Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 42.307 | 285.554 | 37.609 | 90% |
75% December - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 42.307 | 285.554 | 37.609 | 90% |
75% December - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 25 | 25 | 268.247 | 37.609 | 90% |
70% October - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 25 | 25 | 268.247 | 37.609 | 90% |
70% September - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 25 | 0 | 243.247 | 37.609 | 90% |
64% August - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 0 | 25 | 0 | 243.247 | 37.609 | 90% |
64% July - 2020 |
Length 27 Km - cutting of 27 Km completed, WBM of |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 61.467 | 304.714 | 37.609 | 90% |
80% May - 2021 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 61.467 | 304.714 | 37.609 | 90% |
80% April - 2021 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 61.467 | 304.714 | 37.609 | 90% |
80% March - 2021 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 61.467 | 304.714 | 37.609 | 90% |
80% February - 2021 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||
1624 (OG) |
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 380.856 | 243.247 | 100 | 100 | 100 | 42.307 | 285.554 | 37.609 | 90% |
75% January - 2021 |
Length 27 Km - cutting of 27 Km completed, WBM in progress. |
No Image |
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km) | |||||||||||||||||||