Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 16.963 | 359.18 | 417.783 | 48% |
45% December - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 16.963 | 359.18 | 417.783 | 48% |
45% December - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 20 | 20 | 362.217 | 417.783 | 48% |
45% October - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 10 | 10 | 352.217 | 417.783 | 48% |
44% September - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 10 | 10 | 352.217 | 417.783 | 48% |
44% August - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.22 | 40 | 0 | 10 | 0 | 342.22 | 417.78 | 48% |
43% July - 2020 |
Length 22.3 Km (15 units) - 8 Km asphalt completed |
No Image |
1) Boko to Tashkand road (2 Km) Package-1 | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 40 | 382.217 | 417.783 | 48% |
48% March - 2021 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 40 | 382.217 | 417.783 | 48% |
48% February - 2021 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 27.832 | 370.049 | 417.783 | 48% |
46% January - 2021 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued. |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 40 | 382.217 | 417.783 | 48% |
48% May - 2021 |
15- Units
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued.
Demand Rs: 20 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
1542 (OG) |
150853-F/S,Des/const of road pav: Boko-Tashkand, Jhanda-Pajaman, Bada CP via Mangal Chai-Gabasni, Marguz-Yusfi, Pabni, Zarobi, Kalaba Khazana, Sharshami Lar Kota, Yara Khel, Kalabat Topi, Gandf Lar, Nary Lar, Arbzo-Tariq Maneri Pyan,...Jehngira-Dra vill, |
Swabi HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 800 | 342.217 | 40 | 40 | 40 | 40 | 382.217 | 417.783 | 48% |
48% April - 2021 |
Length 22.3 Km (15 units) - 8 Km asphalt completed. All Works , Work order issued.
Demand Rs: 20 M |
No Image |
1) Boko to Tashkand road (2 Km) Package-1
2) Boko to Tashkand road (2.80 Km) Package-2
3) Jhanda Panjmanroad (0.457 Km)
4) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-1
5) Bada Check Post via Mangal Chai to Gabasni road (2 Km) Package-2
6) Bada Check Post via Mangal Chai to Gabasni road (1.80 Km) Package-3
7) Marghuz Yousafi road (2.80 Km)
8) Pabani road (1 Km)
9) Zaroobi road (5 Km)
10) Kalabat Khazana road (1 Km)
11) Sharshami Lar Kotha road (1.4 Km)
12) Yara Khel Lar Kotha road (1.6 Km)
13) Kalabat Topi Swabi raod (1 Km)
14) Pabinin road (Gandaf Lar) (1 Km)
15) Kotha Swabi raod Naray Lar (1 Km) | |||||||||||||||||||
Pages : 1 |