Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% December - 2018 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% November - 2018 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% November - 2018 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% April - 2019 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% March - 2019 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% March - 2019 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% February - 2019 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 114.982 | 131.482 | 0 | 0 | 0 | 0 | 131.482 | 0 | - |
100% January - 2019 |
Completed. |
No Image |
1) RCC Bridge Ghundakai at Wali Noor Jani Khel PK-72, Bannu | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% December - 2018 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% November - 2018 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% November - 2018 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% April - 2019 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% March - 2019 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% March - 2019 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% February - 2019 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.69 | 55.415 | 0 | 0 | 0 | 0 | 55.415 | 0 | - |
100% January - 2019 |
Completed (bridge span 45 mtr). |
No Image |
Construction of RCC Bridge on Nandehar Khawar at Deshan Hotal PK-59 | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 15.421 | 15.421 | 15.421 | 5.421 | 71.3 | 19.351 | 81% |
71% December - 2018 |
Bridge structure completed, approaches in progress. Court case on one side of bridge. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 15.421 | 15.421 | 15.421 | 5.421 | 71.3 | 19.351 | 81% |
71% November - 2018 |
Bridge structure completed, approaches in progress. Court case on one side of bridge. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 15.421 | 15.421 | 15.421 | 5.421 | 71.3 | 19.351 | 81% |
71% November - 2018 |
Bridge structure completed, approaches in progress. Court case on one side of bridge. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 20.842 | 20.842 | 20.842 | 8.342 | 74.221 | 13.93 | 86% |
74% April - 2019 |
Bridge structure completed, approaches in progress. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 20.842 | 20.842 | 20.842 | 8.342 | 74.221 | 13.93 | 86% |
74% March - 2019 |
Bridge structure completed, approaches in progress. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 20.842 | 20.842 | 20.842 | 8.342 | 74.221 | 13.93 | 86% |
74% March - 2019 |
Bridge structure completed, approaches in progress. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 20.842 | 20.842 | 20.842 | 8.342 | 74.221 | 13.93 | 86% |
74% February - 2019 |
Bridge structure completed, approaches in progress. Demand Rs. 18.93 |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.651 | 65.879 | 15.421 | 15.421 | 15.421 | 6.819 | 72.698 | 19.351 | 81% |
72% January - 2019 |
Bridge structure completed, approaches in progress. Court case on one side of bridge. |
No Image |
1) RCC bridge on Barundu Khawar PK-78 Span 60m, | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% December - 2018 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% November - 2018 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% November - 2018 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% April - 2019 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% March - 2019 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% March - 2019 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% February - 2019 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 116.283 | 133.167 | 0 | 0 | 0 | 0 | 133.167 | 0 | - |
100% January - 2019 |
Completed. |
No Image |
Construction of RCC Bridge over Chunai Nullah on Mela Mandra Khel on Shahab Khel road PK-75 Lakki Marwat | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 10.861 | 319.045 | 12.506 | 96% |
91% December - 2018 |
5/6 bridges completed, 1 in progress (Mayar bridge) lauching completed. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 6 | 314.184 | 12.506 | 96% |
90% November - 2018 |
5/6 bridges completed, 1 in progress (Mayar bridge) lauching completed. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 6 | 314.184 | 12.506 | 96% |
90% November - 2018 |
5/6 bridges completed, 1 in progress (Mayar bridge) lauching completed. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 11.291 | 319.475 | 12.506 | 96% |
92% April - 2019 |
5/6 bridges completed, 1 in progress (Mayar bridge) launching completed. Demand Rs.13.4 m. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 11.291 | 319.475 | 12.506 | 96% |
92% March - 2019 |
5/6 bridges completed, 1 in progress (Mayar bridge) launching completed. Demand Rs.22.5 m. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 11.291 | 319.475 | 12.506 | 96% |
92% March - 2019 |
5/6 bridges completed, 1 in progress (Mayar bridge) launching completed. Demand Rs.22.5 m. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 10.861 | 319.045 | 12.506 | 96% |
91% February - 2019 |
5/6 bridges completed, 1 in progress (Mayar bridge) launching completed. Demand Rs. 22.5 M |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 349.12 | 308.184 | 28.43 | 28.43 | 28.43 | 10.861 | 319.045 | 12.506 | 96% |
91% January - 2019 |
5/6 bridges completed, 1 in progress (Mayar bridge) lauching completed. |
No Image |
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span | |||||||||||||||||||
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 27.92 | 62.276 | 62.276 | 29.616 | 1.199 | 29.119 | 1.977 | 98% |
32% December - 2020 |
07- Packages & 51 units
work in progress. |
No Image |
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 27.92 | 62.276 | 62.276 | 29.616 | 1.199 | 29.119 | 1.977 | 98% |
32% December - 2020 |
07- Packages & 51 units
work in progress. |
No Image |
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 27.92 | 62.276 | 62.276 | 15 | 0.667 | 28.587 | 1.977 | 98% |
31% October - 2020 |
07- Packages & 51 units
work in progress. |
No Image |
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 27.92 | 62.276 | 62.276 | 15 | 0 | 27.92 | 1.977 | 98% |
30% September - 2020 |
07- Packages & 51 units
work in progress. |
No Image |
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 27.92 | 62.276 | 62.276 | 15 | 0 | 27.92 | 1.977 | 98% |
30% August - 2020 |
07- Packages & 51 units
work in progress. |
No Image |
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 29.897 | 62.276 | 0 | 0 | 0 | 29.897 | 0 |
July - 2020 |
No Image | ||
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 28.023 | 62.276 | 45.946 | 45.946 | 4.509 | 32.532 | 1.874 | 98% |
35% May - 2021 |
07- Packages
51- Units
work in progress.
02/07 Packages cannot be started due no body participated in tender
Revised esitamate submitted under process |
No Image |
Package I (17 units)
Package II (18 Units)
Package III (07 Units)
Package IV (09 Units)
Package V (07 Units)
Package VI (06 Units)
Package VII (03 Units)
Scope of work:
| |||||||||||||||||||
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 28.023 | 62.276 | 45.946 | 45.946 | 4.509 | 32.532 | 1.874 | 98% |
35% April - 2021 |
07- Packages & 51 units
work in progress.
02/07 Packages cannot be started due no body participated in tender
Revised esitamate submitted under process |
No Image |
Package I (17 units)
Package II (18 Units)
Package III (07 Units)
Package IV (09 Units)
Package V (07 Units)
Package VI (06 Units)
Package VII (03 Units) | |||||||||||||||||||
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 28.023 | 62.276 | 45.946 | 45.946 | 2.096 | 30.119 | 1.874 | 98% |
33% March - 2021 |
07- Packages & 51 units
work in progress. |
No Image |
Package I (17 units)
Package II (18 Units)
Package III (07 Units)
Package IV (09 Units)
Package V (07 Units)
Package VI (06 Units)
Package VII (03 Units) | |||||||||||||||||||
1043 (OG) |
191122-170374-M&R / Rehabilitation / Reconstruction and Construction of Levis/Khassadars Picquets in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 92.173 | 28.023 | 62.276 | 45.946 | 45.946 | 1.721 | 29.744 | 1.874 | 98% |
32% February - 2021 |
07- Packages & 51 units
work in progress. |
No Image |
Package I (17 units)
Package II (18 Units)
Package III (07 Units)
Package IV (09 Units)
Package V (07 Units)
Package VI (06 Units)
Package VII (03 Units) | |||||||||||||||||||
Pages : 1 2 |