Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 29.168 77.504505 236.966 29% 23%
December - 2020
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 29.168 77.504505 236.966 29% 23%
December - 2020
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 37.5 10 58.336505 236.966 29% 17%
October - 2020
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 10 0 48.336505 236.966 29% 14%
September - 2020
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 10 0 48.336505 236.966 29% 14%
August - 2020
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 0 10 0 48.336505 236.966 29% 14%
July - 2020
8.725Km road - Earth work 6Km completed. Bridge
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 48.659 96.995505 236.966 29% 29%
May - 2021
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 40.658 88.994505 236.966 29% 27%
April - 2021
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 33.888 82.224505 236.966 29% 25%
March - 2021
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 33.888 82.224505 236.966 29% 25%
February - 2021
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram
1644
(OG)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram
Battagram
30-11--1 30-11--1 - 30-11--1 - 335.303 48.336505 50 50 50 33.888 82.224505 236.966 29% 25%
January - 2021
8.725Km road - Earth work 6Km completed. Bridge -pile testing in progress.
No Image
Battagram