Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.146 | 0 | 0 | 0 | 0 | 0 | 0 | 35.146 | - |
- September - 2018 |
2 units - 1 work order issued, 1 tender floated on 10/09/2018. |
No Image |
1) GGPS Khwajamad Landidak PK-72 2) GPS Farman Maznaga PK-72 | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1 | 1 | 1 | 0.769 | 0.769 | 0.5 | 67% |
51% May - 2021 |
02- Units
1. Completed
2. Site Issue |
No Image |
1. Janazgah at Kalpani ? Rs; 1.0 M
2. Janzagah at Karapa Shahedan ? Rs; 0.5 M
Scope of work:
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1 | 1 | 1 | 0.769 | 0.769 | 0.5 | 67% |
51% April - 2021 |
02 units
1. completed
2. layout given |
No Image |
1. Janazgah at Kalpani ? Rs; 1.0 M
2. Janzagah at Karapa Shahedan ? Rs; 0.5 M | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1 | 1 | 1 | 0.769 | 0.769 | 0.5 | 67% |
51% March - 2021 |
02 units
1. completed
2. layout given |
No Image |
1. Janazgah at Kalpani ? Rs; 1.0 M
2. Janzagah at Karapa Shahedan ? Rs; 0.5 M | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1 | 1 | 1 | 0.769 | 0.769 | 0.5 | 67% |
51% February - 2021 |
02 units
1. completed
2. layout given |
No Image |
1. Janazgah at Kalpani ? Rs; 1.0 M
2. Janzagah at Karapa Shahedan ? Rs; 0.5 M | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0.446 | 0.446 | 0 | 100% |
30% January - 2021 |
Plinth level completed, B/B work in progress |
No Image |
1. Janazgah at Kalpani
2. Janzagah at Karapa Shahedan | |||||||||||||||||||
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
PC-I/DCE for Rs.18.926 m (GPS No.2 Charsadda) and Rs.18.876 m (GPS Matta PK-22) submitted to DEO M on 16/02/2018 and 07/04/2018. |
No Image |
1) GPS No.2 Charsadda
2) GPS Matta PK-22 | |||||||||||||||||||
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
No Image | |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 0 | 8.43 | 8.43 | 8.43 | 2.5 | 2.5 | 1.57 | 84% |
25% May - 2021 |
02- Units
All work in progess |
No Image |
1. Janazgah at Didargah Garum Chashma
2. Janzagah at Main Eid Gah Ayun Balausht | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 0 | 8.43 | 8.43 | 8.43 | 2.5 | 2.5 | 1.57 | 84% |
25% April - 2021 |
02- units all work in proges |
No Image |
1. Janazgah at Didargah Garum Chashma
2. Janzagah at Main Eid Gah Ayun Balausht | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 0 | 8.43 | 8.43 | 8.43 | 2 | 2 | 1.57 | 84% |
20% March - 2021 |
02- units all work in proges |
No Image |
1. Janazgah at Didargah Garum Chashma
2. Janzagah at Main Eid Gah Ayun Balausht | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 0 | 8.43 | 8.43 | 8.43 | 2 | 2 | 1.57 | 84% |
20% February - 2021 |
02- units all work in proges |
No Image |
1. Janazgah at Didargah Garum Chashma
2. Janzagah at Main Eid Gah Ayun Balausht | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 0 | 0 | 0 | 0 | 0 | 0 | 10 | - |
- January - 2021 |
work in proges |
No Image |
1. Janazgah at Didargah Garum Chashma
2. Janzagah at Main Eid Gah Ayun Balausht | |||||||||||||||||||
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 0 | 0 | 0 | 0 | 0 | 0 | 62.375 | - |
- September - 2018 |
Approved. |
No Image |
1) GPS Nasrat PK-91 2) GPS Atirkon PK-92 3) GPS Panjkoro PK-93 | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.197 | 1.197 | 2.5 | 38% |
30% December - 2020 |
Work started. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.197 | 1.197 | 2.5 | 38% |
30% December - 2020 |
Work started. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- October - 2020 |
Work order issued site not H/O. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- September - 2020 |
Work order issued site not H/O. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- August - 2020 |
Work order issued site not H/O. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.282 | 1.282 | 2.5 | 38% |
32% May - 2021 |
01- Unit
1. Site dispute
2. Roof laid |
No Image |
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.282 | 1.282 | 2.5 | 38% |
32% April - 2021 |
Hall Roof laid |
No Image |
Janzgha at Village Ghazni Khel & Kaka Khel Lakki Marwat | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.282 | 1.282 | 2.5 | 38% |
32% March - 2021 |
Hall Roof laid |
No Image |
Janzgha at Village Ghazni Khel & Kaka Khel Lakki Marwat | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.282 | 1.282 | 2.5 | 38% |
32% February - 2021 |
Hall Roof laid |
No Image |
Janzgha at Village Ghazni Khel & Kaka Khel Lakki Marwat | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 0 | 1.5 | 1.5 | 1.5 | 1.282 | 1.282 | 2.5 | 38% |
32% January - 2021 |
Work started. |
No Image |
Janzgha at Village Ghazni Khel & Kaka Khel Lakki Marwat | |||||||||||||||||||
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
PC-I/DCE for Rs.18.960 m, Rs.18.897 m and Rs.18.851 m submitted to DEO Male on 15/05/2018 and 19/03/2018 respectively. |
No Image |
1) GPS Sohai Bandi UC Lassan Nawab PK-32
2) GPS Chajri Payeen
3) GPS Ranian | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 0.386 | 2.886 | 3.83 | 52% |
36% December - 2020 |
work in progress |
No Image |
1) U/C Khazana Dheri Pk-53
2) U/C Mahoo Dheri Pk-53
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 0.386 | 2.886 | 3.83 | 52% |
36% December - 2020 |
work in progress |
No Image |
1) U/C Khazana Dheri Pk-53
2) U/C Mahoo Dheri Pk-53
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.5 | 1.5 | 1.5 | 0 | 2.5 | 4 | 50% |
31% October - 2020 |
Procurement under process. |
No Image |
1) U/C Khazana Dheri Pk-53
2) U/C Mahoo Dheri Pk-53
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 0 | 7.17 | 7.17 | 7.17 | 2.7 | 0 | 0 |
May - 2021 |
02- Units
1 Grey Strcture completed
2 Site not yet handed over |
No Image | |
1) U/C Khazana Dheri Pk-53 .?.. RS: 4.00
2) U/C Mahoo Dheri Pk-53 .?.. RS: 4.00
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 1.592 | 4.092 | 3.83 | 52% |
51% April - 2021 |
02 Units
1 Grey Strcture completed
2 Site not yet handed over |
No Image |
1) U/C Khazana Dheri Pk-53 .?.. RS: 4.00
2) U/C Mahoo Dheri Pk-53 .?.. RS: 4.00
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 1.52 | 4.02 | 3.83 | 52% |
50% March - 2021 |
02 Units
1 Grey Strcture completed
2 Site not yet handed over |
No Image |
1) U/C Khazana Dheri Pk-53 .?.. RS: 4.00
2) U/C Mahoo Dheri Pk-53 .?.. RS: 4.00
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 1.52 | 4.02 | 3.83 | 52% |
50% February - 2021 |
02 Units
1 Grey Strcture completed
2 Site not yet handed over |
No Image |
1) U/C Khazana Dheri Pk-53 .?.. RS: 4.00
2) U/C Mahoo Dheri Pk-53 .?.. RS: 4.00
| |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 2.5 | 1.67 | 1.67 | 1.67 | 0.386 | 2.886 | 3.83 | 52% |
36% January - 2021 |
work in progress |
No Image |
1) U/C Khazana Dheri Pk-53
2) U/C Mahoo Dheri Pk-53
| |||||||||||||||||||
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 102.217 | 0 | 0 | 0 | 0 | 0 | 0 | 102.217 | - |
- September - 2018 |
4 units - all 4 work order issued, site not handed over. |
No Image |
1) GGPS Taru Jabba PK-12
2) GGPS Banda Sheikh Ismail PK-13
3) GGPS No.1 Dagi Qadeem PK-13
4) GGPS No.1 Manki Sharif PK-13
5) GPS Garhi Momin PK-13 | |||||||||||||||||||
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.523 | 2.5 | 1.5 | 1.5 | 1.5 | 0 | 2.5 | 30.523 | 12% |
7% October - 2020 |
Work in progress. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.523 | 2.5 | 1.5 | 1.5 | 1.5 | 0 | 2.5 | 30.523 | 12% |
7% September - 2020 |
Work in progress. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34.523 | 2.5 | 8.43 | 8.43 | 0 | 0 | 2.5 | 23.593 | 32% |
7% August - 2020 |
Work in progress. |
No Image |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 10 | 0 | 0 | 0 | 0 | 10 | 0 | - |
- October - 2020 |
No Image | |
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
No Image | |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 10 | 0 | 0 | 0 | 0 | 10 | 0 | - |
- September - 2020 |
No Image | |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 10 | 0 | 0 | 0 | 0 | 10 | 0 | - |
- August - 2020 |
No Image | |
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1200 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
No Image | |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 10 | 8.43 | 0 | 0 | 0 | 10 | 0 | - |
- July - 2020 |
No Image | |
156 (OG) |
190077-Construction of Eid Gah & Janazgah in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 10 | 0 | 0 | 0 | 0 | 10 | 0 | - |
- February - 2021 |
No Image | |
156 (OG) |
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.184 | 0 | 0 | 0 | 0 | 0 | 0 | 43.184 | - |
- September - 2018 |
Work order issued to contractor. |
No Image |
1) GPS Mughai Kot PK-31
2) GPS Spin Kani PK-32
3) GPS Tarkha Dobian PK-33 | |||||||||||||||||||
Pages : 1 |