Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 50 50 285.792 114.208 71% 71%
December - 2020
Length 20 Km - 36 units, Completed = 15 Units Work in progress= 21 Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 50 50 285.792 114.208 71% 71%
December - 2020
Length 20 Km - 36 units, Completed = 15 Units Work in progress= 21 Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 37.5 37.5 273.292 114.208 71% 68%
October - 2020
Length 20 Km - 36 units, Completed = 15 Units Work in progress= 21 Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 12.5 12.5 248.292 114.208 71% 62%
September - 2020
Length 20 Km - 36 units, Completed = 15 Units Work in progress= 21 Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 12.5 12.5 248.292 114.208 71% 62%
August - 2020
Length 20 Km - all 22 units, all in progress. Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 0 12.5 0 235.792 114.208 71% 59%
July - 2020
Length 20 Km - all 22 units, all in progress. R
No Image
1) Construction of road from near Modern Publ
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 70.5 70.5 70.5 70.5 306.292 93.708 77% 77%
March - 2021
1. Completed 2. Completed 3. Completed 4. completed 5. Completed 6. Completed 7. 90% completed 8. Completed 9. PCC completed 10. 0.50 KM PCC completed 11. completed 12 Completed 13 70% Completed 14 60% Completed 15 1.90 KM PCC Completed 16 Completed 17 Completed 18 Completed 19 In progress 20 Completed 21 X-Drainage in progress 22 Work in progress 23 Structure work completed, road work in progress 24 E/work & Masonary work completed 25 X-Drainage in progress 26 E/work in progress 27 E/work completed. Masonary work 80% completed, road work in progress 28 Completed 29 PCC 70% completed 30 PCC road 80% completed S/work 100% completed 31 S/work 100%, PCC 60% 32 E/work: completed S/work 80% completed PCC 80% completed 33 Completed 34 X-Drainage completed PCC in progress 35 X-Drainage 60% Shoulder work completed PCC 80% 36 E/work: completed S/work 70% completed R/work in progress
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 70.5 70.5 70.5 70.5 306.292 93.708 77% 77%
February - 2021
1. Completed 2. Completed 3. Completed 4. completed 5. Completed 6. Completed 7. 90% completed 8. Completed 9. PCC completed 10. 0.50 KM PCC completed 11. completed 12 Completed 13 70% Completed 14 60% Completed 15 1.90 KM PCC Completed 16 Completed 17 Completed 18 Completed 19 In progress 20 Completed 21 X-Drainage in progress 22 Work in progress 23 Structure work completed, road work in progress 24 E/work & Masonary work completed 25 X-Drainage in progress 26 E/work in progress 27 E/work completed. Masonary work 80% completed, road work in progress 28 Completed 29 PCC 70% completed 30 PCC road 80% completed S/work 100% completed 31 S/work 100%, PCC 60% 32 E/work: completed S/work 80% completed PCC 80% completed 33 Completed 34 X-Drainage completed PCC in progress 35 X-Drainage 60% Shoulder work completed PCC 80% 36 E/work: completed S/work 70% completed R/work in progress
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 400 235.792 50 50 50 50 285.792 114.208 71% 71%
January - 2021
Length 20 Km - 36 units, Completed = 15 Units Work in progress= 21 Deamnd Rs. 40 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 400 0 50 70.5 70.5 70.5 0 0
May - 2021
1. Completed 2. Completed 3. Completed 4. completed 5. Completed 6. Completed 7. 90% completed 8. Completed 9. PCC completed 10. 0.50 KM PCC completed 11. completed 12 Completed 13 70% Completed 14 60% Completed 15 1.90 KM PCC Completed 16 Completed 17 Completed 18 Completed 19 In progress 20 Completed 21 X-Drainage in progress 22 Work in progress 23 Structure work completed, road work in progress 24 E/work & Masonary work completed 25 X-Drainage in progress 26 E/work in progress 27 E/work completed. Masonary work 80% completed, road work in progress 28 Completed 29 PCC 70% completed 30 PCC road 80% completed S/work 100% completed 31 S/work 100%, PCC 60% 32 E/work: completed S/work 80% completed PCC 80% completed 33 Completed 34 X-Drainage completed PCC in progress 35 X-Drainage 60% Shoulder work completed PCC 80% 36 E/work: completed S/work 70% completed R/work in progress demand Rs. 50 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1660
(OG)
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad.
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 400 0 50 70.5 70.5 70.5 0 0
April - 2021
1. Completed 2. Completed 3. Completed 4. completed 5. Completed 6. Completed 7. 90% completed 8. Completed 9. PCC completed 10. 0.50 KM PCC completed 11. completed 12 Completed 13 70% Completed 14 60% Completed 15 1.90 KM PCC Completed 16 Completed 17 Completed 18 Completed 19 In progress 20 Completed 21 X-Drainage in progress 22 Work in progress 23 Structure work completed, road work in progress 24 E/work & Masonary work completed 25 X-Drainage in progress 26 E/work in progress 27 E/work completed. Masonary work 80% completed, road work in progress 28 Completed 29 PCC 70% completed 30 PCC road 80% completed S/work 100% completed 31 S/work 100%, PCC 60% 32 E/work: completed S/work 80% completed PCC 80% completed 33 Completed 34 X-Drainage completed PCC in progress 35 X-Drainage 60% Shoulder work completed PCC 80% 36 E/work: completed S/work 70% completed R/work in progress demand Rs. 50 M
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
Pages : 1