Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 35 | 35 | 25 | 150.447 | 249.553 | 38% |
38% December - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 35 | 35 | 25 | 150.447 | 249.553 | 38% |
38% December - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 25 | 18.75 | 18.75 | 144.197 | 249.553 | 38% |
36% October - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 25 | 6.25 | 5.5 | 130.947 | 249.553 | 38% |
33% September - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 25 | 6.25 | 0 | 125.447 | 249.553 | 38% |
31% August - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 0 | 6.25 | 0 | 125.447 | 249.553 | 38% |
31% July - 2020 |
Length 21.2 Km (avg 12 ft width) - in progress on |
No Image |
1) Construction of Black Topping of Sowari By | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 157.534 | 25 | 35 | 35 | 35 | 192.534 | 217.466 | 46% |
48% March - 2021 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 157.534 | 25 | 35 | 35 | 35 | 192.534 | 217.466 | 46% |
48% February - 2021 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 125.447 | 25 | 35 | 35 | 35 | 160.447 | 249.553 | 38% |
40% January - 2021 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 157.534 | 25 | 84 | 84 | 82.716 | 240.25 | 217.466 | 46% |
60% May - 2021 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
1578 (OG) |
150803-a) Impt and B/T of 15 km roads b) construction and B/T of Swari Bypass road c) Construction/extension & BT of Battara Akhun Kalay road via Koz shamnal (i/c Cost of Land), Buner. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 157.534 | 25 | 84 | 84 | 82.716 | 240.25 | 217.466 | 46% |
60% April - 2021 |
Length 21.2 Km (avg 12 ft width) - in progress
Liability : 50 M |
No Image |
1) Construction of Black Topping of Sowari Bypass road 2 Km
2) Construction/extension and Black Topping of Akhun Kaley road via Kuz Shamnal road 6.10 Km
3) Improvement and Black Topping of road from Barkandaza Loya Lar Dagari road 2 Km
4) Improvement and Black Topping of road Inzar Maira road 1 Km
5) Improvement and Black Topping of road from Shalpandi Mian road to Shalbandi village 1.275 Km
6) Improvement, widening and extension of Pandar to Raman Tangi road 2 Km
7) Improvement, widening and extension of Raman Tangi to Tera road 3 Km
8) Improvement and Black Topping of road from Gunga Hujra to Kulyri village 2.350 Km
9) Improvement and Black Topping of Dagare Nara and Narei Tangai road 2.40 Km
10) Improvement and Black Topping of Shaptalo and Shangra road 1.20 Km | |||||||||||||||||||
Pages : 1 |