Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2018, July - 2020, August - 2020, September - 2018, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
December - 2020
Completed.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
December - 2020
Completed.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 0 0 0 0 0 0 2.698 - -
October - 2020
Completed.
No Image
153
(OG)
170205-Conversion of 100 Mosque Schools into Primary Schools in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 20.927 0 0 0 0 0 0 20.927 - -
September - 2018
Approved.
No Image
GMPS Barrian PK-48
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 0 0 0 0 0 0 2.698 - -
September - 2020
Completed.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 0 0 0 0 0 0 2.698 - -
August - 2020
Completed.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 0 0 0 0 0 0 2.698 - -
July - 2020
Completed.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
May - 2021
01- Unit Completed.
No Image
Jamia Masjid Siyan Di Trarr, U/C Pattan.
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
April - 2021
Completed.
No Image
Jamia Masjid Siyan Di Trarr, U/C Pattan.
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
March - 2021
Completed.
No Image
Jamia Masjid Siyan Di Trarr, U/C Pattan.
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
February - 2021
Completed.
No Image
Jamia Masjid Siyan Di Trarr, U/C Pattan.
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 2.698 3.296 0 0 0 0 3.296 0 - 100%
January - 2021
Completed.
No Image
Jamia Masjid Siyan Di Trarr, U/C Pattan.
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 0 1.2 1.2 1.2 1.2 1.2 115.401 1% 1%
October - 2020
7 units - 6 completed 1 unit ( Hafiz jee ) in progress.
No Image
05 in Bannu.
    1. Impr
153
(OG)
170205-Conversion of 100 Mosque Schools into Primary Schools in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 52.05 0 0 0 0 0 0 52.05 - -
September - 2018
Foundation in progress.
No Image
1) GMPS Laka Showye Bakka Khel PK-72
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 0 1.2 1.2 1.2 1.2 1.2 115.401 1% 1%
September - 2020
7 units - 6 completed 1 unit ( Hafiz jee ) in progress.
No Image
05 in Bannu.
    1. Impr
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 0 0 0 0 0 0 116.601 - -
August - 2020
7 units - 6 completed 1 unit ( Hafiz jee ) in progress.
No Image
05 in Bannu.
    1. Impr
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 0 0 0 0 0 0 116.601 - -
July - 2020
7 units - 1 in progress, 6 Tender floated on 04/04
No Image
05 in Bannu.
    1. Impr
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 65 3.2 3.2 3.2 3.2 68.2 48.401 58% 58%
May - 2021
07- Units 1. Completed 2. Completed 3. Completed 4. Basement + G.F roof liad F.F Rood liad. Ablution Basement G.F, F.F Finishing stage 5. Completed 6. Site shift to Chakdadan & Revised AA issued on 12-12-19, B.B work completed 7. Completed
No Image
1 Masjid Haji Bakhta Baz Khan  (TS 4.5)
2 Masjid Ghazi Khan Baka Khel
3 Masjid at Kotka Faridullah Khan Baka Khel
4 Markzai Jamia Masjid Hafiz Gee (Eid Gah)
5 Jamia Masjid Manduri atal Shah   (TS 1.999)
6 Masjid in Bada Khel    (TS 2.00)
7 Faizullah Khan Masjid   (TS 2.185)
 
Scope of work:
  • Civil work
  • 24x20 Mosque
  • 08 Kanal (Base+II) + B/W
  • Renovation of 02 Labs
  • Hafiz G = B+2 (80x40)
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 65 3.2 3.2 3.2 3.2 68.2 48.401 58% 58%
April - 2021
7 units - 5 completed 6 unit ( Hafiz jee ) in progress.
No Image
1 Masjid Haji Bakhta Baz Khan  (TS 4.5)
2 Masjid Ghazi Khan Baka Khel
3 Masjid at Kotka Faridullah Khan Baka Khel
4 Markzai Jamia Masjid Hafiz Gee (Eid Gah)
5 Jamia Masjid Manduri atal Shah   (TS 1.999)
6 Masjid in Bada Khel    (TS 2.00)
7 Faizullah Khan Masjid   (TS 2.185)
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 65 3.2 3.2 3.2 3.2 68.2 48.401 58% 58%
March - 2021
7 units - 5 completed 6 unit ( Hafiz jee ) in progress.
No Image
1 Masjid Haji Bakhta Baz Khan  (TS 4.5)
2 Masjid Ghazi Khan Baka Khel
3 Masjid at Kotka Faridullah Khan Baka Khel
4 Markzai Jamia Masjid Hafiz Gee (Eid Gah)
5 Jamia Masjid Manduri atal Shah   (TS 1.999)
6 Masjid in Bada Khel    (TS 2.00)
7 Faizullah Khan Masjid   (TS 2.185)
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 65 3.2 3.2 3.2 3.2 68.2 48.401 58% 58%
February - 2021
7 units - 5 completed 6 unit ( Hafiz jee ) in progress.
No Image
1 Masjid Haji Bakhta Baz Khan  (TS 4.5)
2 Masjid Ghazi Khan Baka Khel
3 Masjid at Kotka Faridullah Khan Baka Khel
4 Markzai Jamia Masjid Hafiz Gee (Eid Gah)
5 Jamia Masjid Manduri atal Shah   (TS 1.999)
6 Masjid in Bada Khel    (TS 2.00)
7 Faizullah Khan Masjid   (TS 2.185)
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Bannu
30-11--1 30-11--1 - 30-11--1 - 116.601 65 3.2 3.2 3.2 3.2 68.2 48.401 58% 58%
January - 2021
7 units - 5 completed 6 unit ( Hafiz jee ) in progress.
No Image
05 in Bannu.
    1. Impr
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
October - 2020
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
September - 2020
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
August - 2020
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
July - 2020
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
May - 2021
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
April - 2021
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
March - 2021
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
February - 2021
Approved.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 1 0 0 0 0 0 0 1 - -
January - 2021
Approved.
No Image
153
(OG)
170205-Conversion of 100 Mosque Schools into Primary Schools in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 0 0 0 0 0 0 1.566 - -
October - 2020
Completed & H/O.
No Image
153
(OG)
170205-Conversion of 100 Mosque Schools into Primary Schools in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
PC-I/DCE for Rs.18.461 m submitted to DEO M on 17/04/2018.
No Image
GPS Nai Abadi Budh PK-65
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 0 0 0 0 0 0 1.566 - -
September - 2020
Completed & H/O.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 0 0 0 0 0 0 1.566 - -
July - 2020
Completed & H/O.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 1.566 0 0 0 0 1.566 0 - 100%
May - 2021
01- Unit Completed & H/O.
No Image
Fatima-Ul-Zahra at Masjid Siddique Akbar Faqirini Gate D.I.KHan
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 1.566 0 0 0 0 1.566 0 - 100%
April - 2021
Completed & H/O.
No Image
Fatima-Ul-Zahra at Masjid Siddique Akbar Faqirini Gate D.I.KHan
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 1.566 0 0 0 0 1.566 0 - 100%
March - 2021
Completed & H/O.
No Image
Fatima-Ul-Zahra at Masjid Siddique Akbar Faqirini Gate D.I.KHan
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 1.566 0 0 0 0 1.566 0 - 100%
February - 2021
Completed & H/O.
No Image
Fatima-Ul-Zahra at Masjid Siddique Akbar Faqirini Gate D.I.KHan
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 1.566 0 0 0 0 1.566 0 - 100%
January - 2021
Completed & H/O.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
DI.Khan
30-11--1 30-11--1 - 30-11--1 - 1.566 0 0 0 0 0 0 1.566 - -
August - 2020
Completed & H/O.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 2.8 2.8 2.8 2.8 9.692 1.808 84% 84%
December - 2020
04- Units 1 - Work order issued 2 Nos units upto lintel level. 4- work in progress.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 2.8 2.8 2.8 2.8 9.692 1.808 84% 84%
December - 2020
04- Units 1 - Work order issued 2 Nos units upto lintel level. 4- work in progress.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 0.8 0.8 0.8 0 6.892 3.808 67% 60%
October - 2020
04- Units 1 - Work order issued 2 Nos units upto lintel level. 4- work in progress.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 0 0 0 0 6.892 4.608 - 60%
September - 2020
04- Units 1 - Work order issued 2 Nos units upto lintel level. 4- work in progress.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 0 0 0 0 6.892 4.608 - 60%
August - 2020
04- Units 1 - Work order issued 2 Nos units upto lintel level. 4- work in progress.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 0 0 0 0 0 0 11.5 - -
July - 2020
Upto lintel level.
No Image
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 2.8 2.8 2.8 2.8 9.692 1.808 84% 84%
May - 2021
03- Units 1. Completed Upto lintal level 2. Completed Upto lintal level 3. Dag Gosam, Kamangaro Mosque completed and Sabar shah Mosque roof as in progress
No Image
1. Cont: of 2 rooms at Madrassa Mahasinat Academy Sangolai Payeen Balambat? Rs: 2.00 M
2. Const: of 2 rooms at Tahseen Ul Quran Nasafi Snagolai?  Rs: 2.00 M
3. Imp: & Rehab: of Masjids & Madariss .?. Rs: 7.5 M
153
(OG)
180496-Improvement and Rehabilitation of Masajids & Darul ulooms/Deeni Madaris in Khyber Pakhtunkhwa (Phase-III) including Hafiz Jee Masjid, Bannu City.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 11.5 6.892 2.8 2.8 2.8 2.8 9.692 1.808 84% 84%
April - 2021
03- Units 1 - Completed Upto lintal level 2 Completed Upto lintal level 3- Dag Gosam, Kamangaro Mosque completed and Sabar shah Mosque roof as in progress
No Image
1. Cont: of 2 rooms at Madrassa Mahasinat Academy Sangolai Payeen Balambat? Rs: 2.00 M
2. Const: of 2 rooms at Tahseen Ul Quran Nasafi Snagolai?  Rs: 2.00 M
3. Imp: & Rehab: of Masjids & Madariss .?. Rs: 7.5 M