Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
11-10-12 | - | - | 11-02-15 | - | 255.368 | 162.76 | 15 | 12.825 | 9.075 | 9.073 | 171.833 | 77.608 | 70% |
67% December - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
11-10-12 | - | - | 11-02-15 | - | 255.368 | 162.76 | 15 | 15 | 5.325 | 5.28 | 168.04 | 77.608 | 70% |
66% September - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
11-10-12 | - | - | 11-02-15 | - | 255.368 | 162.76 | 15 | 15 | 5.325 | 5.28 | 168.04 | 77.608 | 70% |
66% August - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
11-10-12 | - | - | 11-02-15 | - | 255.368 | 162.76 | 15 | 15 | 5.325 | 0 | 162.76 | 77.608 | 70% |
64% July - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 12.825 | 9.075 | 9.073 | 171.833 | 77.608 | 70% |
67% November - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 15 | 9.075 | 5.28 | 168.04 | 77.608 | 70% |
66% October - 2017 |
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 11.163 | 11.163 | 11.163 | 173.923 | 77.608 | 70% |
68% June - 2018 |
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 16.795 | 16.795 | 9.07 | 171.83 | 77.608 | 70% |
67% May - 2018 |
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 16.795 | 16.795 | 10.12 | 172.88 | 77.608 | 70% |
68% April - 2018 |
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 16.795 | 16.795 | 9.075 | 171.835 | 77.608 | 70% |
67% March - 2018 |
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 14.105 | 14.105 | 9.073 | 171.833 | 77.608 | 70% |
67% February - 2018 |
opriginal Scope - 10 km (PCC 14 ft wide) - complted . Revised Scope (4ft additional PCC ) in progress |
ADP's Images |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 162.76 | 15 | 14.105 | 14.105 | 9.073 | 171.833 | 77.608 | 70% |
67% January - 2018 |
10 Km - PCC 10 Km (14 feet) - completed. PCC 3 Km (4 feet) - completed. |
No Image |
PK-92 (Km-1 to 10) | |||||||||||||||||||
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
1144 (OG) |
190350-Strengthening of Legislation Wing of Law Department,Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 64.452 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |