Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, January - 2021, January - 2018, February - 2019, February - 2020, February - 2021, February - 2018, March - 2018, March - 2019, March - 2020, March - 2021, April - 2018, April - 2019, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2018, November - 2019, November - 2017, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 403.101 309.096 0 0 0 0 309.096 94.005 - 77%
September - 2018
21 units - work in progress on all units.
No Image
1) Rehabilitation/improvement of Sherwan road upto Shimla Hill Park (3.450 Km) - 0 - 2 Km
2) Rehabilitation/improvement of Sherwan road upot Shimla Hill Park (3.450 Km) - 2 - 3.450 Km
3) Rehabilitation/improvement of Khushal Chowk to KPK House road
4) Rehabilitation/improvement of Fawara Chowk to Admore Pumpl Chowk
5) Rehabilitation/improvement of road from Shaheen Chowk to FG School i/c Police line road
6) Rehabilitation/improvement of College road to Seena Laboratory
7) Rehabilitation/improvement of road from Shafeeq Plaza to Poly Technical College i/c Old College road
8) Rehabilitation/improvement of Officer Colony road
9) Rehabilitation/improvement of road from Sarban Chowk to Chinar road
10) Rehabilitation/improvement of Kehal road
11) Rehabilitation/improvement of Abbottabad Bazar road 0 - 2.50 Km
12) Rehabilitation/improvement of Abbottabad Bazar road 2.50 - 5 Km
13) Rehabilitation/improvement of Abbottabad Bazar road 5 - 6.40 Km
14) Rehabilitation/improvement of Narrian road
15) Rehabilitation/improvement of Bilal Town road
16) Rehabilitation/improvement of Jail to Jalal Baba Chowk
17) Rehabilitation/improvement of Jail to Sherwan road
18) Black Topping of Missile Chowk to PMA Bypass road
19) Black Topping of Lakhpati Chowk to Mandroch road
20) Black Topping of approaches of Civil Station roads (2 Km)
21) Rehabilitation/improvement of PMA Main Gate to Choona Kari via Mumtaz Town
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 425.501 96.013 1062.065 1062.065 1062.065 6.035 102.048 0 100% 24%
September - 2018
9 Packages - work in progress on all packages.
No Image
1) Rehabilitation/widening of road from inside Lakki Gate to Miryan Gate via Qasaban Chowk (Package-1)
2) Rehabilitation/widening of Juma Khan road from Kohat Chungi to Police line (Package-1)
3) Rehabilitation/widening of Jaman road from Miranshah road (Package-1)
4) Rehabilitation/widening of road from Miranshah road to Mandan Gate via Parity Gate and Chowke Bazar (Package-1)
5) Rehabilitation/widening of Juma Khan roadto Judicial Complex (Package-1)
6) Rehabilitation/widening of road from Qasaban road to Parity Mosque (Package-1)
7) Rehabilitation/widening of road from Main Miranshah road to Dus Chowke via Qasaban Masjid (Package-1)
8) Rehabilitation/widening of road from Zinana Hospital to Kachari Gate (Package-2)
9) Rehabilitation/widening of road from Kachari Gate to Degree College (Package-2)
10) Rehabilitation/widening of road from Ghala Mandi Chowke to Circular road (Package-2)
11) Rehabilitation/widening of road from Main Miranshah road to Kachari Gate (Package-2)
12) Rehabilitation/widening of Miryan road from Degree College to Kachkot Bridge (Package-2)
13) Rehabilitation/widening of road Old Sabzi Mandi road (Package-2)
14) Rehabilitation/widening of Miryan road and reconstruction of BW of Degree College No.1 (Package-2)
15) Rehabilitation/widening of road from Circular road to Sokari Jabar (Package-2)
16) Construction of drain/foot path at Officer Colony (Package-2)
17) Drainage System at Bakka Khel Mandi alongwith Miranshah road (Package-2)
18) Rehabilitation/widening of Allah Wala Chowke to Bazar Ahmad Khen (Package-3)
19) Rehabilitation/widening of road from Lakki Gate to Parity Gate via Police Line (Package-3)
20) Rehabilitation/widening of road from Mall Mandi to Mandan road via Kotka Khattakan (Package-3)
21) Rehabilitation/widening of road from Mandan Gate to Trange Qabristan (Package-3)
22) Rehabilitation/widening of road from Judicial Complex to Bazar Ahmad Khan via Fatma Khel (Package-3)
23) Rehabilitation/widening of road from Amandi to Kachkot Asad Khan Bridge (remaiing portion) (Package-3)
24) Rehabilitation/widening of road from Sokari Gate to Tanchi Bazar (Package-3)
25) Rehabilitation/widening of Tehsil Domel Bazar (Package-4)
26) Rehabilitation/widening of Main Kakki Bazar road (Package-4)
27) Rehabilitation/widening of road from Domel Police Station to Ghani Khel Chowke (Package-4)
28) Parcks/Dustgin/Green Belts/Parks (Fazal-e-Qadir Shaheed)/Delassa Park/Milad Park/Lady Park/Allah Wala Chowke (Package-4)
29) Dustbin (Bannu City) (Package-4)
30) Greet Belts (DI.Khan road and Kohat road) (Package-4)
31) Green Belts (DI.Khan road and Kohat road) (Package-4)
32) Rehab/widening of road from Kurram Bridge to Police Station Saddar via Kohat Chungi/GTS Chowke/Lakki Gate (Package-5)
33) Rehab/widening of Circular road from Kachari Gate to Mal Mandi via Degree College No.1 and Hinjal (Package-6)
34) Rehab/widening of Miranshah road from University Plaza to Tapi Killah (Package-7)
35) Rehab/widening of Baran Dam road from Officer Colony to Daud Shah (Package-7)
36) Rehabilitation/widening of road from PS Haved to PS Mandan (Package-8)
37) Construction  of drainage system at Bannu City (Package-8)
38) Muslim League Gate to Miryan Gate via Zanana Hospital (Package-8)
39) Muslim League Gate to Degree Collage via Sokari road (Package-8)
40) Miryan Gate to GHS No.4 via Degree College (Package-8)
41) Alongwith Allah Wala Chowk (Package-8)
42) Alongwith Cantt Police Station main Miranshah road (Package-8)
43) Along with Bannu Kohat road near Kuram bridge (Package-8)
44) Women and Children Hospital Bannu (construction of labour room) (Package-9)
45) Electricity/PTCL (Package-10)
46) Construction/widening/rehabilitation of road from Main Kakki Bazar
47) Rehabilitation/widening of remaining portion of serivce road from Miryan Gate to Mandan Gate via Hinjal Gate Bannu
48) Repair/rehabilitation of tehsil administrative building Bannu
 
Construction of drain, foot path and PCC Shoulders in front of PAF near Chakarkot on Bannu road
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 181.215 133.003 0 0 0 0 133.003 48.212 - 73%
September - 2018
Work in progress.
No Image
1) Construction of road remaining portion Gillani Town towards Wandha Modchianwala DI.Khan
2) Construction of road main Multan road towards Muryali DI.Khan
3) Construction of road line road opposite site DHO office to Bannu road DI.Khan
4) Construction of road BTR from Bannu road towards Wandha Balochan Wala DI.Khan
5) Construction of road Sabzi Mandi towards village Lakhra DI.Khan
6) Construction of BTR from Main Bannu road to Darya Bund in front of Cantt Bus stand (Mosmiate road) DI.Khan
7) Construction of BTR road from Diyal road to river Indus Gulshan Jameel Colony
8) Improvement/construction of Asphalt road from Bab-e-Dera to Sheikh Yousaf Chowk DI.Khan
9) Construction of various streets in UC-5 and UC City-2 (additional works)
10) Construction of various streets in UC Dewala (additional works)
11) Construction of various streets in UC Ratta Kulachi/UC Shore Kot (additional works)
12) Construction of various streets in UC ZaffarAbad (additional works)
13) Construction of various streets in UC DD-1 and DD-2 (additional works)
143) Construction of street/drain at Khayaban-e-Khyber Colony Panyala House Diyal road to Masjid Kosar Main Street DI.Khan (additional works)
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 98.987 0 0 0 0 0 0 98.987 - -
September - 2018
Work order issued. Site dispute.
No Image
Dir Upper
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 29.763 10 30 25.0005 25 54.763 210.237 16% 22%
December - 2018
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of (a) Makhnial to Kharian Neelan Poto road (9 Km) (b) Gandian Kamawa Chapra Road (12 Km), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 29.763 10 30 25.001 0 29.763 210.237 16% 12%
November - 2018
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of (a) Makhnial to Kharian Neelan Poto road (9 Km) (b) Gandian Kamawa Chapra Road (12 Km), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 29.763 10 30 25.001 0 29.763 210.237 16% 12%
November - 2018
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 29.763 10 35 35 27.499 57.262 360.237 10% 14%
April - 2019
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 29.763 10 35 32.5005 26.5 56.263 360.237 10% 14%
March - 2019
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 29.763 10 35 32.5005 26.5 56.263 360.237 10% 14%
March - 2019
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 29.763 10 35 32.5005 25 54.763 360.237 10% 14%
February - 2019
Work in progress.
No Image
Haripur
1002
(OG)
170183-Construction of: Makhnial to Kharian Neelan Poto road (9 Km), Gandian Kamawa Chapra Road, BT road from Qutba Chowk to JB (7 Km), Chaohian Board to Mohallah Rajpur (1.200 Km), Mang to Kali Tarrar Bala (1.200 Km), Mang Stop to village Mang (700 mtr), Main road village Ghalam (700 mtr), Qutba Chowk to village Qutba (3.400 Km), Bandi Muneem Stop to Soka (700 mtr), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 29.763 10 30 25.0005 25 54.763 210.237 16% 22%
January - 2019
Work in progress.
No Image
Haripur
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
December - 2019
Length 23 Km - Land payment made. 16 km BT completed
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 180 45 45 2742.6 2105.392 58% 55%
November - 2019
Length 23 Km - Land payment made. 16 km BT completed
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 180 45 45 2742.6 2105.392 58% 55%
October - 2019
Length 23 Km - Land payment made. 16 km BT completed
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 180 45 45 2742.6 2105.392 58% 55%
September - 2019
Length 23 Km - Land payment made. 16 km BT completed
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4686.204 2697.6 180 180 45 45 2742.6 1808.604 61% 59%
August - 2019
Length 23 Km - Land payment made. BT in progress. 2nd Revised PC-I/DCE for Rs.4999.796 m sumbitted to Chief Infra P&D on 18/03/2019.
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
May - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub grade, WBM in progress. Pack-2 (5.25 Km) sub base, sub grade, WBM in progress. Pack-3 (5.25 Km) sub base, sub grade, WBM in progress. Pack-4 (4.2 Km) AWC in progress. Pack-5 (3.83 Km) AWC completed. 16 km BT completed.
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
April - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub grade, WBM in progress. Pack-2 (5.25 Km) sub base, sub grade, WBM in progress. Pack-3 (5.25 Km) sub base, sub grade, WBM in progress. Pack-4 (4.2 Km) AWC in progress. Pack-5 (3.83 Km) AWC completed. 16 km BT completed.
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
March - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub grade, WBM in progress. Pack-2 (5.25 Km) sub base, sub grade, WBM in progress. Pack-3 (5.25 Km) sub base, sub grade, WBM in progress. Pack-4 (4.2 Km) AWC in progress. Pack-5 (3.83 Km) AWC completed. 16 km BT completed.
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
February - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub grade, WBM in progress. Pack-2 (5.25 Km) sub base, sub grade, WBM in progress. Pack-3 (5.25 Km) sub base, sub grade, WBM in progress. Pack-4 (4.2 Km) AWC in progress. Pack-5 (3.83 Km) AWC completed. 16 km BT completed.
No Image
1002
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 2697.6 180 172.35 172.35 172.35 2869.95 2105.392 58% 58%
January - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub grade, WBM in progress. Pack-2 (5.25 Km) sub base, sub grade, WBM in progress. Pack-3 (5.25 Km) sub base, sub grade, WBM in progress. Pack-4 (4.2 Km) AWC in progress. Pack-5 (3.83 Km) AWC completed. 16 km BT completed.
No Image
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 466.273 241.506 268.3 268.3 268.3 11.861 253.367 0 100% 54%
September - 2018
BW, step mosaic, beautification, drain, foot path, WB, asphalt, PCC shoulder in progress.
No Image
1) Qilla Ground and Municipal Ground Kohat (reconstruction/rehabilitation of BW, Gates and installation of flood lights)
2) TMS office to Murghi Mandid and GHS No.2 Kohat (rehabilitation of road)
3) Redesignation of Chow of Link road and KDA main road near Gulshan Abad Chowk KDA Kohat
4) Removal of encroachment and expansion of road near Kind Gate Kohat
5) Construction of road sides/shoulder and rehabilitation of drain footh path from OTS Chowk to Gulshan Abad Chowk Peshawar road Kohat
6) Development of public park of Defence Colony Bannu road Kohat Cantt
7) Improvement and rehabilitation of natural springs including construction of fabric huts in Chili Bagh Spring
8) Preservation and construction of Tehsil Building Kohat
9) Provision of Security measures, raising of BW construction of Watch Tower and improvement of Govt offices in
District Kohat
10) Rehabilitation of road in Kohat Cantt area
11) Rehabilitation of road in Phase-I and Phase-II KDA Kohat
12) Establishment and rehabilitation of Tanda Dam Tourist Resort, construction, rehabilitation/widening of road and children park etc
13) Rehabilitation and repair of OTS road
14) Construction of drain, path and shoulder in front of PAF near Chakarkot on Bannu road
15) Installation of Solar Lights at Gulshan Abad Chowk to Kotal Top
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 87.903 44 0 0 0 0 44 43.903 - 50%
September - 2018
Work in progress.
No Image
1) Construction of dedicated U-turn and round about District Mardan N-45
2) Rehabilitation/restoration of Traffic Signals with installation of additional equipments required for the system at various locations at District Mardan
3) Construction/fabrication of waiting shed at various location (4 Nos)/beutification works N-45 in Mardan
4) Constructionof service road alongwith N-4 from Bab-e-Mardan towards Ring road Mardan
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
December - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
December - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
October - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
September - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
August - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 0 0 0 122.22 34.19 84% 56%
July - 2020
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
May - 2021
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
April - 2021
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
March - 2021
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
February - 2021
Approved.
No Image
1002
(OG)
160541-F/S and construction of Bachelor Hostel of Police at Police lines Peshawar
Peshawar
30-11--1 30-11--1 - 30-11--1 - 218.536 122.22 62.126 62.126 0 0 122.22 34.19 84% 56%
January - 2021
Approved.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
25-06-15 30-06-18 - 13-02-15 - 49.933 31.173 18.01 18.01 13.508 13.508 44.681 0.75 98% 89%
December - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 13.508 12 43.173 0.75 98% 86%
November - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 13.505 9.005 40.178 0.75 98% 80%
October - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
25-06-15 30-06-18 - 13-02-15 - 49.933 31.173 18.01 18.01 9.005 9.005 40.178 0.75 98% 80%
September - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
25-06-15 30-06-18 - 13-02-15 - 49.933 31.173 18.01 18.01 9.005 9.005 40.178 0.75 98% 80%
August - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
25-06-15 30-06-18 - 13-02-15 - 49.933 31.173 18.01 18.01 6.394 6.394 37.567 0.75 98% 75%
July - 2017
Bridge 60 mtr - bridge structure work and base course completed.
No Image
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 18.01 18.01 49.183 0.75 98% 98%
June - 2018
Bridge 60 mtr - bridge structure and asphalt completed.
No Image
Peshawar
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 18.01 18.01 49.183 0.75 98% 98%
May - 2018
Bridge 60 mtr - bridge structure and asphalt completed. Rs.6 m demanded above alloaction for completion of scheme.
No Image
Peshawar
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 18.01 18.01 49.183 0.75 98% 98%
April - 2018
Bridge 60 mtr - bridge structure and asphalt completed.
No Image
Peshawar
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 13.508 13.508 44.681 0.75 98% 89%
March - 2018
Bridge 60 mtr - bridge structure work and base course completed.
No Image
Peshawar
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 13.508 13.508 44.681 0.75 98% 89%
February - 2018
Bridge 60 mtr - bridge structure work and base course completed. Rs.8.500 m demanded for completion.
No Image
Peshawar
1002
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 49.933 31.173 18.01 18.01 13.508 13.508 44.681 0.75 98% 89%
January - 2018
Bridge 60 mtr - bridge structure work and base course completed.
No Image
Peshawar
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 6400 6000 100 100 0 0 6000 0 - -
September - 2018
No Image
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Swat
30-11--1 30-11--1 - 30-11--1 - 96.993 51.928 0 0 0 0 51.928 45.065 - 54%
September - 2018
Out of 4 units, 1 post qualification tender called on 14/11/2017, 2 technical evaluation of contractors under process, 1 pre-qualification of contractors called on 08/11/2017.
No Image
1) Reconstruction/rehabilitation of boundary walls and other repair works at PK-80, Swat
2) Rehabilitation/renovation and other repair works at Allaho-Akbar Masjid Saidu Sharif, Swat
3) Reconstruction/renovation/beatification at Grassy Ground (foot ball) Saidu Sharif Swat
4) Construction of pavilion (civil work)
5) Developmental works
6) Football ground (astro turf)
7) Repair/renovation and beautification of Wadudia Hall Saidu Sharif, Swat
8) Construction of Manument at Continental Chowk
9) Construction of Manument at Bypass Chowk Fiza Ghat
10) Construction of Monument at Manglawar Chowk
11) Construciton of Monument at Saidu Sharif SINOR Hospital
12) Construction of Monument at People Chowk
13) WAPDA
14) Rehabilitation/renovation and other repair works at Janazo Masjid Mingora Swat
1002
(OG)
140797-Uplift & Beautification of Divisional Headquarters in Khyber PakhtunKhwa.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 471.174 47.552 0 0 0 0 47.552 423.622 - 10%
September - 2018
11 units - 5 in progress, 3 work order issued, 2 tender approval under process.
No Image
Pages : 1