Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 34.158 | 23.017 | 20.321 | 51.198 | 0 | 100% |
90% December - 2020 |
12- Components
Work in progress on all. |
No Image |
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 34.158 | 23.017 | 20.321 | 51.198 | 0 | 100% |
90% December - 2020 |
12- Components
Work in progress on all. |
No Image |
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 34.158 | 15 | 13.167 | 44.044 | 0 | 100% |
77% October - 2020 |
12- Components
Work in progress on all. |
No Image |
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 34.158 | 15 | 10.858 | 41.735 | 0 | 100% |
73% September - 2020 |
12- Components
Work in progress on all. |
No Image |
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 34.158 | 0 | 0 | 30.877 | 0 | 100% |
54% August - 2020 |
12- Components
Work in progress on all. |
No Image |
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 22.878 | 34.158 | 0 | 0 | 0 | 22.878 | 0 |
July - 2020 |
No Image | ||
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 28.528 | 28.528 | 22.884 | 53.761 | 0 | 100% |
94% May - 2021 |
12- Components
05 Units - H/O
02 Units - Completed
05 Units - Work in progress |
No Image |
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12 Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2 | |||||||||||||||||||
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 28.528 | 28.528 | 22.884 | 53.761 | 0 | 100% |
94% April - 2021 |
12- Components
05 Units - H/O
02 Units - Completed
05 Units - Work in progress |
No Image |
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12 Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2 | |||||||||||||||||||
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 28.528 | 28.528 | 22.884 | 53.761 | 0 | 100% |
94% March - 2021 |
12- Components
05 Units - H/O
02 Units - Completed
05 Units - Work in progress |
No Image |
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12 Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2 | |||||||||||||||||||
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 23.017 | 23.017 | 20.321 | 51.198 | 0 | 100% |
90% February - 2021 |
12- Components
05 Units - H/O
02 Units - Completed
05 Units - Work in progress |
No Image |
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12 Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2 | |||||||||||||||||||
1051 (OG) |
191150-180226 - Construction / Re-construction / Rehab of Khasadar Check Posts and Rehab of Levy Barracks and offices in Sub-Division Bannu. [MA] |
FR Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.036 | 30.877 | 34.158 | 23.017 | 23.017 | 21.824 | 52.701 | 0 | 100% |
92% January - 2021 |
12- Components
Work in progress on all. |
No Image |
1 Khassadar Piqucet Aqibal Akhya Khel
2 Khassadar Piqucet Azam Khel
3 Khassadar Piqucet Lower SHankai
4 Khassadar Piqucet Upper SHankai
5 Khassadar Piqucet Saidqi Ziaulhaq
6 Khassadar Piqucet Sarka Pul
7 Khassadar Piqucet Puranan Mandi Ayaz Khel
8 Khassadar Piqucet Kanday Umer Ali
9 Khassadar Piqucet Khojul Khel
10 Khassadar Piqucet Khojule Shkurural Khel Zarwam No.2
11 Khassadar Piqucet Tanga Kalim Khel Gangai Khel 1
12 Khassadar Piqucet Tanga Hafiz Khel Gangi Khel 2 | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
- | - | - | 26-11-15 | - | 200 | 23.5 | 30 | 30 | 30 | 10.65 | 34.15 | 146.5 | 27% |
17% December - 2017 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved. to CA for change in nomenlcalture. DCE submitted to P&D . PDWP awaited. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 30 | 10.65 | 10.65 | 34.15 | 146.5 | 27% |
17% November - 2017 |
3/11 Km asphalt completed. WBM, AWC in progress. Revised scope tender cancelled. Summary submitted to CA for change in nomenlcalture. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 30 | 10.65 | 0 | 23.5 | 146.5 | 27% |
12% October - 2017 |
3/11 Km asphalt completed. WBM, AWC in progress. Revised scope tendering in progress. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
- | - | - | 26-11-15 | - | 200 | 23.5 | 30 | 30 | 10.65 | 0 | 23.5 | 146.5 | 27% |
12% September - 2017 |
3/11 Km asphalt completed. WBM, AWC in progress. Revised scope tendering in progress, opening on 01/11/2017. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
- | - | - | 26-11-15 | - | 99.999 | 23.5 | 30 | 30 | 10.65 | 0 | 23.5 | 46.499 | 54% |
24% August - 2017 |
3/11 Km asphalt completed. Revised PC-I/DCE for Rs.200 m submitted to SOR on 01/08/2017.Pre-PDWP held. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
- | - | - | 26-11-15 | - | 99.999 | 23.5 | 30 | 30 | 10.65 | 0 | 23.5 | 46.499 | 54% |
24% July - 2017 |
3/11 Km asphalt completed. Revised PC-I/DCE for Rs.200 m submitted to SOR on 01/08/2017. |
No Image |
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 57.812 | 57.812 | 57.812 | 81.312 | 146.5 | 27% |
41% June - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
Nowshera | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 57.812 | 57.812 | 57.812 | 81.312 | 146.5 | 27% |
41% May - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
Nowshera | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 57.812 | 57.812 | 55.121 | 78.621 | 146.5 | 27% |
39% April - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
Nowshera | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 57.812 | 57.812 | 55.121 | 78.621 | 146.5 | 27% |
39% March - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
Nowshera | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 55.122 | 55.122 | 43.226 | 66.726 | 146.5 | 27% |
33% February - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
Nowshera | |||||||||||||||||||
1051 (OG) |
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 23.5 | 30 | 25.122 | 25.122 | 20 | 43.5 | 146.5 | 27% |
22% January - 2018 |
3/11 Km asphalt completed. WBM, AWC in progress. Work order issued. Summary approved to CA for change in nomenlcalture. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 5 | 5 | 10 | 2.498 | 91% |
36% December - 2019 |
Shafting of 1st floor slab in progress. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 5 | 4.593 | 9.593 | 2.498 | 91% |
35% November - 2019 |
Foundation raft completed. Ist Floor Column is in progress |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 5 | 4.593 | 9.593 | 2.498 | 91% |
35% October - 2019 |
Foundation raft completed. Ist Floor Column is in progress |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 5 | 4.593 | 9.593 | 2.498 | 91% |
35% September - 2019 |
Foundation raft completed. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 20 | 16.157 | 21.157 | 2.498 | 91% |
77% May - 2020 |
Fnishing in progress. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 20 | 12.317 | 17.317 | 2.498 | 91% |
63% April - 2020 |
Fnishing in progress. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 20 | 12.317 | 17.317 | 2.498 | 91% |
63% March - 2020 |
Fnishing in progress. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 20 | 12.317 | 17.317 | 2.498 | 91% |
63% February - 2020 |
Fnishing in progress. |
No Image |
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 20 | 12.317 | 17.317 | 2.498 | 91% |
63% January - 2020 |
Shafting of 1st floor slab in progress. |
No Image |
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 778.3 | 778.3 | 778.3 | 9758.928 | 33% |
5% November - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 50 | 25 | 7.296 | 22.018 | 2470.35 | 3% |
1% November - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 778.3 | 778.3 | 778.3 | 9758.928 | 33% |
5% November - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 50 | 25 | 7.296 | 22.018 | 2470.35 | 3% |
1% November - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 1217.371 | 1110.432 | 1110.432 | 9758.928 | 33% |
8% December - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 50 | 30 | 25.889 | 40.611 | 2470.35 | 3% |
2% December - 2018 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 1591.742 | 1591.742 | 1591.742 | 9758.928 | 33% |
11% January - 2019 |
Package - I & 2 Work in progress. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km)
| |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Peshawar PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 50 | 30 | 30 | 44.722 | 2470.35 | 3% |
2% January - 2019 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018.
Summary for additional grant in GoP share approved. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
180315-Construction of District Social Welfare Office Peshawar |
Provincial BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.498 | 5 | 20 | 20 | 5 | 0 | 5 | 2.498 | 91% |
18% August - 2019 |
Foundation raft completed. |
No Image |
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 2054.056 | 2054.056 | 2054.056 | 9758.928 | 33% |
14% April - 2019 |
Package - I & 2 Work in progress. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km)
| |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 207 | 207 | 40 | 54.722 | 2470.35 | 3% |
2% April - 2019 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018.
Summary for additional grant in GoP share approved. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 2054.056 | 2054.056 | 2054.056 | 9758.928 | 33% |
14% March - 2019 |
Package - I & 2 Work in progress. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km)
| |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 207 | 207 | 40 | 54.722 | 2470.35 | 3% |
2% March - 2019 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018.
Summary for additional grant in GoP share approved. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 2054.056 | 2054.056 | 2054.056 | 9758.928 | 33% |
14% March - 2019 |
Package - I & 2 Work in progress. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km)
| |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 207 | 207 | 40 | 54.722 | 2470.35 | 3% |
2% March - 2019 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018.
Summary for additional grant in GoP share approved. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14567.928 | 0 | 4809 | 4809 | 1591.742 | 1591.742 | 1591.742 | 9758.928 | 33% |
11% February - 2019 |
Package - I & 2 Work in progress. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km)
| |||||||||||||||||||
1051 (OG) |
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted). |
Provincial PRIP |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2535.072 | 14.722 | 50 | 50 | 40 | 30 | 44.722 | 2470.35 | 3% |
2% February - 2019 |
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio. PC-I/DCE for Rs.1045.2 m submitted to Chief Infra P&D Deptt on 20/03/2018.
Summary for additional grant in GoP share approved. |
No Image |
Pachage-1
- Shah Alam Sardaryab road (11.8 Km)
- Umerzai-Harichand-Shergarh (29 Km)
- Jandori-Sang-e-Marmar (Western Bypass) (17.5 Km)
Package-2
- Khair Abad-Khi (Nizampur) road (23 Km)
- Risalpur-Pir Sabaq-Misri Banda-Jehangira (37 Km)
- Jandori Sang-e-Marmar (Eastern Bypass) (17 Km)
- Adina-Yar Hussain-Chota Lahore (25 Km)
- Maqsood Kohala Pir Sohawa road (35 Km)
- Dulaization of Hattar-Haripur road (23 Km) | |||||||||||||||||||