Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 8.704 | 8.704 | 8.704 | 0 | 0 |
May - 2021 |
Work in progress. |
No Image | |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 11.704 | 11.704 | 0 | 0 | 64 | 32% |
- December - 2020 |
Work in progress. |
No Image |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 11.704 | 11.704 | 0 | 0 | 64 | 32% |
- December - 2020 |
Work in progress. |
No Image |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 30 | 7 | 0 | 0 | 64 | 32% |
- October - 2020 |
Work in progress. |
No Image |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 30 | 7 | 0 | 0 | 64 | 32% |
- September - 2020 |
Work in progress. |
No Image |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 30 | 7 | 0 | 0 | 64 | 32% |
- August - 2020 |
Work in progress. |
No Image |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 8.704 | 8.704 | 8.704 | 0 | 0 |
April - 2021 |
Work in progress. |
No Image | |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 18.704 | 18.704 | 0 | 0 | 0 |
March - 2021 |
Work in progress. |
No Image | |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 18.704 | 18.704 | 0 | 0 | 0 |
February - 2021 |
Work in progress. |
No Image | |
1908 (OG) |
195284-Improvement and Rehabilitation of Existing BT Road from Main TP Road to Alamsher Sehra & Dangela 5-KMs Kurram (ER) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94 | 0 | 30 | 18.704 | 18.704 | 0 | 0 | 64 | 32% |
- January - 2021 |
Work in progress. |
No Image |
Pages : 1 |