Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
December - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.s
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
December - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.s
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 0 127.994 0 100% 100%
October - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.s
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 0 127.994 0 100% 100%
September - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 0 127.994 0 100% 100%
August - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 0 5 0 127.994 0 100% 100%
July - 2020
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
March - 2021
(A) Chorkalan Road. 1- Earth work Completed. (2) Structure Work in Progress. 3- B/Toped 3.60 Km Completed. (B) Jabbori Methal Kayan Road. 1- E/Work = Completed. (2) Structure Work in Progress. (3) B/Topped 3 Km Completed.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
February - 2021
(A) Chorkalan Road. 1- Earth work Completed. (2) Structure Work in Progress. 3- B/Toped 3.60 Km Completed. (B) Jabbori Methal Kayan Road. 1- E/Work = Completed. (2) Structure Work in Progress. (3) B/Topped 3 Km Completed.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
January - 2021
Length 7.6 Km - (a) Chor Kalan road 3.6 Km -completed. Completion : december 2020.s
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
May - 2021
1 Earth work Completed. (2) Structure Work in Progress. 3- B/Toped 3.60 Km Completed. (B) Jabbori Methal Kayan Road. Can be complted provided Rs. 9.6 as per TS 1- E/Work = Completed. (2) Structure Work in Progress. (3) B/Topped 3 Km Completed.
No Image
PK-56, Mansehra
1648
(OG)
140920-F/S, design and Construction of a) Chor Kalan road & b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 120 127.994 5 5 5 5 132.994 0 100% 100%
April - 2021
1 Earth work Completed. (2) Structure Work in Progress. 3- B/Toped 3.60 Km Completed. (B) Jabbori Methal Kayan Road. Can be complted provided Rs. 9.6 as per TS 1- E/Work = Completed. (2) Structure Work in Progress. (3) B/Topped 3 Km Completed.
No Image
PK-56, Mansehra
Pages : 1