Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
December - 2020
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
December - 2020
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 37.5 37.5 116.537 70.963 65% 58%
October - 2020
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 63.62 50 50 12.5 12.5 76.12 86.38 57% 38%
September - 2020
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 63.62 50 50 12.5 12.5 76.12 86.38 57% 38%
August - 2020
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 63.62 50 0 12.3 0 63.62 86.38 57% 32%
July - 2020
Length 13 Km - out of 5 units, all earth work in p
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
March - 2021
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
February - 2021
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
January - 2021
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 40 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
May - 2021
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 20 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47
1663
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 200 79.037 50 50 50 50 129.037 70.963 65% 65%
April - 2021
Length 13 Km - out of 5 units, all earth work in progress. Deamnd Rs. 20 M
No Image
1) Hajia Gali toChamnakaroad (2.5 Km) PK-47
2) Phumermar to Nagra Gali road (2.5 Km) PK-47
3) Guda Takia raod (2 Km) PK-47
4) Beesan Riala road (2.5 Km) PK-47
5) Sajikot Ghora road (2 Km) PK-47