Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 7.001 | 4.5 | 110.962 | 83.602 | 58% |
55% December - 2018 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 4.501 | 4.5 | 110.962 | 83.602 | 58% |
55% November - 2018 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 4.501 | 4.5 | 110.962 | 83.602 | 58% |
55% November - 2018 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 8.2505 | 6.9 | 113.362 | 83.602 | 58% |
57% April - 2019 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 8.2505 | 6.9 | 113.362 | 83.602 | 58% |
57% March - 2019 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 8.2505 | 6.9 | 113.362 | 83.602 | 58% |
57% March - 2019 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 8.2505 | 6.9 | 113.362 | 83.602 | 58% |
57% February - 2019 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islam Kot road, Booji road, Mirpura road, Blolia / Dana road, Dana Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.064 | 106.462 | 10 | 9.5 | 7.001 | 6.9 | 113.362 | 83.602 | 58% |
57% January - 2019 |
Out of 9 units, all in progress. |
No Image |
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
- | 30-06-18 | - | 28-01-15 | - | 76.516 | 28.193 | 49.073 | 49.073 | 24.537 | 9.451 | 37.644 | 0 | 100% |
49% December - 2017 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
- | 30-06-18 | - | 28-01-15 | - | 76.516 | 28.193 | 49.073 | 49.073 | 17.421 | 0 | 28.193 | 0 | 100% |
37% September - 2017 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5-Km) earth work completed. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
- | 30-06-18 | - | 28-01-15 | - | 76.516 | 28.193 | 49.073 | 49.073 | 17.421 | 0 | 28.193 | 0 | 100% |
37% August - 2017 |
Length 8 Km - road work 3 Km, earth work 80%, structure work 40% completed, WBM in progress. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
- | 30-06-18 | - | 28-01-15 | - | 76.516 | 28.193 | 49.073 | 49.073 | 17.421 | 0 | 28.193 | 0 | 100% |
37% July - 2017 |
Length 8 Km - road work 3 Km, earth work 80%, structure work 40% completed, WBM in progress. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.193 | 49.073 | 49.073 | 24.537 | 9.613 | 37.806 | 0 | 100% |
49% November - 2017 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.193 | 49.073 | 49.073 | 24.537 | 0 | 28.193 | 0 | 100% |
37% October - 2017 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.7917 | 49.073 | 39.074 | 39.074 | 31.272 | 60.0637 | 0 | 100% |
78% June - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Cannot be completed to court case. |
No Image |
Bannu | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.7917 | 49.073 | 49.074 | 49.074 | 27.868 | 56.6597 | 0 | 100% |
74% May - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. Cannot be completed to court case. |
No Image |
Bannu | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.7917 | 49.073 | 49.074 | 49.074 | 24.533 | 53.3247 | 0 | 100% |
70% April - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
Bannu | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.7917 | 49.073 | 49.073 | 24.537 | 24.537 | 53.3287 | 0 | 100% |
70% March - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
Bannu | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.7917 | 49.073 | 49.073 | 24.537 | 17.66 | 46.4517 | 0 | 100% |
61% February - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
Bannu | |||||||||||||||||||
975 (OG) |
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.516 | 28.193 | 49.073 | 49.073 | 24.537 | 9.451 | 37.644 | 0 | 100% |
49% January - 2018 |
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5 Km) earth work completed. |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 190.505 | 20 | 2.447 | 16.584 | 0 | 100% |
8% December - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Revised DCE submitted |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 190.505 | 20 | 2.447 | 16.584 | 0 | 100% |
8% December - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Revised DCE submitted |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 0 | 0 | 20 | 2.447 | 16.584 | 184.414 | - |
8% October - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress. |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 0 | 0 | 20 | 2.447 | 16.584 | 184.414 | - |
8% September - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress. |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 0 | 0 | 0 | 0 | 14.137 | 184.414 | - |
7% August - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress. |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 0 | 0 | 0 | 14.137 | 0 | 100% |
7% July - 2020 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress. |
No Image |
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 64.712 | 64.712 | 2.447 | 16.584 | 0 | 100% |
8% May - 2021 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Cannot be completed due to revision
Revised DCE submitted |
No Image |
Construction of Building for Govt Degree College Ara Khel, FR Kohat. | |||||||||||||||||||
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 64.712 | 64.712 | 2.447 | 16.584 | 0 | 100% |
8% April - 2021 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Cannot be completed due to revision
Revised DCE submitted |
No Image |
Construction of Building for Govt Degree College Ara Khel, FR Kohat. | |||||||||||||||||||
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 64.712 | 64.712 | 2.447 | 16.584 | 0 | 100% |
8% March - 2021 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Cannot be completed due to revision
Revised DCE submitted |
No Image |
Construction of Building for Govt Degree College Ara Khel, FR Kohat. | |||||||||||||||||||
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 64.712 | 64.712 | 2.447 | 16.584 | 0 | 100% |
8% February - 2021 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Cannot be completed due to revision
Revised DCE submitted |
No Image |
Construction of Building for Govt Degree College Ara Khel, FR Kohat. | |||||||||||||||||||
975 (OG) |
191576-170422 - Construction of Building for Govt Degree College Ara Khel, FR Kohat. [MA] |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.551 | 14.137 | 190.505 | 64.712 | 64.712 | 2.447 | 16.584 | 0 | 100% |
8% January - 2021 |
C/Wall completed.
Test Bare in progress.
Levelling, Dressing in progress.
Revised DCE submitted |
No Image |
Construction of Building for Govt Degree College Ara Khel, FR Kohat. | |||||||||||||||||||
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- December - 2019 |
Tender floated on 13/01/2020. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- November - 2019 |
Approved. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
Approved on 08/11/2019. AA awaited. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
DCE will be re submitted by 21-10-2019 on MRS 2019. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
Dce under preparation |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- May - 2020 |
Work order issued. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- April - 2020 |
Work order issued. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- March - 2020 |
Work order issued. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- February - 2020 |
Work order issued. |
No Image |
975 (New) |
190590-Construction / Improvement / Rehabilitation and BT of Oghi Ahi Battal road Jandar Pari to Balian Chakal road Darband District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 0 | 10 | 10 | 0 | 0 | 0 | 240 | 4% |
- January - 2020 |
Tender approval under process. |
No Image |
Pages : 1 |