1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 25 | 133.877 | 36.193 | 81% |
69% December - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 25 | 133.877 | 36.193 | 81% |
69% December - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 25 | 1.802 | 110.679 | 36.193 | 81% |
57% October - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing course in progress. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 13 | 0 | 108.877 | 36.193 | 81% |
56% September - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing course in progress. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 13 | 0 | 108.877 | 36.193 | 81% |
56% August - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing com 50 M Demand. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 0 | 13 | 0 | 108.877 | 36.193 | 81% |
56% July - 2020 |
Length 10.5 Km - 6.5 Km asphaltic base/wearing com 50 M Demand. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 43.729 | 152.606 | 36.193 | 81% |
78% May - 2021 |
Length 9 Km - 8.6 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 40.613 | 149.49 | 36.193 | 81% |
77% April - 2021 |
Length 9 Km - 8.6 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 34.012 | 142.889 | 36.193 | 81% |
73% March - 2021 |
Length 9 Km - 8.6 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 34.012 | 142.889 | 36.193 | 81% |
73% February - 2021 |
Length 9 Km - 8.6 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |
No Image |
Peshawar | |||||||||||||||||||
1490 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.07 | 108.877 | 50 | 50 | 50 | 34.105 | 142.982 | 36.193 | 81% |
73% January - 2021 |
Length 9 Km - 8.6 Km asphaltic base/wearing course in progress.
P-II : Balance funds.
Demand - Rs 35 M. |