Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 20 | 0 | 178.804 | 56.564 | 78% |
70% December - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 20 | 0 | 178.804 | 56.564 | 78% |
70% December - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 15 | 0 | 178.804 | 56.564 | 78% |
70% October - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 5 | 0 | 178.804 | 56.564 | 78% |
70% September - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 5 | 0 | 178.804 | 56.564 | 78% |
70% August - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress. |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 0 | 5 | 0 | 178.804 | 56.564 | 78% |
70% July - 2020 |
Original scope - 10 Km (PCC 14 ft wide) - complete |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 15 | 15 | 0 | 178.804 | 56.564 | 78% |
70% May - 2021 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 15 | 15 | 0 | 178.804 | 56.564 | 78% |
70% April - 2021 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 10 | 10 | 0 | 178.804 | 56.564 | 78% |
70% March - 2021 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 10 | 10 | 0 | 178.804 | 56.564 | 78% |
70% February - 2021 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
1621 (OG) |
100382-Construction of Sairay Kalkot to Thall Kumrat road, 10-km ,Dir Upper |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 255.368 | 178.804 | 20 | 20 | 20 | 0 | 178.804 | 56.564 | 78% |
70% January - 2021 |
Original scope - 10 Km (PCC 14 ft wide) - complete.
Revision in progress.
Snow Bound
TS submitted to CE |
No Image |
PK-92 Dir Upper (Km-1 to 10) | |||||||||||||||||||
Pages : 1 |