Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
December - 2020
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
December - 2020
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 15 6 51.1 34.9 65% 51%
October - 2020
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 5 2.9 48 34.9 65% 48%
September - 2020
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 5 1.05 46.15 34.9 65% 46%
August - 2020
Length 06-Km (2 Units) Work in progress.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 0 5 0 45.1 34.9 65% 45%
July - 2020
Length 6 Km - Shingle road - Bar Paro (3 Km) - ear
No Image
1) Construction of shingle road Bar Paro (3 K
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
May - 2021
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
April - 2021
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
March - 2021
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 20 65.1 34.9 65% 65%
February - 2021
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1639
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 45.1 20 20 20 15 60.1 34.9 65% 60%
January - 2021
Length 06-Km (2 Units) Work in progress? 1- 20 pile left side pile cap complete along with pier. 2-_6. girder completed.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)