Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
- | - | - | 15-09-17 | - | 300 | 0 | 10 | 10 | 2.5 | 0 | 0 | 290 | 3% |
- December - 2017 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.300 m approved. AA awaited. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.300 m submitted to P&D. Pre-PDWP held. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
- | - | - | - | Line Deptt | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.300 m submitted to SE on 26/07/2017. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 2.5 | 0 | 0 | 290 | 3% |
- November - 2017 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 0 | 0 | 0 | 290 | 3% |
- October - 2017 |
Pre-qualification of contractors opened on 01/11/2017. |
No Image |
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% June - 2018 |
19 units (PCC) - work order issued. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% May - 2018 |
19 units (PCC) - work order issued. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 10 | 10 | 10 | 290 | 3% |
3% April - 2018 |
19 units (PCC) - work order issued. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 2.5 | 0 | 0 | 290 | 3% |
- March - 2018 |
19 units (PCC) - work order issued. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 2.5 | 0 | 0 | 290 | 3% |
- February - 2018 |
Units -19 (PCC ) Tendering in progress. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (New) |
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 300 | 0 | 10 | 10 | 2.5 | 0 | 0 | 290 | 3% |
- January - 2018 |
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited. |
No Image |
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam | |||||||||||||||||||
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- December - 2020 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- December - 2020 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- October - 2020 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- September - 2020 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- August - 2020 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 0 | 0 | 0 | 10 | 0 |
July - 2020 |
No Image | ||
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- May - 2021 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- April - 2021 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- March - 2021 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- February - 2021 |
No Image | |
1233 (OG) |
191621-170124-Construction of Small Bridge for Taritang, Gowder and Village Cheena of Kurram Agency. (Phase-I) [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.11 | 10 | 28.11 | 28.11 | 0 | 0 | 10 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |