Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 10.464 | 10.464 | 71.756 | 22.053 | 76% |
76% December - 2020 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 10.464 | 10.464 | 71.756 | 22.053 | 76% |
76% December - 2020 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 12.696 | 10.454 | 71.746 | 22.053 | 76% |
76% October - 2020 |
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
P-II: 28 M as per AA |
No Image |
Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 10.454 | 10.454 | 71.746 | 22.053 | 76% |
76% September - 2020 |
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
P-II: 28 M as per AA |
No Image |
Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 10.454 | 10.454 | 71.746 | 22.053 | 76% |
76% August - 2020 |
Building Completed.
Boundary Wall in Progress.
RCC Column completed.
Bore completed.
P-II: 28 M as per AA |
No Image |
Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 0 | 0 | 0 | 61.292 | 22.053 | 76% |
65% July - 2020 |
Building Completed.
Boundary Wall in Progress.
RCC Column completed |
No Image |
Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 0 | 10.464 | 39.046 | 39.046 | 29.679 | 0 | 0 |
May - 2021 |
01-Unit
M. Building Completed.
Boundary Wall completed.
Dev: work 95% Completed
Int: Elec: Completed
Bore Hole Completed
Fire Fighting Completed
Sewerage System Completed
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image | |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 0 | 10.464 | 14.464 | 14.464 | 14.464 | 0 | 0 |
April - 2021 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image | |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 0 | 10.464 | 14.464 | 14.464 | 14.464 | 0 | 0 |
March - 2021 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image | |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 0 | 10.464 | 14.464 | 14.464 | 14.464 | 0 | 0 |
February - 2021 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image | |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
1449 (OG) |
170167-Reconstruction of C&W Office, Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.809 | 61.292 | 10.464 | 10.464 | 10.464 | 10.464 | 71.756 | 22.053 | 76% |
76% January - 2021 |
Building Completed.
Building Completed.
Boundary Wall completed.
RCC Column completed.
Bore completed.
TS Submitted to SE.
P-II: Balance Funds.
Demand: 28.582 M. |
No Image |
1. Reconstruction of C&W Office, Kohat | |||||||||||||||||||
Pages : 1 |