Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 50 | 27.5 | 0 | 209.424 | 63.11 | 80% |
65% December - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 50 | 27.5 | 0 | 209.424 | 63.11 | 80% |
65% December - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 50 | 37.5 | 1 | 210.424 | 63.11 | 80% |
65% October - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 50 | 12.5 | 0 | 209.424 | 63.11 | 80% |
65% September - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 50 | 12.5 | 0 | 209.424 | 63.11 | 80% |
65% August - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 0 | 12.5 | 0 | 209.424 | 63.11 | 80% |
65% July - 2020 |
Length 210 m tr - 35/48 piles, 6/9 girder, left an |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 37.5 | 37.5 | 2.072 | 211.496 | 63.11 | 80% |
66% May - 2021 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 37.5 | 37.5 | 2.072 | 211.496 | 63.11 | 80% |
66% April - 2021 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 37.5 | 37.5 | 2.072 | 211.496 | 63.11 | 80% |
66% March - 2021 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 37.5 | 37.5 | 2.072 | 211.496 | 63.11 | 80% |
66% February - 2021 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
1638 (OG) |
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 322.534 | 209.424 | 50 | 27.5 | 27.5 | 0 | 209.424 | 63.11 | 80% |
65% January - 2021 |
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress. |
No Image |
Dassu Kohistan | |||||||||||||||||||
Pages : 1 |