Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 80 | 80 | 24.13 | 34.13 | 110 | 27% |
23% December - 2020 |
Work in progress.
P-II : Balance Funds. |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 80 | 80 | 24.13 | 34.13 | 110 | 27% |
23% December - 2020 |
Work in progress.
P-II : Balance Funds. |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 30 | 7.5 | 7.5 | 17.5 | 110 | 27% |
12% October - 2020 |
Work in progress.
P-II : Rs. 135 M |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 30 | 5 | 0 | 10 | 110 | 27% |
7% September - 2020 |
Work in progress.
P-II : Rs. 135 M |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 30 | 5 | 0 | 10 | 110 | 27% |
7% August - 2020 |
Work in progress.
P-II : Rs. 135 M |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 0 | 5 | 0 | 10 | 110 | 27% |
7% July - 2020 |
Work in progress. |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 16.051 | 30 | 80 | 80 | 53.709 | 69.76 | 103.949 | 31% |
47% March - 2021 |
Work in progress.
P-II : Balance Funds.
Demand Rs: 40 M |
No Image |
| |||||||||||||||||||
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 16.051 | 30 | 80 | 80 | 53.709 | 69.76 | 103.949 | 31% |
47% February - 2021 |
Work in progress.
P-II : Balance Funds.
Demand Rs: 40 M |
No Image |
| |||||||||||||||||||
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 10 | 30 | 80 | 80 | 49.473 | 59.473 | 110 | 27% |
40% January - 2021 |
Work in progress.
P-II : Balance Funds.
Demand Rs: 40 M |
No Image |
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 16.051 | 30 | 80 | 80 | 72.029 | 88.08 | 103.949 | 31% |
59% May - 2021 |
Work in progress.
P-II : Balance Funds.
Demand Rs: 40 M |
No Image |
| |||||||||||||||||||
1580 (OG) |
190575-Upgradation & Strengthening of C&W roads in District Buner. |
Buner HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 16.051 | 30 | 80 | 80 | 72.029 | 88.08 | 103.949 | 31% |
59% April - 2021 |
Work in progress.
P-II : Balance Funds.
Demand Rs: 40 M |
No Image |
| |||||||||||||||||||
Pages : 1 |