Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1127 (New) |
180566-Construction of Recreational Park at Hund Swabi |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 110 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
1127 (New) |
200060-Development of Small Indutrial Estate on Bannu Miranshah Road, NW (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 191 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
10-02-16 | 30-06-18 | - | 20-08-15 | - | 45 | 29 | 15 | 15 | 11.25 | 11.25 | 40.25 | 1 | 98% |
89% December - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 11.25 | 8.542 | 37.542 | 1 | 98% |
83% November - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 7.5 | 5.325 | 34.325 | 1 | 98% |
76% October - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
10-02-16 | 30-06-18 | - | 20-08-15 | - | 45 | 29 | 15 | 15 | 7.5 | 5.325 | 34.325 | 1 | 98% |
76% September - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
10-02-16 | 30-06-18 | - | 20-08-15 | - | 45 | 29 | 15 | 15 | 7.5 | 5.325 | 34.325 | 1 | 98% |
76% August - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
10-02-16 | 30-06-18 | - | 20-08-15 | - | 45 | 29 | 15 | 15 | 5.325 | 0 | 29 | 1 | 98% |
64% July - 2017 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 12.31 | 14.19 | 12.31 | 41.31 | 1 | 98% |
92% June - 2018 |
Completed (2.6 Km). |
No Image |
PK-81, Swat (2.60 Km) | |||||||||||||||||||
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 15 | 11.25 | 40.25 | 1 | 98% |
89% May - 2018 |
Completed (2.6 Km). |
No Image |
PK-81, Swat (2.60 Km) | |||||||||||||||||||
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 15 | 11.25 | 40.25 | 1 | 98% |
89% April - 2018 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
PK-81, Swat (2.60 Km) | |||||||||||||||||||
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 15 | 11.25 | 40.25 | 1 | 98% |
89% March - 2018 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
PK-81, Swat (2.60 Km) | |||||||||||||||||||
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 11.25 | 11.25 | 40.25 | 1 | 98% |
89% February - 2018 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
ADP's Images |
PK-81, Swat | |||||||||||||||||||
1127 (OG) |
150947-Construction of Mingora Kokray Marghuzar road District Swat. |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 29 | 15 | 15 | 11.25 | 11.25 | 40.25 | 1 | 98% |
89% January - 2018 |
Length 2.6 Km - road work completed, ancillary works in completion stage. |
No Image |
Pages : 1 |