Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 32.827 | 16.683 | 7.714 | 34.219 | 0 | 100% |
58% December - 2018 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 32.827 | 16.683 | 5.182 | 31.687 | 0 | 100% |
54% November - 2018 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 32.827 | 16.683 | 5.182 | 31.687 | 0 | 100% |
54% November - 2018 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 33.093 | 33.093 | 16.887 | 43.392 | 0 | 100% |
74% April - 2019 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 33.093 | 33.093 | 14.93 | 41.435 | 0 | 100% |
71% March - 2019 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 33.093 | 33.093 | 14.93 | 41.435 | 0 | 100% |
71% March - 2019 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 32.827 | 32.827 | 11.422 | 37.927 | 0 | 100% |
65% February - 2019 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.Balance Wrok tendered
Will be complted. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.605 | 26.505 | 32.827 | 32.827 | 16.683 | 9.107 | 35.612 | 0 | 100% |
61% January - 2019 |
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. |
No Image |
Phase-V Hayatabad, Peshawar | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
01-01-16 | - | - | 18-10-17 | - | 350 | 97.223 | 50 | 77 | 64.5 | 63.5 | 160.723 | 202.777 | 42% |
46% December - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
- | - | - | 10-09-15 | - | 250 | 97.223 | 50 | 50 | 25 | 17.085 | 114.308 | 102.777 | 59% |
46% September - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. Liability of the contractor is Rs.200 m. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
- | - | - | 10-09-15 | - | 250 | 97.223 | 50 | 50 | 25 | 17.085 | 114.308 | 102.777 | 59% |
46% August - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
- | - | - | 10-09-15 | - | 250 | 97.223 | 50 | 50 | 17.75 | 0 | 97.223 | 102.777 | 59% |
39% July - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.223 | 50 | 50 | 37.5 | 37.5 | 134.723 | 202.777 | 42% |
38% November - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 97.223 | 50 | 50 | 25 | 24.915 | 122.138 | 102.777 | 59% |
49% October - 2017 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. Liability of the contractor is Rs.200 m. |
No Image |
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 108.044 | 108.044 | 108.044 | 205.215 | 202.829 | 42% |
59% June - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 108.044 | 108.044 | 108.046 | 205.217 | 202.829 | 42% |
59% May - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Rs.144.786 m demanded. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 108.044 | 108.044 | 107.848 | 205.019 | 202.829 | 42% |
59% April - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Rs.144.786 m demanded. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 108.044 | 108.044 | 104.848 | 202.019 | 202.829 | 42% |
58% March - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 95.354 | 95.354 | 95.354 | 192.525 | 202.829 | 42% |
55% February - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m. |
ADP's Images |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1063 (OG) |
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 97.171 | 50 | 95.354 | 95.354 | 95.354 | 192.525 | 202.829 | 42% |
55% January - 2018 |
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m. |
No Image |
Pages : 1 |