Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% December - 2019 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% November - 2019 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% October - 2019 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% September - 2019 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% August - 2019 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% May - 2020 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% April - 2020 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% March - 2020 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% February - 2020 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 4 | 0 | 0 | 0 | 0 | 4 | 4.2 | - |
49% January - 2020 |
Deposit Work. |
No Image |
Acquisition of land Abbottabad Muree road (widening) in Mouza Bagnotour | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 2 | 2 | 2 | 2 | 2 | 6.2 | 24% |
24% December - 2019 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 2 | 2 | 2 | 2 | 2 | 6.2 | 24% |
24% November - 2019 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 0 | 0 | 0 | 0 | 0 | 8.2 | - |
- October - 2019 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 0 | 0 | 0 | 0 | 0 | 8.2 | - |
- September - 2019 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 0 | 0 | 0 | 0 | 0 | 8.2 | - |
- August - 2019 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 3 | 3 | 3 | 1.826 | 1.826 | 5.2 | 37% |
22% May - 2020 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 3 | 3 | 3 | 0.918 | 0.918 | 5.2 | 37% |
11% April - 2020 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 3 | 3 | 3 | 0.918 | 0.918 | 5.2 | 37% |
11% March - 2020 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 3 | 3 | 3 | 0.918 | 0.918 | 5.2 | 37% |
11% February - 2020 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8.2 | 0 | 2 | 2 | 2 | 2 | 2 | 6.2 | 24% |
24% January - 2020 |
Funds demanded to clear liabilities. |
No Image |
GCT Bannu | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% August - 2019 |
Completed.
Check issued to contractor. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% December - 2019 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% November - 2019 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% October - 2019 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% September - 2019 |
Completed.
Check issued to contractor. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 4.999 | 4.999 | 4.999 | 4.999 | 157.557 | 0 | 100% |
100% May - 2020 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 4.999 | 4.999 | 4.999 | 4.999 | 157.557 | 0 | 100% |
100% April - 2020 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 4.999 | 4.999 | 4.999 | 4.999 | 157.557 | 0 | 100% |
100% March - 2020 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 4.999 | 4.999 | 4.999 | 4.999 | 157.557 | 0 | 100% |
100% February - 2020 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 147.283 | 152.558 | 0 | 0 | 0 | 0 | 152.558 | 0 | - |
100% January - 2020 |
Completed. |
No Image |
District Chitral | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.283 | 0 | 7.283 | 7.283 | 7.283 | 7.283 | 7.283 | 0 | 100% |
100% May - 2020 |
Court decretal. Rs.7.283 m paid to Haji Muhammad Khan Govt Contractor. |
No Image |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.283 | 0 | 7.283 | 7.283 | 7.283 | 7.283 | 7.283 | 0 | 100% |
100% April - 2020 |
Court decretal. Rs.7.283 m paid to Haji Muhammad Khan Govt Contractor. |
No Image |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.283 | 0 | 7.283 | 7.283 | 7.283 | 7.283 | 7.283 | 0 | 100% |
100% March - 2020 |
Court decretal. Rs.7.283 m paid to Haji Muhammad Khan Govt Contractor. |
No Image |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.283 | 0 | 7.283 | 7.283 | 7.283 | 7.283 | 7.283 | 0 | 100% |
100% February - 2020 |
Court decretal. Rs.7.283 m paid to Haji Muhammad Khan Govt Contractor. |
No Image |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.283 | 0 | 7.283 | 7.283 | 7.283 | 7.283 | 7.283 | 0 | 100% |
100% January - 2020 |
Court decretal. Rs.7.283 m paid to Haji Muhammad Khan Govt Contractor. |
No Image |
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.015371 | 0 | 0 | 0 | 0 | 0 | 0 | 15.015 | - |
- December - 2019 |
Approved. |
No Image |
1) Upgradation of THQ Hospital Kulachi to Category-D, District DI.Khan | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.015371 | 0 | 0 | 0 | 0 | 0 | 0 | 15.015 | - |
- November - 2019 |
Approved. |
No Image |
1) Upgradation of THQ Hospital Kulachi to Category-D, District DI.Khan | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.015371 | 0 | 0 | 0 | 0 | 0 | 0 | 15.015 | - |
- October - 2019 |
Approved. |
No Image |
1) Upgradation of THQ Hospital Kulachi to Category-D, District DI.Khan | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.015371 | 0 | 0 | 0 | 0 | 0 | 0 | 15.015 | - |
- September - 2019 |
Approved. |
No Image |
1) Upgradation of THQ Hospital Kulachi to Category-D, District DI.Khan | |||||||||||||||||||
688 (New) |
160453-Provision for Contractors Decretal accrued Liabilities, Land Compensation and Uncashed Cheques |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 15.015371 | 0 | 0 | 0 | 0 | 0 | 0 | 15.015 | - |
- August - 2019 |
Approved. |
No Image |
1) Upgradation of THQ Hospital Kulachi to Category-D, District DI.Khan | |||||||||||||||||||
Pages : 1 2 3 4 5 |