Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2018, February - 2019, February - 2018, March - 2018, March - 2019, April - 2018, April - 2019, May - 2018, June - 2018, July - 2017, August - 2017, September - 2017, October - 2017, November - 2018, November - 2017, December - 2018, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 32.827 16.683 7.714 34.219 0 100% 58%
December - 2018
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 32.827 16.683 5.182 31.687 0 100% 54%
November - 2018
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 32.827 16.683 5.182 31.687 0 100% 54%
November - 2018
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 33.093 33.093 16.887 43.392 0 100% 74%
April - 2019
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 33.093 33.093 14.93 41.435 0 100% 71%
March - 2019
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 33.093 33.093 14.93 41.435 0 100% 71%
March - 2019
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress. Balance wrok tendered. Will be completed.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 32.827 32.827 11.422 37.927 0 100% 65%
February - 2019
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.Balance Wrok tendered Will be complted.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150447-Construction of T.A.B.D.E.E.L.I Centre at Hayatabad Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 58.605 26.505 32.827 32.827 16.683 9.107 35.612 0 100% 61%
January - 2019
Drawing approved by PDA on 03/06/2017. Basement completed. GF in progress.
No Image
Phase-V Hayatabad, Peshawar
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
01-01-16 - - 18-10-17 - 350 97.223 50 77 64.5 63.5 160.723 202.777 42% 46%
December - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
- - - 10-09-15 - 250 97.223 50 50 25 17.085 114.308 102.777 59% 46%
September - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. Liability of the contractor is Rs.200 m.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
- - - 10-09-15 - 250 97.223 50 50 25 17.085 114.308 102.777 59% 46%
August - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
- - - 10-09-15 - 250 97.223 50 50 17.75 0 97.223 102.777 59% 39%
July - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.223 50 50 37.5 37.5 134.723 202.777 42% 38%
November - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 250 97.223 50 50 25 24.915 122.138 102.777 59% 49%
October - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. Liability of the contractor is Rs.200 m.
No Image
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 108.044 108.044 108.044 205.215 202.829 42% 59%
June - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process.
No Image
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km)
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 108.044 108.044 108.046 205.217 202.829 42% 59%
May - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Rs.144.786 m demanded.
No Image
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km)
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 108.044 108.044 107.848 205.019 202.829 42% 59%
April - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Rs.144.786 m demanded.
No Image
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km)
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 108.044 108.044 104.848 202.019 202.829 42% 58%
March - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m.
No Image
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km)
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 95.354 95.354 95.354 192.525 202.829 42% 55%
February - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m.
ADP's Images
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km)
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 350 97.171 50 95.354 95.354 95.354 192.525 202.829 42% 55%
January - 2018
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Liability of the contractor is Rs.200 m.
No Image
Pages : 1