Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 25 0 0 0 42.365 17.059 80% 50%
July - 2020
Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
December - 2020
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 22.763 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
December - 2020
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 22.763 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 2.727 45.092 37.78 55% 53%
October - 2020
Length 11.5 Km Road work & Premix completed S/Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 0 42.365 37.78 55% 50%
September - 2020
Length 11.5 Km Road work & Premix completed S/Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 0 42.365 37.78 55% 50%
August - 2020
Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
May - 2021
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 10 M
No Image
  1. Rehab: of road from College Chowk Khar to Damadola via Tangai 10 KM
  2. Rehab: of Inayat Killi by pass road 1.9 Km
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
April - 2021
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 10 M
No Image
  1. Rehab: of road from College Chowk Khar to Damadola via Tangai 10 KM
  2. Rehab: of Inayat Killi by pass road 1.9 Km
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
March - 2021
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 22.763 M
No Image
  1. Rehab: of road from College Chowk Khar to Damadola via Tangai 10 KM
  2. Rehab: of Inayat Killi by pass road 1.9 Km
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
February - 2021
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 22.763 M
No Image
  1. Rehab: of road from College Chowk Khar to Damadola via Tangai 10 KM
  2. Rehab: of Inayat Killi by pass road 1.9 Km
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 84.424 42.365 4.279 4.279 4.279 4.279 46.644 37.78 55% 55%
January - 2021
Length 11.5 Km Road work & Premix completed S/Work in progress. Demand Rs. 22.763 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Khyber
30-11--1 30-11--1 - 30-11--1 - 120.118 70.054 25 0 0 0 70.054 25.064 79% 58%
July - 2020
Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 120.118 70.054 0.721 0.721 0.721 0.721 70.775 49.343 59% 59%
October - 2020
08 Units E/work, road work, S/Work & premix in progress.
No Image
1) Rehab: of B/T road Takhtbaig to Matani by Pass (27.45Km)  
2) Constn: of B/T road from Dwa toi Shin Qamar road to Upper Nullah Khowar Toward Yousaf Talab via Haji Jalandar (1.30 Km)
3) Rehab of road from Landi Kotal to Loi Shalman Phase-II  Km 18 bto 21
4) B/T roadfromDarroAdda toMelwart Camp (6.5 Km)
5) Reh: of road from Dwa jhang to Baz Gara Kamar Khel (03-Km)
6) Rehab: of road from Langroo jumat Kallay to Chargai Dagri (3Km)
7) B/T road from Serajudin Madrassa to Bur Qamar khel via Shalubar (3KM)
8) Rehab of road from Sambaba Adera to kohi Chowk (4KM)
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 120.118 70.054 0.721 0.721 0.721 0.721 70.775 49.343 59% 59%
September - 2020
08 Units E/work, road work, S/Work & premix in progress.
No Image
1) Rehab: of B/T road Takhtbaig to Matani by Pass (27.45Km)  
2) Constn: of B/T road from Dwa toi Shin Qamar road to Upper Nullah Khowar Toward Yousaf Talab via Haji Jalandar (1.30 Km)
3) Rehab of road from Landi Kotal to Loi Shalman Phase-II  Km 18 bto 21
4) B/T roadfromDarroAdda toMelwart Camp (6.5 Km)
5) Reh: of road from Dwa jhang to Baz Gara Kamar Khel (03-Km)
6) Rehab: of road from Langroo jumat Kallay to Chargai Dagri (3Km)
7) B/T road from Serajudin Madrassa to Bur Qamar khel via Shalubar (3KM)
8) Rehab of road from Sambaba Adera to kohi Chowk (4KM)
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 120.118 70.054 0.721 0.721 0.721 0.721 70.775 49.343 59% 59%
August - 2020
Work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 3 3 3 3 19.28 55.5 26% 26%
December - 2020
02 Units. 08-Km B/C completed, work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 3 3 3 3 19.28 55.5 26% 26%
December - 2020
02 Units. 08-Km B/C completed, work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 0 0 0 0 16.28 58.5 - 22%
October - 2020
02 Units. 08-Km B/C completed, work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 0 0 0 0 16.28 58.5 - 22%
September - 2020
02 Units. 08-Km B/C completed, work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 0 0 0 0 16.28 58.5 - 22%
August - 2020
02 Units. 08-Km B/C completed, work in progress.
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 32.479 32.479 32.479 16.092 32.372 26.021 65% 43%
March - 2021
02 Units. 08-Km B/C completed, work in progress.
No Image
1 Repair & Reh: of BT road from Had to Ziarat Tehsil Prang Ghar
2 Repair & Reh: of BTR from Main Ekka Ghund road to Shno Ghundo Ekkaghund
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 32.479 32.479 32.479 16.092 32.372 26.021 65% 43%
February - 2021
02 Units. 08-Km B/C completed, work in progress.
No Image
1 Repair & Reh: of BT road from Had to Ziarat Tehsil Prang Ghar
2 Repair & Reh: of BTR from Main Ekka Ghund road to Shno Ghundo Ekkaghund
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 3 3 3 3 19.28 55.5 26% 26%
January - 2021
02 Units. 08-Km B/C completed, work in progress.
No Image
1 Repair & Reh: of BT road from Had to Ziarat Tehsil Prang Ghar
2 Repair & Reh: of BTR from Main Ekka Ghund road to Shno Ghundo Ekkaghund
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
HW
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 32.479 0 0 0 16.28 26.021 65% 22%
May - 2021
02 Units. 08-Km B/C completed, work in progress.
No Image
1 Repair & Reh: of BT road from Had to Ziarat Tehsil Prang Ghar
2 Repair & Reh: of BTR from Main Ekka Ghund road to Shno Ghundo Ekkaghund
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Mohmand
HW
30-11--1 30-11--1 - 30-11--1 - 74.78 16.28 32.479 36.407 36.407 25.461 41.741 26.021 65% 56%
April - 2021
02 Units. 08-Km B/C completed, work in progress.
No Image
1 Repair & Reh: of BT road from Had to Ziarat Tehsil Prang Ghar
2 Repair & Reh: of BTR from Main Ekka Ghund road to Shno Ghundo Ekkaghund
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 70.054 25 25 0 0 70.054 0 100% 100%
December - 2020
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 70.054 25 25 0 0 70.054 0 100% 100%
December - 2020
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 70.054 0 0 0 0 70.054 0 - 100%
October - 2020
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 70.054 0 0 0 0 70.054 0 - 100%
September - 2020
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 0 0 0 0 0 0 69.988 - -
March - 2021
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 0 0 0 0 0 0 69.988 - -
February - 2021
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 69.988 0 0 0 0 0 0 69.988 - -
January - 2021
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 69.988 0 0 0 0 0 0 69.988 - -
May - 2021
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 69.988 0 0 0 0 0 0 69.988 - -
April - 2021
Work in progress. Demand 10 M
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
December - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
December - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
October - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
September - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
August - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 0 0 0 130 0
July - 2020
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
May - 2021
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
April - 2021
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
March - 2021
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
February - 2021
No Image
1876
(OG)
191845-170334-Maintenance and Rehabilitation of Roads in Tribal Districts. (Bajaur, Mohmand, Orakzai & Khyber) [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 349.01 130 25 25 0 0 130 0 - -
January - 2021
No Image