Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 50 | 50 | 285.792 | 114.208 | 71% |
71% December - 2020 |
Length 20 Km - 36 units,
Completed = 15 Units
Work in progress= 21
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 50 | 50 | 285.792 | 114.208 | 71% |
71% December - 2020 |
Length 20 Km - 36 units,
Completed = 15 Units
Work in progress= 21
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 37.5 | 37.5 | 273.292 | 114.208 | 71% |
68% October - 2020 |
Length 20 Km - 36 units,
Completed = 15 Units
Work in progress= 21
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 12.5 | 12.5 | 248.292 | 114.208 | 71% |
62% September - 2020 |
Length 20 Km - 36 units,
Completed = 15 Units
Work in progress= 21
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 12.5 | 12.5 | 248.292 | 114.208 | 71% |
62% August - 2020 |
Length 20 Km - all 22 units, all in progress.
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 0 | 12.5 | 0 | 235.792 | 114.208 | 71% |
59% July - 2020 |
Length 20 Km - all 22 units, all in progress.
R |
No Image |
1) Construction of road from near Modern Publ | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 70.5 | 70.5 | 70.5 | 70.5 | 306.292 | 93.708 | 77% |
77% March - 2021 |
1. Completed
2. Completed
3. Completed
4. completed
5. Completed
6. Completed
7. 90% completed
8. Completed
9. PCC completed
10. 0.50 KM PCC completed
11. completed
12 Completed
13 70% Completed
14 60% Completed
15 1.90 KM PCC Completed
16 Completed
17 Completed
18 Completed
19 In progress
20 Completed
21 X-Drainage in progress
22 Work in progress
23 Structure work completed, road work in progress
24 E/work & Masonary work completed
25 X-Drainage in progress
26 E/work in progress
27 E/work completed.
Masonary work 80% completed, road work in progress
28 Completed
29 PCC 70% completed
30 PCC road 80% completed
S/work 100% completed
31
S/work 100%, PCC 60%
32 E/work: completed
S/work 80% completed
PCC 80% completed
33 Completed
34 X-Drainage completed
PCC in progress
35 X-Drainage 60%
Shoulder work completed
PCC 80%
36 E/work: completed
S/work 70% completed
R/work in progress |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 70.5 | 70.5 | 70.5 | 70.5 | 306.292 | 93.708 | 77% |
77% February - 2021 |
1. Completed
2. Completed
3. Completed
4. completed
5. Completed
6. Completed
7. 90% completed
8. Completed
9. PCC completed
10. 0.50 KM PCC completed
11. completed
12 Completed
13 70% Completed
14 60% Completed
15 1.90 KM PCC Completed
16 Completed
17 Completed
18 Completed
19 In progress
20 Completed
21 X-Drainage in progress
22 Work in progress
23 Structure work completed, road work in progress
24 E/work & Masonary work completed
25 X-Drainage in progress
26 E/work in progress
27 E/work completed.
Masonary work 80% completed, road work in progress
28 Completed
29 PCC 70% completed
30 PCC road 80% completed
S/work 100% completed
31
S/work 100%, PCC 60%
32 E/work: completed
S/work 80% completed
PCC 80% completed
33 Completed
34 X-Drainage completed
PCC in progress
35 X-Drainage 60%
Shoulder work completed
PCC 80%
36 E/work: completed
S/work 70% completed
R/work in progress |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 235.792 | 50 | 50 | 50 | 50 | 285.792 | 114.208 | 71% |
71% January - 2021 |
Length 20 Km - 36 units,
Completed = 15 Units
Work in progress= 21
Deamnd Rs. 40 M |
No Image |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 0 | 50 | 70.5 | 70.5 | 70.5 | 0 | 0 |
May - 2021 |
1. Completed
2. Completed
3. Completed
4. completed
5. Completed
6. Completed
7. 90% completed
8. Completed
9. PCC completed
10. 0.50 KM PCC completed
11. completed
12 Completed
13 70% Completed
14 60% Completed
15 1.90 KM PCC Completed
16 Completed
17 Completed
18 Completed
19 In progress
20 Completed
21 X-Drainage in progress
22 Work in progress
23 Structure work completed, road work in progress
24 E/work & Masonary work completed
25 X-Drainage in progress
26 E/work in progress
27 E/work completed.
Masonary work 80% completed, road work in progress
28 Completed
29 PCC 70% completed
30 PCC road 80% completed
S/work 100% completed
31
S/work 100%, PCC 60%
32 E/work: completed
S/work 80% completed
PCC 80% completed
33 Completed
34 X-Drainage completed
PCC in progress
35 X-Drainage 60%
Shoulder work completed
PCC 80%
36 E/work: completed
S/work 70% completed
R/work in progress
demand Rs. 50 M |
No Image | |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
1660 (OG) |
140981-Construction/ Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in Ucs Bandas Pir Khan, Mir Pure, Kakul, Shiekul Bandi, Nawanshehr, Keyal. Central Urban, Malik Pura & Ward 1 to 15 Cantt, Abbottabad. |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 0 | 50 | 70.5 | 70.5 | 70.5 | 0 | 0 |
April - 2021 |
1. Completed
2. Completed
3. Completed
4. completed
5. Completed
6. Completed
7. 90% completed
8. Completed
9. PCC completed
10. 0.50 KM PCC completed
11. completed
12 Completed
13 70% Completed
14 60% Completed
15 1.90 KM PCC Completed
16 Completed
17 Completed
18 Completed
19 In progress
20 Completed
21 X-Drainage in progress
22 Work in progress
23 Structure work completed, road work in progress
24 E/work & Masonary work completed
25 X-Drainage in progress
26 E/work in progress
27 E/work completed.
Masonary work 80% completed, road work in progress
28 Completed
29 PCC 70% completed
30 PCC road 80% completed
S/work 100% completed
31
S/work 100%, PCC 60%
32 E/work: completed
S/work 80% completed
PCC 80% completed
33 Completed
34 X-Drainage completed
PCC in progress
35 X-Drainage 60%
Shoulder work completed
PCC 80%
36 E/work: completed
S/work 70% completed
R/work in progress
demand Rs. 50 M |
No Image | |
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44 | |||||||||||||||||||
Pages : 1 |