Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
- | 30-06-18 | - | 09-02-16 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 8.746 | 28.746 | 6.682 | 89% |
48% December - 2017 |
FF roofing in progress. |
No Image |
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
- | 30-06-18 | - | 09-02-16 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 4.455 | 24.455 | 6.682 | 89% |
41% September - 2017 |
SS in progress. |
No Image |
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
- | 30-06-18 | - | 09-02-16 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 0 | 20 | 6.682 | 89% |
34% August - 2017 |
SS in progress. |
No Image |
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
- | 30-06-18 | - | 09-02-16 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 0 | 20 | 6.682 | 89% |
34% July - 2017 |
SS in progress. |
No Image |
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 6 | 6 | 6 | 6 | 34.588 | 90.412 | 28% |
28% December - 2018 |
Flooring in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 4.455 | 24.455 | 6.682 | 89% |
41% November - 2017 |
FF roofing in progress. |
No Image |
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 6 | 6 | 6 | 6 | 34.588 | 90.412 | 28% |
28% November - 2018 |
Flooring in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 6 | 6 | 6 | 6 | 34.588 | 90.412 | 28% |
28% November - 2018 |
Flooring in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 4.455 | 24.455 | 6.682 | 89% |
41% October - 2017 |
SS in progress. |
No Image |
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 17.548 | 17.548 | 17.548 | 17.547 | 37.547 | 22.142 | 63% |
63% June - 2018 |
GF plastering in progress. FF roof laid. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 17.547 | 37.547 | 6.682 | 89% |
63% May - 2018 |
GF plastering in progress. FF roof laid. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 17.547 | 37.547 | 6.682 | 89% |
63% April - 2018 |
GF plastering in progress. FF roof laid. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 19 | 19 | 19 | 10 | 38.588 | 77.412 | 38% |
31% April - 2019 |
Finishing in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 13.31 | 33.31 | 6.682 | 89% |
56% March - 2018 |
GF plastering in progress. FF roof laid. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 19 | 19 | 19 | 10 | 38.588 | 77.412 | 38% |
31% March - 2019 |
Finishing in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 19 | 19 | 19 | 10 | 38.588 | 77.412 | 38% |
31% March - 2019 |
Finishing in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 8.746 | 28.746 | 6.682 | 89% |
48% February - 2018 |
FF roof laid. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 19 | 19 | 19 | 10 | 38.588 | 77.412 | 38% |
31% February - 2019 |
Finishing in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.69 | 20 | 33.008 | 33.008 | 33.008 | 8.746 | 28.746 | 6.682 | 89% |
48% January - 2018 |
FF roofing in progress. |
No Image |
GPGC (Boys) No.2 Mandian Abbottabad (BS block) | |||||||||||||||||||
629 (OG) |
160538-Construction of Rooms for District and High Court Bar Swat and Bar Rooms Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 28.588 | 10 | 10 | 10 | 8.945 | 37.533 | 86.412 | 31% |
30% January - 2019 |
Finishing in progress. |
No Image |
Abbottabad | |||||||||||||||||||
629 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari PK-73 District Bannu (3.9 Km). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 47.064 | 0% |
- September - 2018 |
Opening of financial bids on 12/03/2018. Technical evaluation under process. |
No Image |
PK-73, Bannu | |||||||||||||||||||
629 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari PK-73 District Bannu (3.9 Km). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 0.001 | 0.001 | 0.0005 | 0 | 0 | 47.064 | 0% |
- July - 2018 |
Opening of financial bids on 12/03/2018. Technical evaluation under process. |
No Image |
PK-73, Bannu | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% December - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% December - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 0 | 0 | 0 | 0 | 0 | 0 | 35.961 | - |
- October - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 0 | 0 | 0 | 0 | 0 | 0 | 35.961 | - |
- September - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 0 | 0 | 0 | 0 | 0 | 0 | 35.961 | - |
- August - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 0 | 0 | 0 | 0 | 0 | 0 | 35.961 | - |
- July - 2020 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% May - 2021 |
01- Unit
Completed. |
No Image |
Construction of Regional office of ACE at Phagora
Scope of work:
| |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% April - 2021 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% March - 2021 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% February - 2021 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.961 | 39.2927 | 0 | 0 | 0 | 0 | 39.2927 | 0 | - |
100% January - 2021 |
Completed. |
No Image |
Construction of Regional office of ACE at Pha | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-03-16 | 30-06-18 | - | 09-02-16 | - | 49.769 | 18.41 | 17 | 17 | 17 | 4.272 | 22.682 | 14.359 | 71% |
46% December - 2017 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-03-16 | 30-06-18 | - | 09-02-16 | - | 49.769 | 18.41 | 17 | 17 | 17 | 0 | 18.41 | 14.359 | 71% |
37% September - 2017 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-03-16 | 30-06-18 | - | 09-02-16 | - | 49.769 | 18.41 | 17 | 17 | 17 | 0 | 18.41 | 14.359 | 71% |
37% August - 2017 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-03-16 | 30-06-18 | - | 09-02-16 | - | 49.769 | 18.41 | 0 | 0 | 0 | 0 | 18.41 | 31.359 | - |
37% July - 2017 |
Roof level. Shuttering for roof slab in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 4.272 | 22.682 | 14.359 | 71% |
46% November - 2017 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 0 | 18.41 | 14.359 | 71% |
37% October - 2017 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 14.608 | 14.608 | 14.608 | 14.608 | 33.018 | 16.751 | 66% |
66% June - 2018 |
GF - completed. FF - plastering in progress. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 31.365 | 31.365 | 31.365 | 11.61 | 30.02 | 0 | 100% |
60% May - 2018 |
GF - completed. FF - plastering in progress. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 9.644 | 28.054 | 14.359 | 71% |
56% April - 2018 |
GF - completed. FF - plastering in progress. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 9.644 | 28.054 | 14.359 | 71% |
56% March - 2018 |
GF plastering in progress. FF roof laid. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 9.644 | 28.054 | 14.359 | 71% |
56% February - 2018 |
GF plastering in progress. FF roof level. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.769 | 18.41 | 17 | 17 | 17 | 4.272 | 22.682 | 14.359 | 71% |
46% January - 2018 |
GF roof laid. FF column in progress. |
No Image |
GDC Daggar PK-78 (BS block) | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
D.I.Khan |
02-02-16 | 30-06-18 | - | 09-02-16 | - | 52.497 | 46.858 | 3 | 3 | 3 | 0.08 | 46.938 | 2.639 | 95% |
89% December - 2017 |
Completed & H/O (1 units). |
No Image |
1) GDC No.1 DI.Khan | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
D.I.Khan |
02-02-16 | 30-06-18 | - | 09-02-16 | - | 52.497 | 46.858 | 3 | 3 | 3 | 0 | 46.858 | 2.639 | 95% |
89% September - 2017 |
Completed & H/O (1 units). |
No Image |
1) GDC No.1 DI.Khan | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
D.I.Khan |
02-02-16 | 30-06-18 | - | 09-02-16 | - | 52.497 | 46.858 | 3 | 3 | 3 | 0 | 46.858 | 2.639 | 95% |
89% August - 2017 |
Completed (1 units). |
No Image |
1) GDC No.1 DI.Khan | |||||||||||||||||||
629 (OG) |
140008-Construction of BS Blocks in Government Colleges. |
D.I.Khan |
02-02-16 | 30-06-18 | - | 09-02-16 | - | 52.497 | 46.858 | 0 | 0 | 0 | 0 | 46.858 | 5.639 | - |
89% July - 2017 |
Finishing stage. |
No Image |
1) GDC No.1 DI.Khan
2) GGDC No.1 DI.Khan | |||||||||||||||||||
629 (OG) |
150538-Strengthening / Capacity Building of Directorate of Anti-Corruption Establishment. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.685 | 0 | 0 | 0 | 0 | 0 | 0 | 31.685 | - |
- December - 2020 |
Work order issued on 29/01/2016 but site not available. |
No Image |
DI.Khan | |||||||||||||||||||
Pages : 1 2 3 4 5 |