Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% December - 2020 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% December - 2020 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 15 | 6 | 51.1 | 34.9 | 65% |
51% October - 2020 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 5 | 2.9 | 48 | 34.9 | 65% |
48% September - 2020 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 5 | 1.05 | 46.15 | 34.9 | 65% |
46% August - 2020 |
Length 06-Km (2 Units)
Work in progress. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 0 | 5 | 0 | 45.1 | 34.9 | 65% |
45% July - 2020 |
Length 6 Km - Shingle road - Bar Paro (3 Km) - ear |
No Image |
1) Construction of shingle road Bar Paro (3 K | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% May - 2021 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% April - 2021 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% March - 2021 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 20 | 65.1 | 34.9 | 65% |
65% February - 2021 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
1639 (OG) |
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan. |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100 | 45.1 | 20 | 20 | 20 | 15 | 60.1 | 34.9 | 65% |
60% January - 2021 |
Length 06-Km (2 Units)
Work in progress?
1- 20 pile left side pile cap complete along with pier.
2-_6. girder completed. |
No Image |
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km) | |||||||||||||||||||
Pages : 1 |