Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
28-10-15 | - | - | 22-01-15 | - | 144 | 31.744 | 20 | 17.1 | 12.1 | 12.1 | 43.844 | 92.256 | 36% |
30% December - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Liability Rs.25 m. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
28-10-15 | - | - | 22-01-15 | - | 144 | 31.744 | 20 | 20 | 7.1 | 7.1 | 38.844 | 92.256 | 36% |
27% September - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Laibility Rs.25 m. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
28-10-15 | - | - | 22-01-15 | - | 144 | 31.744 | 20 | 20 | 7.1 | 7.1 | 38.844 | 92.256 | 36% |
27% August - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
28-10-15 | - | - | 22-01-15 | - | 144 | 31.744 | 20 | 20 | 7.1 | 0 | 31.744 | 92.256 | 36% |
22% July - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 17.1 | 12.1 | 12.1 | 43.844 | 92.256 | 36% |
30% November - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Laibility Rs.25 m. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 20 | 7.1 | 7.1 | 38.844 | 92.256 | 36% |
27% October - 2017 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Laibility Rs.25 m. |
No Image |
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 70.508 | 70.508 | 70.508 | 102.252 | 92.256 | 36% |
71% June - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
PK-79 Buner | |||||||||||||||||||
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 70.515 | 70.515 | 70.508 | 102.252 | 92.256 | 36% |
71% May - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
PK-79 Buner | |||||||||||||||||||
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 70.515 | 70.515 | 68.813 | 100.557 | 92.256 | 36% |
70% April - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
PK-79 Buner | |||||||||||||||||||
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 70.515 | 70.515 | 42.131 | 73.875 | 92.256 | 36% |
51% March - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
No Image |
PK-79 Buner | |||||||||||||||||||
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 20.515 | 20.515 | 20.515 | 52.259 | 92.256 | 36% |
36% February - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. |
ADP's Images |
PK-79 Buner | |||||||||||||||||||
1097 (OG) |
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 144 | 31.744 | 20 | 20.515 | 20.515 | 12.1 | 43.844 | 92.256 | 36% |
30% January - 2018 |
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Liability Rs.25 m. |
No Image |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- December - 2020 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- December - 2020 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- October - 2020 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- September - 2020 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- August - 2020 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- May - 2021 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- April - 2021 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- March - 2021 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- February - 2021 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
- January - 2021 |
No Image | |
1097 (OG) |
193193-Establishment of Technical Institute at Wana in SWA, (A) BOD/26-12-2017 [FDA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.613 | 178.259 | 0 | 0 | 0 | 0 | 178.259 | 0 | - |
July - 2020 |
No Image | |