1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 12.5 | 245.5 | 0 | 100% |
95% December - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 12.5 | 245.5 | 0 | 100% |
95% December - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 6 | 239 | 0 | 100% |
93% October - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 6 | 239 | 0 | 100% |
93% September - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 6.5 | 239.5 | 0 | 100% |
93% August - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 0 | 0 | 0 | 233 | 0 | 100% |
90% July - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 25 | 25 | 258 | 0 | 100% |
100% May - 2021 |
PC-II: Rs. 10.M on
dated: 18-02-13
01-Unit
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 25 | 25 | 258 | 0 | 100% |
100% April - 2021 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 25 | 25 | 258 | 0 | 100% |
100% March - 2021 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 25 | 25 | 258 | 0 | 100% |
100% February - 2021 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 233 | 25 | 25 | 12.5 | 12.5 | 245.5 | 0 | 100% |
95% January - 2021 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
01-07-15 | 30-06-18 | - | 15-09-17 | - | 150 | 47.905 | 101.345 | 101.345 | 76.008 | 35.815 | 83.72 | 0.75 | 100% |
56% December - 2017 |
Length 5 Km - 3.5 Km completed. |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
01-07-15 | 30-06-18 | - | 22-01-15 | - | 150 | 47.905 | 101.345 | 101.345 | 50.672 | 35.815 | 83.72 | 0.75 | 100% |
56% September - 2017 |
Length 5 Km - structure work. WBM on both side in progress. |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
01-07-15 | 30-06-18 | - | 22-01-15 | - | 100 | 47.905 | 101.345 | 101.345 | 50.672 | 32 | 79.905 | 0 | 100% |
80% August - 2017 |
Length 5 Km - structure work. WBM on both side in progress. Revised PC-I submitted. Pre-PDWP held. |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
01-07-15 | 30-06-18 | - | 22-01-15 | - | 100 | 47.905 | 101.345 | 101.345 | 35.977 | 0 | 47.905 | 0 | 100% |
48% July - 2017 |
Length 5 Km - structure work. WBM on both side in progress. Revised PC-I submitted. Pre-PDWP held. |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 76.008 | 35.815 | 83.72 | 0.75 | 100% |
56% November - 2017 |
Length 5 Km - 3.5 Km completed |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 50.672 | 35.815 | 83.72 | 0.75 | 100% |
56% October - 2017 |
Length 5 Km - 3.5 Km completed |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 55.209 | 55.209 | 55.209 | 103.114 | 0.75 | 100% |
69% June - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Cannot be completed because of the work in progress on the revsied scope of work. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 101.344 | 55.209 | 103.114 | 0.75 | 100% |
69% May - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Canot be complted because of the work in progress on the revsied scope of work. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 101.344 | 48.115 | 96.02 | 0.75 | 100% |
64% April - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 76.008 | 48.115 | 96.02 | 0.75 | 100% |
64% March - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 76.008 | 35.815 | 83.72 | 0.75 | 100% |
56% February - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. |
No Image |
1147 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 47.905 | 101.345 | 101.345 | 76.008 | 35.815 | 83.72 | 0.75 | 100% |
56% January - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. |
No Image |