Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
December - 2020
Length 4 Km - completed Summary approvced for change of scope from BT to Shingle. Revised PC-I Rs: 99.785 Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
December - 2020
Length 4 Km - completed Summary approvced for change of scope from BT to Shingle. Revised PC-I Rs: 99.785 Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 70.961 28.824 28.824 21.618 0 70.961 0 100% 71%
October - 2020
Length 4 Km - earth work 90%, structure work 65% in prtogress Summary under process for change of scope from BT to Shingle. Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 70.961 28.824 28.824 14.412 0 70.961 0 100% 71%
September - 2020
Length 4 Km - earth work 90%, structure work 65% in prtogress Summary under process for change of scope from TSt to BT. Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 70.961 28.824 28.824 14.412 0 70.961 0 100% 71%
August - 2020
Length 4 Km - earth work 90%, structure work 65% in prtogress Summary under process for change of scope from TSt to BT. Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 70.961 28.824 0 14.412 0 70.961 0 100% 71%
July - 2020
Length 4 Km - earth work 90%, structure work 65% c
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
May - 2021
Length 4 Km -Original Scope Complete. Revised DCE approved in March 2021. Cannot be complted in CFY. Work Started on new alignment.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
April - 2021
Length 4 Km -Original Scope Complete. Revised DCE approved in March 2021. Cannot be complted in CFY. Work Started on new alignment.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
March - 2021
Length 4 Km - completed Summary approvced for change of scope from BT to Shingle. Revised PC-I Rs: 99.785 Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
February - 2021
Length 4 Km - completed Summary approvced for change of scope from BT to Shingle. Revised PC-I Rs: 99.785 Completion : June-2021.
No Image
Tor Ghar
1689
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar
Tor Ghar
30-11--1 30-11--1 - 30-11--1 - 99.785 44.35 28.824 28.824 28.824 0 44.35 26.611 73% 44%
January - 2021
Length 4 Km - completed Summary approvced for change of scope from BT to Shingle. Revised PC-I Rs: 99.785 Completion : June-2021.
No Image
Tor Ghar