Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
23-08-13 | - | - | 07-05-12 | - | 917.317 | 679.223 | 35 | 35 | 17.5 | 17.5 | 696.723 | 203.094 | 78% |
76% December - 2017 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
23-08-13 | - | - | 07-05-12 | - | 917.317 | 679.223 | 35 | 35 | 17.5 | 2 | 681.223 | 203.094 | 78% |
74% September - 2017 |
Academic/admin block, cafetaria, library, mosque in progress.
Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
23-08-13 | - | - | 07-05-12 | - | 917.317 | 679.223 | 35 | 35 | 0 | 0 | 679.223 | 203.094 | 78% |
74% August - 2017 |
Academic/admin block, cafetaria, library, mosque in progress.
Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
23-08-13 | - | - | 07-05-12 | - | 917.317 | 679.223 | 35 | 35 | 0 | 0 | 679.223 | 203.094 | 78% |
74% July - 2017 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 17.5 | 9.764 | 688.987 | 203.094 | 78% |
75% November - 2017 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 17.5 | 1.052 | 680.275 | 203.094 | 78% |
74% October - 2017 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. |
No Image |
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 35 | 34.954 | 714.177 | 203.094 | 78% |
78% June - 2018 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
Bannu | |||||||||||||||||||
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 35 | 32.519 | 711.742 | 203.094 | 78% |
78% May - 2018 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
Bannu | |||||||||||||||||||
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 35 | 26.25 | 705.473 | 203.094 | 78% |
77% April - 2018 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
Bannu | |||||||||||||||||||
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 26.25 | 26.25 | 705.473 | 203.094 | 78% |
77% March - 2018 |
Academic/admin block, cafetaria, library, mosque in progress.
Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
Bannu | |||||||||||||||||||
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 26.25 | 17.169 | 696.392 | 203.094 | 78% |
76% February - 2018 |
Academic/admin block, cafetaria, library, mosque in progress.
Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
ADP's Images |
Bannu | |||||||||||||||||||
573 (OG) |
70190-Establishment of Bannu Medical College Bannu (Phase-II). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 679.223 | 35 | 35 | 17.5 | 17.5 | 696.723 | 203.094 | 78% |
76% January - 2018 |
Academic/admin block, cafetaria, library, mosque in progress. Revised PC-I/DCE for Rs.1532.050 m submitted to Project Director BMC Bannu on 11/11/2016. Pre-PDWP held on 20/12/2017. New demands made, will be incorporated in PC-I. |
No Image |
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 22.016 | 479.376 | 76.493 | 87% |
82% December - 2019 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 12.5 | 469.86 | 76.493 | 87% |
80% November - 2019 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 12.5 | 469.86 | 76.493 | 87% |
80% October - 2019 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 12.5 | 12.5 | 469.86 | 76.493 | 87% |
80% September - 2019 |
Main building - Plastering in progress. Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 12.5 | 0 | 457.36 | 76.493 | 87% |
78% August - 2019 |
Main building - Plastering in progress. Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 37.846 | 495.206 | 76.493 | 87% |
85% May - 2020 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 37.846 | 495.206 | 76.493 | 87% |
85% April - 2020 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 37.846 | 495.206 | 76.493 | 87% |
85% March - 2020 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 37.846 | 495.206 | 76.493 | 87% |
85% February - 2020 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||
573 (OG) |
130445-Construction of Joint Judicial Complex at Karak and Takhte- Nasrati. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 583.853 | 457.36 | 50 | 50 | 50 | 27.063 | 484.423 | 76.493 | 87% |
83% January - 2020 |
Main building - Plastering in progress.
Judicial lockup - finishing in progress. |
No Image |
Karak | |||||||||||||||||||