Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 50 27.5 0 209.424 63.11 80% 65%
December - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 50 27.5 0 209.424 63.11 80% 65%
December - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 50 37.5 1 210.424 63.11 80% 65%
October - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 50 12.5 0 209.424 63.11 80% 65%
September - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 50 12.5 0 209.424 63.11 80% 65%
August - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 0 12.5 0 209.424 63.11 80% 65%
July - 2020
Length 210 m tr - 35/48 piles, 6/9 girder, left an
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 37.5 37.5 2.072 211.496 63.11 80% 66%
May - 2021
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 37.5 37.5 2.072 211.496 63.11 80% 66%
April - 2021
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 37.5 37.5 2.072 211.496 63.11 80% 66%
March - 2021
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 37.5 37.5 2.072 211.496 63.11 80% 66%
February - 2021
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.
No Image
Dassu Kohistan
1638
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 209.424 50 27.5 27.5 0 209.424 63.11 80% 65%
January - 2021
Length 210 m tr - 35/48 piles, 6/9 girder, left abutment completed. 20 piles of right side pier completed. Platform preparation for right side abutment in progress.