | 38 | 52.446 | 42% |
42% February - 2021 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90.446 | 35.5 | 0 | 0 | 0 | 0 | 35.5 | 54.946 | - |
39% January - 2021 |
GF/FF SS in progress.
Demand 20 m for tempo of Work |
No Image |
Haripur | |||||||||||||||||||
183 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 50 | 141.496 | 141.496 | 123.624 | 123.624 | 173.624 | 585.749 | 25% |
22% December - 2018 |
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
183 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 50 | 141.496 | 141.496 | 100.748 | 99.848 | 149.848 | 585.749 | 25% |
19% November - 2018 |
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
183 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 50 | 141.496 | 141.496 | 100.748 | 99.848 | 149.848 | 585.749 | 25% |
19% November - 2018 |
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
183 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 50 | 141.496 | 190.974 | 190.974 | 190.974 | 240.974 | 585.749 | 25% |
31% April - 2019 |
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
183 (OG) |
110441-Establishment of Cadet College in Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 777.245 | 50 | 141.496 | 186.496 | 186.496 | 186.496 | 236.496 | 585.749 | 25% |
30% March - 2019 |
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress. |
No Image |
Cadet College Lakki Marwat | |||||||||||||||||||
Pages : 1 2 |