Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 10 10 10 240 4% 4%
December - 2020
11/33 Unirts work order issued. Demand Rs. 100 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 10 10 10 240 4% 4%
December - 2020
11/33 Unirts work order issued. Demand Rs. 100 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 7.5 1.429 1.429 240 4% 1%
October - 2020
11/33 Unirts work order issued. Demand Rs. 8.75 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 2.25 1.429 1.429 240 4% 1%
September - 2020
11/33 Unirts work order issued. Demand Rs. 8.75 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 1.429 0 0 240 4% -
August - 2020
11/33 Unirts work order issued.
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 0 1.429 0 0 240 4% -
July - 2020
11/33 Unirts work order issued.
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 16 16 16 16 240 4% 6%
March - 2021
11/33 Unirts work order issued. Demand Rs. 100 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 16 16 16 16 240 4% 6%
February - 2021
11/33 Unirts work order issued. Demand Rs. 100 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 10 10 10 10 240 4% 4%
January - 2021
11/33 Unirts work order issued. Demand Rs. 100 M
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
HW
30-11--1 30-11--1 - 30-11--1 - 250 0 10 21 21 21 21 240 4% 8%
May - 2021
11/33 Unirts work order issued.
No Image
1682
(OG)
190372-Construction of Interrnal Roads in the Entire UCs of District Haripur.
Haripur
HW
30-11--1 30-11--1 - 30-11--1 - 250 0 10 21 21 21 21 240 4% 8%
April - 2021
11/33 Unirts work order issued.
No Image
Pages : 1