Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 20 | 20 | 3.362 | 40.34 | 87.782 | 50% |
23% December - 2020 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 20 | 20 | 3.362 | 40.34 | 87.782 | 50% |
23% December - 2020 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 50 | 37.5 | 3.362 | 40.34 | 87.782 | 50% |
23% October - 2020 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 50 | 10 | 3.362 | 40.34 | 87.782 | 50% |
23% September - 2020 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 50 | 10 | 0 | 36.978 | 87.782 | 50% |
21% August - 2020 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 40.113 | 50 | 0 | 0 | 0 | 40.113 | 84.647 | 52% |
23% July - 2020 |
Work order issued. Section - 4 in process |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 5 | 5 | 5 | 41.978 | 87.782 | 50% |
24% May - 2021 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 5 | 5 | 5 | 41.978 | 87.782 | 50% |
24% April - 2021 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 5 | 5 | 3.362 | 40.34 | 87.782 | 50% |
23% March - 2021 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 5 | 5 | 3.362 | 40.34 | 87.782 | 50% |
23% February - 2021 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
1596 (OG) |
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km) |
Swat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.76 | 36.978 | 50 | 50 | 50 | 3.362 | 40.34 | 87.782 | 50% |
23% January - 2021 |
Work order issued. Section - 6 sent to DC for approval. |
No Image |
PK-83, Swat | |||||||||||||||||||
Pages : 1 |