Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 15.267 15.267 10.267 18.267 0 100% 70%
May - 2021
Complted . Delete from drfat ADP
No Image
Const: of B/T Road from aragai Abdul Khel via to Lakari Sarorogha 2-KM
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 15.267 15.267 10.267 18.267 0 100% 70%
April - 2021
Complted . Delete from drfat ADP
No Image
Const: of B/T Road from aragai Abdul Khel via to Lakari Sarorogha 2-KM
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 18.18 10.267 10.267 18.267 0 100% 70%
December - 2020
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 18.18 10.267 10.267 18.267 0 100% 70%
December - 2020
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 18.18 6 6 14 0 100% 53%
October - 2020
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 18.18 6 6 14 0 100% 53%
September - 2020
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 18.18 6 0 8 0 100% 31%
August - 2020
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 0 0 0 8 0
July - 2020
No Image
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 15.267 15.267 10.267 18.267 0 100% 70%
March - 2021
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
Const: of B/T Road from aragai Abdul Khel via to Lakari Sarorogha 2-KM
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 15.267 15.267 10.267 18.267 0 100% 70%
February - 2021
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image
Const: of B/T Road from aragai Abdul Khel via to Lakari Sarorogha 2-KM
1862
(OG)
191793-180225 - Construction and Black Topping of Roads in Sub-Division Bannu. [MA]
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 26.18 8 18.18 15.267 15.267 10.267 18.267 0 100% 70%
January - 2021
E/W ,S/B & TST Completed. B/C & S/W in progress. Completion : June-2021.
No Image