Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II Approved for Rs. 10 M
LOA issued to GSK consultant |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II Approved for Rs. 10 M
LOA issued to GSK consultant |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-II Approved for Rs. 10 M . RFP floated |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II Approved for Rs. 10 M . RFP floated |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-II Approved for Rs. 10 M . RFP floated |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 210 | 0 | 10 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 244.67 | 0 | 10 | 5 | 5 | 3.418 | 3.418 | 234.67 | 4% |
1% May - 2021 |
Tender approval under process. |
No Image |
Scope of work:
| |||||||||||||||||||
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 244.67 | 0 | 10 | 10 | 0 | 0 | 0 | 234.67 | 4% |
- April - 2021 |
Tender approval under process. |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 244.67 | 0 | 10 | 10 | 0 | 0 | 0 | 234.67 | 4% |
- March - 2021 |
Tender approval under process. |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 244.67 | 0 | 10 | 10 | 0 | 0 | 0 | 234.67 | 4% |
- February - 2021 |
PC-II Approved for Rs. 10 M
LOA issued to GSK consultant |
No Image |
160 (New) |
200312-Construction of 60 Class rooms at Darul uloom Islamia including hall and Library at Aza Khel Bala Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 244.67 | 0 | 10 | 10 | 0 | 0 | 0 | 234.67 | 4% |
- January - 2021 |
PC-II Approved for Rs. 10 M
LOA issued to GSK consultant |
No Image |
160 (OG) |
150140-Establishment of Girls Primary cum Seondary School in one building at Qazi Killy Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.173 | 33.402 | 25 | 25 | 12.5 | 0 | 33.402 | 40.771 | 59% |
34% September - 2018 |
Land payment made. Site not H/O. |
No Image |
Qazi Killy Peshawar PK-01 | |||||||||||||||||||
160 (OG) |
150140-Establishment of Girls Primary cum Seondary School in one building at Qazi Killy Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.173 | 33.402 | 25 | 25 | 0 | 0 | 33.402 | 40.771 | 59% |
34% July - 2018 |
Land payment made. Site not H/O. |
No Image |
Qazi Killy Peshawar PK-01 | |||||||||||||||||||
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
160 (OG) |
141026-Continuous Capacity Development of Parent Teachers Councils (SBSE). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0.001 | 0 | 0.001 | 0.001 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
Pages : 1 |