Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
- | 30-06-18 | - | 03-03-17 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 9.799 | 10.772 | 0 | 100% |
33% December - 2017 |
Working piles in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 9.799 | 10.772 | 0 | 100% |
33% November - 2017 |
Working piles in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 9.714 | 10.687 | 0 | 100% |
33% October - 2017 |
Working piles in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
- | 30-06-18 | - | 03-03-17 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 2.714 | 3.687 | 0 | 100% |
11% September - 2017 |
Work piles in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
- | 30-06-18 | - | 03-03-17 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 2.714 | 3.687 | 0 | 100% |
11% August - 2017 |
Work piles in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
- | 30-06-18 | - | 03-03-17 | - | 32.53 | 0.973 | 31.558 | 31.558 | 11.203 | 0 | 0.973 | 0 | 100% |
3% July - 2017 |
Test pile completed. |
No Image |
PK-25 | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 15.717 | 16.849 | 15.717 | 16.69 | 0 | 100% |
51% June - 2018 |
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 31.558 | 15.717 | 16.69 | 0 | 100% |
51% May - 2018 |
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress. Amount to the tune of Rs. 3.25 M required for completion. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 31.558 | 15.717 | 16.69 | 0 | 100% |
51% April - 2018 |
Bridge (30 mtr 2 span) - girders, transum, abutment completed. Slab in progress. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 31.558 | 15.717 | 16.69 | 0 | 100% |
51% March - 2018 |
Bridge (30 mtr 2 span) - girders, transum, abutment completed. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 15.717 | 16.69 | 0 | 100% |
51% February - 2018 |
Girders in progress. |
ADP's Images |
Bridge Shifted to Lar Jabba PK-25, Mardan ( 2 Span 30 m each ) | |||||||||||||||||||
1075 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan. |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 0.973 | 31.558 | 31.558 | 15.779 | 15.717 | 16.69 | 0 | 100% |
51% January - 2018 |
Girders in progress. |
No Image |
PK-25 | |||||||||||||||||||
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1075 (New) |
200300-Establishment of Oxygen Plant. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |