Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 50 49 49 149.4 25% 25%
December - 2020
17 Units - PCC - Work in progress. Liability Rs. 25 M Demand - Rs 169 M.
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 50 49 49 149.4 25% 25%
December - 2020
17 Units - PCC - Work in progress. Liability Rs. 25 M Demand - Rs 169 M.
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 37.5 7.018 7.018 149.4 25% 4%
October - 2020
17 Units - PCC - Work in progress. Liability Rs. 25 M
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 7.143 7.018 7.018 149.4 25% 4%
September - 2020
17 Units - PCC - Work in progress. Liability Rs. 25 M
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 7.143 7.018 7.018 149.4 25% 4%
August - 2020
17 Units - PCC - Work in progress. Liability Rs. 25 M
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 0 7.143 0 0 149.4 25% -
July - 2020
Work order issued.
No Image
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 50 50 50 149.4 25% 25%
March - 2021
17 Units - Package 1 1. X-Drainange Work in Progress. 2. Not started 3. Structure Work in Progress 4. Drain Work in Progress. 5. PCC Work is in Progress. 6. Structure Work in Progress. 7. Earth Work, Structure Work & Dressing work is in Progress. 8. Structure Work Completed, Dressing Work is in Progress. 9. Drain is in Progress. Package 2 1. X-Drainage work in Progress. 2. Not started 3. Earth Work Completed, Structrue Work in Progress 4. Not started 5. Earth Work in Progress 6. Not started 7. PCC Work is in Progress. 8. Structure work is in Progress.
No Image
Package No. 1 (09 Nos roads)
1. Mungan Machi Pole Road (2 Km) (BT)         
2. Hathi Maira Road (1 Km) (BT)        
3. Gandian Lung Sharif&Hafeez Bandi Road (2.5 Km) (PCC)         
4. Panjab Chowk to Jail Road (1 Km) (BT)         
5. Reerh Road (1 Km) (PCC)       
6. Kanggar Maira Road (0.800 Km) (PCC)         
7. Sandesar Road (1 Km) (PCC)        
8. Darra Saleem Khan Road (1 Km) (PCC)         
9. Zafar Road to Panjab Chowk & Pakhwal Chowk up-to KKH (1.500 Km) (BT)         
Package 2
1. Pakhwal Road (1 Km) (BT)        
2. Dhangri Road (1 Km) (BT)       
3. Chitta Batta to Batair (2.4 Km) (PCC)        
4. Kharar Maira Road (2 Km) (BT8/PCC)        
5. Data to Bujjia Road (1 Km) (PCC)        
6. Hathi Maira to Hathi Bala Road (1.3 Km) (PCC)         
7. Lundian Road College Dorah (1.5 Km) (PCC)         
8. Phagla Road (1 Km) (PCC)        
 
 
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 50 49 49 149.4 25% 25%
February - 2021
17 Units - Package 1 1. X-Drainange Work in Progress. 2. Not started 3. Structure Work in Progress 4. Drain Work in Progress. 5. PCC Work is in Progress. 6. Structure Work in Progress. 7. Earth Work, Structure Work & Dressing work is in Progress. 8. Structure Work Completed, Dressing Work is in Progress. 9. Drain is in Progress. Package 2 1. X-Drainage work in Progress. 2. Not started 3. Earth Work Completed, Structrue Work in Progress 4. Not started 5. Earth Work in Progress 6. Not started 7. PCC Work is in Progress. 8. Structure work is in Progress.
No Image
Package No. 1 (09 Nos roads)
1. Mungan Machi Pole Road (2 Km) (BT)         
2. Hathi Maira Road (1 Km) (BT)        
3. Gandian Lung Sharif&Hafeez Bandi Road (2.5 Km) (PCC)         
4. Panjab Chowk to Jail Road (1 Km) (BT)         
5. Reerh Road (1 Km) (PCC)       
6. Kanggar Maira Road (0.800 Km) (PCC)         
7. Sandesar Road (1 Km) (PCC)        
8. Darra Saleem Khan Road (1 Km) (PCC)         
9. Zafar Road to Panjab Chowk & Pakhwal Chowk up-to KKH (1.500 Km) (BT)         
Package 2
1. Pakhwal Road (1 Km) (BT)        
2. Dhangri Road (1 Km) (BT)       
3. Chitta Batta to Batair (2.4 Km) (PCC)        
4. Kharar Maira Road (2 Km) (BT8/PCC)        
5. Data to Bujjia Road (1 Km) (PCC)        
6. Hathi Maira to Hathi Bala Road (1.3 Km) (PCC)         
7. Lundian Road College Dorah (1.5 Km) (PCC)         
8. Phagla Road (1 Km) (PCC)        
 
 
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 50 50 49 49 149.4 25% 25%
January - 2021
17 Units - PCC - Work in progress. Liability Rs. 25 M Demand - Rs 169 M.
No Image
Package No. 1 (09 Nos roads)
Package No. 2 (08 Nos roads)
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 81.2 81.2 80.082 80.082 149.4 25% 40%
May - 2021
17 Units - Package 1 1. X-Drainange Work in Progress. 2. Not started 3. Structure Work in Progress 4. Drain Work in Progress. 5. PCC Work is in Progress. 6. Structure Work in Progress. 7. Earth Work, Structure Work & Dressing work is in Progress. 8. Structure Work Completed, Dressing Work is in Progress. 9. Drain is in Progress. Package 2 1. X-Drainage work in Progress. 2. Not started 3. Earth Work Completed, Structrue Work in Progress 4. Not started 5. Earth Work in Progress 6. Not started 7. PCC Work is in Progress. 8. Structure work is in Progress.
No Image
Package No. 1 (09 Nos roads)
1. Mungan Machi Pole Road (2 Km) (BT)         
2. Hathi Maira Road (1 Km) (BT)        
3. Gandian Lung Sharif&Hafeez Bandi Road (2.5 Km) (PCC)         
4. Panjab Chowk to Jail Road (1 Km) (BT)         
5. Reerh Road (1 Km) (PCC)       
6. Kanggar Maira Road (0.800 Km) (PCC)         
7. Sandesar Road (1 Km) (PCC)        
8. Darra Saleem Khan Road (1 Km) (PCC)         
9. Zafar Road to Panjab Chowk & Pakhwal Chowk up-to KKH (1.500 Km) (BT)         
Package 2
1. Pakhwal Road (1 Km) (BT)        
2. Dhangri Road (1 Km) (BT)       
3. Chitta Batta to Batair (2.4 Km) (PCC)        
4. Kharar Maira Road (2 Km) (BT8/PCC)        
5. Data to Bujjia Road (1 Km) (PCC)        
6. Hathi Maira to Hathi Bala Road (1.3 Km) (PCC)         
7. Lundian Road College Dorah (1.5 Km) (PCC)         
8. Phagla Road (1 Km) (PCC)        
 
 
1654
(OG)
190585-Rehabilitation of Roads in, District Mansehra.
Mansehra
HW
30-11--1 30-11--1 - 30-11--1 - 199.4 0 50 81.2 81.2 80.082 80.082 149.4 25% 40%
April - 2021
17 Units - Package 1 1. X-Drainange Work in Progress. 2. Not started 3. Structure Work in Progress 4. Drain Work in Progress. 5. PCC Work is in Progress. 6. Structure Work in Progress. 7. Earth Work, Structure Work & Dressing work is in Progress. 8. Structure Work Completed, Dressing Work is in Progress. 9. Drain is in Progress. Package 2 1. X-Drainage work in Progress. 2. Not started 3. Earth Work Completed, Structrue Work in Progress 4. Not started 5. Earth Work in Progress 6. Not started 7. PCC Work is in Progress. 8. Structure work is in Progress.
No Image
Package No. 1 (09 Nos roads)
1. Mungan Machi Pole Road (2 Km) (BT)         
2. Hathi Maira Road (1 Km) (BT)        
3. Gandian Lung Sharif&Hafeez Bandi Road (2.5 Km) (PCC)         
4. Panjab Chowk to Jail Road (1 Km) (BT)         
5. Reerh Road (1 Km) (PCC)       
6. Kanggar Maira Road (0.800 Km) (PCC)         
7. Sandesar Road (1 Km) (PCC)        
8. Darra Saleem Khan Road (1 Km) (PCC)         
9. Zafar Road to Panjab Chowk & Pakhwal Chowk up-to KKH (1.500 Km) (BT)         
Package 2
1. Pakhwal Road (1 Km) (BT)        
2. Dhangri Road (1 Km) (BT)       
3. Chitta Batta to Batair (2.4 Km) (PCC)        
4. Kharar Maira Road (2 Km) (BT8/PCC)        
5. Data to Bujjia Road (1 Km) (PCC)        
6. Hathi Maira to Hathi Bala Road (1.3 Km) (PCC)         
7. Lundian Road College Dorah (1.5 Km) (PCC)         
8. Phagla Road (1 Km) (PCC)        
 
 