Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 20.028 9.892 65.6306 0 100% 92%
December - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 20.028 9.892 65.6306 0 100% 92%
December - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 15.021 5.007 60.7456 0 100% 85%
October - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 5.007 5.007 60.7456 0 100% 85%
September - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 5.007 5.007 60.7456 0 100% 85%
August - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 0 5.007 0 55.7386 0 100% 78%
July - 2020
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 20.028 11.979 67.7176 0 100% 95%
March - 2021
05 Units 1. Earth Work Completed, Structure Work Completed, Road Work 1 Km Asphalt Completed, PCC shoulders & Site Drain in Progress." 2. Completed 3. Earth Work Completed Structure Work Completed Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 4. Earth Work Completed. Structure Work Completed. Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 5. Earth Work Completed Structure Work Completed. Road Work in Progress
No Image
1. Dhehgri to Mohar U/C Sawan Mera (1-Km). (PK-32)         
2. Ghazikot to Chameri U/C Nikka Pani (1 Km). (PK-33)         
3. Phulra to Matserian U/C Phulra (1 Km). (PK-32)         
4. Ratta Deppa to Chanial U/C Perhina (1 Km). (PK-32)         
5. Sehra Gali to Darband U/C Shanaya (1 Km) (PK-33)         
 
 
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 20.028 20.028 9.892 65.6306 0 100% 92%
February - 2021
05 Units 1. Earth Work Completed, Structure Work Completed, Road Work 1 Km Asphalt Completed, PCC shoulders & Site Drain in Progress." 2. Completed 3. Earth Work Completed Structure Work Completed Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 4. Earth Work Completed. Structure Work Completed. Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 5. Earth Work Completed Structure Work Completed. Road Work in Progress
No Image
1. Dhehgri to Mohar U/C Sawan Mera (1-Km). (PK-32)         
2. Ghazikot to Chameri U/C Nikka Pani (1 Km). (PK-33)         
3. Phulra to Matserian U/C Phulra (1 Km). (PK-32)         
4. Ratta Deppa to Chanial U/C Perhina (1 Km). (PK-32)         
5. Sehra Gali to Darband U/C Shanaya (1 Km) (PK-33)         
 
 
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 15.021 15.021 9.892 65.6306 0 100% 92%
January - 2021
5km- Earth work completed. 4-km Asphalt completed.
No Image
Mansehra
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 12.028 12.028 11.989 67.7276 0 100% 95%
May - 2021
05 Units 1. Earth Work Completed, Structure Work Completed, Road Work 1 Km Asphalt Completed, PCC shoulders & Site Drain in Progress." 2. Completed 3. Earth Work Completed Structure Work Completed Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 4. Earth Work Completed. Structure Work Completed. Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 5. Earth Work Completed Structure Work Completed. Road Work in Progress
No Image
1. Dhehgri to Mohar U/C Sawan Mera (1-Km). (PK-32)         
2. Ghazikot to Chameri U/C Nikka Pani (1 Km). (PK-33)         
3. Phulra to Matserian U/C Phulra (1 Km). (PK-32)         
4. Ratta Deppa to Chanial U/C Perhina (1 Km). (PK-32)         
5. Sehra Gali to Darband U/C Shanaya (1 Km) (PK-33)         
 
 
1652
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 71.292 55.7386 20.028 12.028 12.028 11.979 67.7176 0 100% 95%
April - 2021
05 Units 1. Earth Work Completed, Structure Work Completed, Road Work 1 Km Asphalt Completed, PCC shoulders & Site Drain in Progress." 2. Completed 3. Earth Work Completed Structure Work Completed Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 4. Earth Work Completed. Structure Work Completed. Road Work 1 Km Asphalt Completed. PCC shoulders & Site Drain in Progress. 5. Earth Work Completed Structure Work Completed. Road Work in Progress
No Image
1. Dhehgri to Mohar U/C Sawan Mera (1-Km). (PK-32)         
2. Ghazikot to Chameri U/C Nikka Pani (1 Km). (PK-33)         
3. Phulra to Matserian U/C Phulra (1 Km). (PK-32)         
4. Ratta Deppa to Chanial U/C Perhina (1 Km). (PK-32)         
5. Sehra Gali to Darband U/C Shanaya (1 Km) (PK-33)         
 
 
Pages : 1