Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 20 20 0 0 567.768 3% -
December - 2020
Work order issued. ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 20 20 0 0 567.768 3% -
December - 2020
Work order issued. ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 20 10 0 0 567.768 3% -
October - 2020
Procurement in proress.
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 20 0 0 0 567.768 3% -
September - 2020
Procurement in proress.
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 Line Deptt 587.768 0 20 20 0 0 0 567.768 3% -
August - 2020
Procurement in proress.
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 Line Deptt 587.768 0 20 0 0 0 0 567.768 3% -
July - 2020
Procurement in proress.
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 10 10 10 10 567.768 3% 2%
May - 2021
E/Work Tranches/Excvation of existing road in progress ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 10 10 10 10 567.768 3% 2%
April - 2021
E/Work Tranches/Excvation of existing road in progress ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 10 10 0 0 567.768 3% -
March - 2021
E/Work Tranches/Excvation of existing road in progress ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 10 10 0 0 567.768 3% -
February - 2021
E/Work Tranches/Excvation of existing road in progress ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
1692
(New)
200006-Repair and Rehabilittion of road between Banda Daud Shaha (TERRI Chowk) & Gurguri District Karak (38-Km)
Karak
30-11--1 30-11--1 - 30-11--1 - 587.768 0 20 10 10 0 0 567.768 3% -
January - 2021
Work order issued. ( MOL Share : 400 M ( ADP : 187.76 M )
No Image
Pages : 1