Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 100 | 100 | 75 | 1105.758 | 2276.929 | 33% |
32% December - 2020 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M] |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 100 | 100 | 75 | 1105.758 | 2276.929 | 33% |
32% December - 2020 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M] |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 100 | 75 | 25 | 1055.758 | 2276.929 | 33% |
31% October - 2020 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Land Compensation Rs. 1000 M
Deamnd Rs. 1200 M |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1273.7 | 100 | 100 | 25 | 25 | 1298.7 | 2033.987 | 40% |
38% September - 2020 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Land Compensation Rs. 1000 M
Deamnd Rs. 1200 M |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1273.7 | 100 | 100 | 25 | 25 | 1298.7 | 2033.987 | 40% |
38% August - 2020 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Land Compensation Rs. 1000 M
Deamnd Rs. 1200 M |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1273.7 | 100 | 0 | 25 | 0 | 1273.7 | 2033.987 | 40% |
37% July - 2020 |
16 Km - 12 km WBM in progress. 4 km Earth work in |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 300 | 300 | 219.104 | 1249.862 | 2276.929 | 33% |
37% March - 2021 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M] |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 300 | 300 | 219.104 | 1249.862 | 2276.929 | 33% |
37% February - 2021 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M] |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 100 | 100 | 75 | 1105.758 | 2276.929 | 33% |
32% January - 2021 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M] |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 397 | 397 | 388.455 | 1419.213 | 2276.929 | 33% |
42% May - 2021 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M]
Demand Rs: 1 B |
No Image |
Abbottabad | |||||||||||||||||||
1667 (OG) |
160628-F/S, Design and Construction & Supervision of bypass road from Ayub Bridge Havellian (N-35) to Dhamtour at Abbotabad (18.325 Km) |
Abbottabad HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3407.687 | 1030.758 | 100 | 397 | 397 | 388.455 | 1419.213 | 2276.929 | 33% |
42% April - 2021 |
(FWO )
17.7 Km - 12 km WBM in progress. 4 km Earth work in progress
Total Demand: Rs 2300 M.
[Land Compenstn Rs.1000 M
For Work Rs. 1300 M]
Demand Rs: 1 B |
No Image |
Abbottabad | |||||||||||||||||||
Pages : 1 |